Joint School District of Beloit
Beloit City Council Meeting
Monday, February 24, 2014
5 primary buildings◦ Converse◦ Robinson◦ Hackett◦ Todd◦ Merrill
The Swimming Pool
Completed Projects
Cunningham Intermediate School
Gaston Primary School
Fitness Center
McNeel
Aldrich
Memorial
Projects in Progress
Fran FruzenIntermediate School
Update as of January 29, 2014
North-East Exterior Front ViewNorth-West Exterior Front View
Architect Renderings
West Exterior ViewSouth-West Exterior View
Architect Renderings
South-East Exterior ViewNorth-East Exterior View
Architect Renderings
Site Layout
Sidewalk
4-6 Entrance
7/8 Entrance
Plaza
DumpsterEnclosure Hard
SurfacePlay
Storage Building16 x 16
Site Plan
First FloorFirst Floor= 70,242 SFSecond Floor= 30,214 SFTotal= 100,456 SF
Second Floor
First Floor= 70,242 SFSecond Floor= 30,214 SFTotal= 100,456 SF
Site Clearing/Demolition: March/April 2014
Bid Date: April 17, 2014
Construction Start: April 30, 2014
Construction Complete: July 31, 2015
Timeline
Tennis CourtsBig Field between 6th and 4th
ScoreboardsNew Storage for FootballPropane Tank outside of Swimming Pool
Athletic Fields