MESYUARAT PEGAWAI KANAN JKR MALAYSIA 2013
KUALA TERENGGANU
PENANG SECOND BRIDGE
‘THE CHALLENGES, SUCCESS CRITERIA AND
LESSONS LEARNT’
28 MAY 2013
JAMBATAN KEDUA SDN BHD.
LEMBAGA LEBUHRAYA MALAYSIA
KERAJAAN MALAYSIA
Presented by: Dato’ Ir. Dr. Ismail bin Mohamed TaibManaging Director, Jambatan Kedua Sdn Bhd
content
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
INTRODUCTION
ISSUES AND CHALLENGES
SUCCESS CRITERIAS
LESSONS LEARNT
CONCLUSION
Jambatan Kedua Sdn Bhd (JKSB), a wholly-owned company of the Ministry ofFinance, Incorporated (MoF Inc.), was appointed as the concessionaire for theSecond Penang Bridge Project in August 2008.
JKSB is responsible for the design, construction, management, operation andmaintenance of the bridge.
The Second Penang Bridge which connects Batu Kawan on the Mainland and BatuMaung on the Island when completed in September 2013 will be the longest inSouth-East Asia with the total length over water of 16.9km. The project overalllength is 24km with estimated construction cost of RM 4.5 billion.
introduction
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
main navigation span
Fireworks show during final closure of mid span ceremony on 20th April 2013
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
9+000.
10+000.
11+000.
12+000. 13+000. 14+000.
15+000.
16+000.
0.
1+000. 2+000.
3+000. 4+000. 5+000. 6+000.
7+000.
8+000.
17+000.
18+000.
19+000.
20+000.
21+000.
22+000.
23+000.
PULAU
JEREJAK
PULAU
AMAN
PENANG
ISLAND
(Batu Maung)
NAVIGATIONAL
SPAN
MAIN LAND
(Batu Kawan)
Existing Penang Bridge Legend:Existing Penang Bridge
North South Expressway (PLUS)
Package 1&2
Package 3
Marine Bridge
Land Expressway8.4 km
Second Penang Bridge
project alignment
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
PLAZA TOL PB2X
PLAZA TOL PLUS
LEBUHRAYA UTARA
SELATAN
PERSIMPANGAN
BATU KAWAN
PERSIMPANGAN
CLOVERLEAF
BATU KAWAN
SECOND PENANG
BRIDGE
EXISTING
PENANG BRIDGE
project alignment (view from batu kawan)
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
governance structure chart of jksb
SHAREHOLDER
( MINISTRY OF FINANCE)
BOARD TENDER
COMMITTEE
BOARD OF DIRECTORS
(CHAIRMAN: TAN SRI DR SULAIMAN MAHBOB)
BOARD AUDIT, RISK &
GOVERNANCE
COMMITTEE
NOMINATION &
REMUNERATION
COMMITTEE
BOARD FINANCE &
TECHNICAL COMMITTEE
MANAGING DIRECTORDATO’ IR. DR. ISMAIL
MOHAMED TAIB
TENDER MANAGEMENT
COMMITTEE
FINANCIAL TECHNICAL
COMMITTEE
OPERATING DIVISIONS
INTERNAL AUDIT
MANAGEMENT RISK
COMMITTEE
ENTERPRISE RISK
ASSESSMENT
CLAIM CONSULTANT
ISO ACCREDITION
CHIEF OPERATING OFFICERMEJAR (B) IR MOHD ASHARI ALIAS
CONSTRUCTION DIRECTORIR HAMIZOL NGAH
CHIEF FINANCIAL OFFICERDARWIS ABDUL RASAK
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
Project Organization Chart
TN Synergy S/BPa’ Wan Teh S/B
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
Design &
Build
Package 3B,3C,3D & 3G
Conventional Contract
Package 1 : Main Navigation Span &
Substructure & Foundation Works for
Approach Spans.
Package 2: Superstructure Works of
Approach Spans.
Package 3A:
Conventional
Contract
Package 1, 2, 3E & 3F
Design & Build
Integrated Toll System
work packages diagram
Summary of Progress –2 MAY 2013 (Rev. No. 04)
PAKE
JDESCRIPTION CONTRACTOR
COST
(RM
MIL.)
START
JKSB
TARGET
FINISH
PHYSICAL
PROGRESS %
SCH % ACT %
1
Main Navigation Span And
Substructure And Foundation
Works For Approach Spans
CHEC Construction
(M) Sdn Bhd2,200 8 Nov 08 24-Jul-13 99.21 99.17
2Superstructure Works of
Approach SpansUEM Builders Bhd 1,550 8 Jun 09 8-Sep-13 94.46 94.53
3A Batu Maung InterchangeCergas Murni Sdn
Bhd152.7 19 May 10 30-Jun-13 84.28 86.60
3B Batu Kawan ExpresswaysIJM Construction
Sdn Bhd349.9 28 Jun 10 8-Sep-13 76.87 82.10
3CBatu Kawan Trumpet
InterchangeHRA Teguh Sdn Bhd 67.3 19 May 10 30-Apr-13 76.69 68.94
3D Toll Plaza And Related Works Pa’ Wan Teh Sdn Bhd 79.8 15-Nov-11 15-Jul-13 52.82 28.95
3E Toll Collection SystemTERAS Teknologi
Sdn Bhd14.97 01-Jun-12
31-Aug-
1342.08 34.00
3FTraffic Control An
Surveillance System
Itramas Technology
Sdn Bhd19.8 26-Jun-12 25 Jul 13 55.74 55.26
3G M&E Installation WorksTN SYNERGY Sdn
Bhd13.4 26-Sept-12 30 Jul 13 64.20 70.68
Total4.5
billion8 Nov 08 8 Sept 13
94.06 94.29
Var 0.23
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
In the feasibility study conducted in 2002, the following alternative alignments wereconsidered:
i. The Northern Route (highest IRR)
ii. The Mid-Channel Route
iii. The Southern Route
• The alignment of the Southern route was chosen as to promote socio-economics development in the south that would provide a balanceddevelopment across Penang state.
The Southern Route
background
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
• The Government of Malaysia offered the privatisation of the Second Penang Bridgeto UEM Group Berhad in 2006. The ground breaking ceremony was performed on12 November 2006 by the fifth Prime Minister of Malaysia, Tun Abdullah AhmadBadawi.
• A joint venture between UEMC (a subsidiary of UEM Group) was formed with ChinaHarbour Engineering Company Ltd (CHEC) to execute the Project. MOA with ChinaExim Bank was later signed for the loan amount of USD800 Million.
• On 29 August 2008, the Government has revoked the offer to UEM Group Berhaddue to UEM and CHEC could not finalize the apportionment of jobs and cost.
• Subsequently, Jambatan Kedua Sdn Bhd (JKSB) a company of the Ministry ofFinance Incorporated (MoF Inc.), was appointed as the concessionaire for theSecond Penang Bridge Project.
BACKGROUND
1. Design
o During initial stage of construction
• No design calculations.
• No detail & construction drawings available.
• CHEC has completed 10% of the piling works as of April 2009.
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
ISSUES AND CHALLENGES FACED IN THE PACKAGE 1 & 2
• Perunding Zaaba Sdn.Bhd. was initially appointed as the IndependentChecking Engineer (ICE) on 20 April 2009.
• However, the service was eventually terminated and replaced by ArupJururunding Sdn. Bhd. on 27 January 2010 for Package 1 and 2.
• Minconsult was appointed as the Independent Checking Engineer forPackage 3.
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
ISSUES AND CHALLENGES FACED IN THE PACKAGE 1 & 2
ISSUES AND CHALLENGES FACED IN THE PACKAGE 1 & 2
o Ship Impact Requirement
• In the Employer’s Requirements (ER); the minimum collision force at anybridge pier is 6.24 MN based on fully loaded barge with SBG (in accordancewith AASHTO LRFD). However a minimum collision force of 1 MN withempty barge is adopted in CHEC’s Design Brief.
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
o 2500 Years Earthquake Event.
• The Employer’s Requirement (ER) requires no damage criteria for a 500 yearsreturn period. In addition to this, a requirement of ‘no collapse’ criteria forthe most credible earthquake (2500 years return period) was also introduced.First Penang Bridge was design on a similar requirement.
• Based on ICE’s comments on the detail design, spun piles at the approachbridge of Package 1 could only cater for the 500 years return periodearthquake. No plastic hinge forms as required for ‘no collapse’ criteria of2500 years return period.
ISSUES AND CHALLENGES FACED IN THE PACKAGE 1 & 2
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
o Durability Requirement
• JKSB requires the durability requirements based on the latest EurocodesBS EN 1992-1-1:2004 and for high performance concrete: RCPT shall beless than 800 Coulombs for 56 days. CHEC claimed that the requirementsare deemed as additional requirements as design are based on BS 5400.
o 6 Span and 5 Span Module
• JKSB adopted the 6-span module / 5 span module based on CHEC’s designfor the Approach Span Bridges instead of 15-span module proposed byUEMB.
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
ISSUES AND CHALLENGES FACED IN THE PACKAGE 1 & 2
o Notional Lanes
• CHEC has designed the Main Navigation Span (cable stay bridge)where the loading is based on 3 notional lanes with New JerseyBarrier (NJB) a divider for motorcycle lane is consideredpermanent.
• JKSB maintains that the practice in Malaysia is to design the full deck for 4 notional lanes with the NJB as a removal structure.
ISSUES AND CHALLENGES FACED IN THE PACKAGE 1 & 2
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
o Pilecap/Pier• Hairline cracks appeared in all Package 1 piers due to Package 2 SBG
launching works and eccentricity of launching gantry legs. Package 1 pierdesign consider no eccentricity.
o Dry Joints or Glued Joints for SBG prestressing tendon• UEMB had adopted external tendon in their original proposal with dry joint.
However, JKSB highlighted that for marine condition the standard practice isto adopt the glued joint.
o Change of Mechanical Pot Bearings to High Damping Rubber Bearings.• In order to cater for the 2500 years period earthquake with ‘no collapse’
criteria for Package 1 piles, JKSB decided to adopt High Damping RubberBearings in lieu of Mechanical Pot Bearings for Package 2.
Gluing works in progress
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
ISSUES AND CHALLENGES FACED IN THE PACKAGE 1 & 2
2. Contract
o Advanced Payment
• RM330 million advance payment requested by CHEC exceeds the TreasuryGuidelines of either RM10 million or 25% of the contract sum (whichever islower). National Audit Department upon auditing in January 2009 statedthat special approval needed from MOF for the payment.
o Lump Sum Item
• Cable stay works was issued as a lump sum item with only 6 preliminarydrawings available.
o Variation of Prices (VOP) Basic Price
• JKSB have fixed the Variation of Prices (VOP) for the three materials only i.ecement, steel and diesel. CHEC proposed to include other steel basedmaterials for VOP.
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
ISSUES AND CHALLENGES FACED IN THE PACKAGE 1 & 2
o CHEC’s Contract Document
• CHEC has submitted the Contract Document Proposal based on FIDICConditions of Contract for EPC/Turnkey Projects. However, JKSB requiresthe contract based on PWD Form DB. (Rev. 2007).
o Late Site Possesion
• Handing over of site at Batu Kawan to CHEC was late by 5.5 months dueto delay in settlement of payment issues to local fishermen and cocklesbreeders.
Compensation amounting RM6.6 million
to fishermen and cockle breeders was
made on 24 Oct 2011
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
ISSUES AND CHALLENGES FACED IN THE PACKAGE 1 & 2
3. Construction
o Interfacing works with Package 2
• Blockage and barge collision incidents occurred during the disposal ofmud by Package 2 subcontractor due to commercial dispute withPackage 1 subcontractors.
• The use of main dredged channel was required by Department ofEnvironmental (DoE).
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
Article from Guangming
Daily dated 22nd Sept 2009
ISSUES AND CHALLENGES FACED IN THE PACKAGE 1 & 2
o Erection of SBG at interface Pier 292, Pier 0, Pier 27, Pier 24.
• There was a constraint and timing factor where the erection of SBG has to becompleted prior to launching of beams and side spans of cable stayed bridgeconstruction by Package 3B & 3A and Package 1 contractors.
• If the launching of beams or side spans construction is carried out earlier thanSBG launching, prestressing works of the SBG has to be carried out at 3m abovethe deck level. This will pose a very high risk in terms of safety.
• Similarly, for Pier 24 and 27 where the pier height is 28m above sea level and atslope position, the launching of SBG will be extremely dangerous.
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
ISSUES AND CHALLENGES FACED IN THE PACKAGE 1 & 2
o Land Access from Batu Kawan to the Approach Span (Marine bridge)
UEMB has requested to have an early land access from Batu Kawan to ApproachSpan as to expedite the finishing works. However, there were several issues to beresolved by Package 1 as follows:
• Waste Disposal RouteThere was an existing waste disposal route which passed through Pier 272 to279. The State Government requested that the route is to be maintained untilMay 2011 when the Pulau Burung disposal ramp completed.
• Bored Pile ConstructionFrom Pier 283 to Pier 292, the water is shallow and muddy thus bargemovement is not possible for driving spun piles. The bored pile design adoptedwould require longer period for construction.
• As for Package 3B Land BridgePart of the land access to the marine bridge was theconstruction of 160m land bridge and also the 200mapproach access. Since Package 3B had not beenawarded, the early land access can be onlymaterialise in January 2011.
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
ISSUES AND CHALLENGES FACED IN THE PACKAGE 1 & 2
o Spun Piles - Short length• JKSB was concerned that there were groups of piles at Pier P170, P180, P181 and
P183 where the piles driven length were shorter by more than 10m from thedesigned length.
o Bored Piles• Sonic Logging & Class II and III defects
Based on the result, the Class III defects were detected at 30m to 60m depthat various piles needs to be repaired & retested.
• Failed test pile failed at less than half design capacity. At Main Span, 2.0mdiameter and 100m length bored piles needs to be socketed 5m in rock.
o Spun Piles Cracked• Total of 12 piles cracked for the month of July 2010 and stop work order was given
after the 11th pile cracked. Concrete spalling appeared at top of the pile due toheavy driving.
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
ISSUES AND CHALLENGES FACED IN THE PACKAGE 1 & 2
P24 P25 P26 P27
Installed 11/12 21/21 21/21 12/12
CSL carried out 6/12 21/22 21(22) 12/12
Class 1 4 15 15 10 10 8
Class 2 2 2 3 10 11 3
Class 3 0 1 0 0 0 1
Class 4 0 3 3 1 0 0
Def
ect
ive
*red color represent after remedial work
o Sequence of Pier Works and SBG Launching
• Under the Employer’s Requirement, the sequence of pier construction is asbelow:
CHEC’s Sequence of Pier Works
GROUP PIER
Group 1 Pier 178 to 282
Group 2 Pier 46 to 28
Group 3 Pier 47 to 144
Group 4 Pier 283 to 292
Group 5 Pier 0 to 23
Group 6 Pier 145 to 177
Group 7 Pier 24 to 27
SBG Launching SequenceP0
P27
P292
P24
P46
P144P177
P282
CHEC’s Sequence of Pier Works
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
ISSUES AND CHALLENGES FACED IN THE PACKAGE 1 & 2
UEMB’s SBG Launching Proposal
GANTRY PIER
LG1 & LG2 Pier 267 to Pier 117
Pier 267 to Pier 292
LG3 & LG4 Pier 117 to Pier 27
Pier 0 to Pier 24
o Sequence of Pier Works and SBG Launching (continue)
• However UEMB had submitted the new SBG launching sequence tofacilitate early land access and to expedite the finishing works.
SBG Launching Sequence
P1
53
P2
67
P0
P2
7
P2
92
P2
4
P1
17
LG1 & LG 2
SBG Launching Sequence
P15
3
P26
7
P0
P27
P29
2
P24
P11
7
LG3 & LG 4
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
ISSUES AND CHALLENGES FACED IN THE PACKAGE 1 & 2
o Dredging of Main Channel and Maintenance Dredging Works by Package 1 Contractor
• The dredged channel was purely to facilitate CHEC’s foundation and pier works.However, it did not consider the Package 2 SBG erection works.
ISSUES AND CHALLENGES FACED IN THE PACKAGE 1 & 2
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
• The maintenance dredging works by Package 1 Contractor would be ceased afterthe last pier is completed in October 2012 while the SBG erection would continueuntil May 2013.
• The SBG delivery by barge maybe disrupted if siltation rate is high as the draftclearance for the barge need to be maintained at -3.5m ACD.
During early construction of the project, JKSB has :
o Minimal manpower
Chief Executive Officer - 1 Chief Operating Officer - 1 Senior Manager - 2 Chief Financial Officer - 1
o Limited office equipment.
o Proposal for the Consultant Project Management Team was rejected by Board ofDirectors. JKSB was directed to set up own Project Team.
o RM80 million budget approved but only RM50 million was given to JKSB by MOFfor operation during 5 years construction period.
ISSUES AND CHALLENGES FACED BY JKSB
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
• Appointment of consultant for Package 3 Land Expressway not formalized.
• Discrepancies on the land acquisition cost between Valuation and Property ServicesDepartment and Penang State Government.
• Comparative assessment made by the Valuation and Property Services Departmentof MOF (JPPH) and State Government is tabulated as follows:
ISSUES AND CHALLENGES FACED BY JKSB
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
• RM500 million Bridging Facility from Bank Pembangunan needs to be taken forPackage 1. Further payment only can be made after execution of the formalContract Agreement with China Exim Bank and the Concessionaire Agreementwith LLM. Package 1 claimed delay due to the late finalization of the ContractDocument.
• Delay finalizations of financing requirements of PB2X.
• As of December 2009, the actual physical progress of works is 8.65%compared to schedule physical progress of 39.7%. This was due tocontractual, design and construction issues.
ISSUES AND CHALLENGES FACED BY JKSB
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
Business &
Organization
Management
Share-
holders
Board
SUCCESS CRITERIA
1. BOARD PLAY A CENTRAL ROLE TO DRIVE GOVERNANCE AND PERFORMANCE.
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
Structure
STRUCTURE
Culture
Policies & Procedures
Leadership &Talent
OrganisationalConfiguration
2. THE LEVEL FOR ACHIEVING WORLD - CLASS RESULTS…
Business Results
Process
SUCCESS CRITERIA
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
vi. Persuade, inspire and motivate others to follow you
ii. Foster innovation
i. Set and achieve business goals
iv. Set priorities and focus on key tasks
iii. Solve problem and make decisions
vii. Perform and get result
v. Set high standards and lead byexample
Leadership:Seven responsibilities of leadership (extract from
“ How the Best Leaders Lead” by Brian Tracy)
SUCCESS CRITERIA
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
• The Design & Build contract implemented in the Second Penang Bridge Project, provides the following advantages:
Singular Responsibility concept Better Quality of product Time Saving for the project Improved Risk Management
Lessons learnt
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
• Independent Checking Engineer (ICE) site audit:
Conducted once every 2 months to ensure the quality of the construction meets the international standard specifications.
LESSONS LEARNT
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
LESSONS LEARNT
• Penalty system
A well balanced training/ penalty/ award system is utilized to keep allmanagement staff and contractors up to date with the Quality and HSEstandards to ensure their compliance.
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
• INTERNATIONAL GREEN APPLE AWARDSFOR THE BUILT ENVIRONMENT & ARCHITECTURAL HERITAGE 2013
LESSONS LEARNT
• Innovative High Dumping Rubber Bearing (HDRB)
The design of the HDRB is by Tun Abdul Razak Research Centre (TARRC), a laboratory of the Malaysian Rubber Board (MRB) and manufactured locally.
Second Penang Bridge is the longest bridge in the world using HDRB.
HDRB at Package 2
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
LESSONS LEARNT
• Settlement criteria 50mm in 20years
• 100% primary consolidation (according to Asoka Plot)
For minimal maintenance requirements JKSB hasreviewed the settlement criteria of the surcharge from100mm in 5 years to 50mm in 20 years with minimaltime and cost penalty.
Prefabricated Vertical Drain (PVD)To ensure ‘no settlement’ criteria is complied,buckling test for PVD was carried out at PSB Lab inSingapore and subsequently to National University ofSingapore to show that the results complement thecompliance test.
Stone columnLoad test that was carried out all failed to complywith the specification criteria. Consultant wasdirected to back analyze their design and ensure thatno sliding failure during construction and nosettlement after completion occurs.
Overall view of the Trumpet
Interchange
Plate Bearing of Group 4 Column at
CH 23300, M001PVD installation Sonic logger
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
LESSONS LEARNT
• Design & Built for relocation of services
Under Package 3C contract, the scope of relocation of TNB Pylon wasspecified as Design and Built item. However, in Package 3A contract, therelocation of services is specified as provisional items.
Package 3C contractor is responsible for design, obtaining approval fromauthorities and construction within time and cost. The works is successfullycompleted on time. Package 3A contractor has claimed on the additionalworks and delays occurred due to authorities approval.
TNB Pylon relocation
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
LESSONS LEARNT
• Design for ease of construction compared with minimum material cost.
DESIGN CRITERIA PACKAGE 1 PACKAGE 3A
Piling Design The pile was designed in a circularposition which make it easier forpiling operation. Requires lessmovement of piling barge.
The pile was designed in arectangular position whichrequires piling barge movement.
Pilecap Design Twin Circular Pilecap. Proximity ofpilecap make it easier to construct.The first layer of pilecap was used asa permanent base of formwork.Precast shell act as a permanentside formwork.
Single Pilecap make it longertime to construct and extraformworks used.
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
• UEMB SBG’s quality problem due to minimum weight design.
Excessive blow holes at surface
Rebar exposed at the haunch area
Honeycombing at surface
LESSONS LEARNT
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
LESSONS LEARNT
• All products must be tested for compliance
Additional Materials Testing for Geotextiles
Compliance tests carried out in PSB Lab in Singapore, indicate that thegeotextile materials did not comply with the specifications and thusrejected.
Further confirmatory test was carried out at TRI lab in Austin, Texas,USA which also demonstrates failure. Approval of other alternativesuppliers shall be subjected to compliance of similar tests.
Laying of Geotextile Separator
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
LESSONS LEARNT
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
• All products must be tested for compliance (continue)
Perkins Generator Set
The FAT for the generator set type Perkins has failed twice due tofailure on alternator (Stanford). However the third FAT has passedusing alternator by Merrilly.
Anchorage Leakage Test
The test was done and only pass at the 3rd time.
LESSONS LEARNT
• Used of sonic logging (CSL) for Quality Control of bored piles
Cross-hole sonic logging (CSL) is a non-destructive method which involvedultrasonic signal transmission through the shaft between two parallel waterfilled access tubes. CSL is used by JKSB to evaluate the concrete and shaftconstruction quality of bored piles.
The defect identified by CSL include but are not limited to lower qualityconcreted due to mixing with drilling slurry, honeycombing, necking and soilintrusions, and soft toe conditions.
Defects are classified based on Class I, II, III, IV.
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
• Site clearing & earth work proceeded before land acquisition finalized.
JKSB has proceeded with land rental agreement with private land owners prior to land acquisition. This will enable the contractor to commence their works without awaiting for the land acquisition.
LESSONS LEARNT
Government land – 195.50 acres
Private Lots – 60.67 acres
Total land acquisition at Batu Kawan is = 256.17
acres
Land Acquisition – Batu Kawan
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
• Package 3A – Marine piling
Package 3A contractor was unable to proceed with work
The scope of works for marine piling work at Package 3A was novated to Package 1 contractor.
The work was successfully completed and Package 3A is back on track.
LESSONS LEARNT
LATEST PROGRESS
PHOTOS
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
Package 1
P25P26
P24 P27
Final Mid Span Closure cast completed MS19
on 21 April 2013
Overall View of Main Navigation Span
Balance of Works Start Date
1. Mid Span Deck of P25 & P27:
MS 19 Final stitchingCuring In
progress
2. Crown Structure Installation (1st
Set)08 May 2013
3. HT Cable Installation 07 June 2013
4. Transformer T24 & T27
Installation06 May 2013
5. Parapet Installation 15 May 2013
6. Premix Works 07 June 2013
7. Expansion Joint Installation 17 June 2013
LATEST PROGRESS PHOTO
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
LATEST PROGRESS PHOTO
Completed
Parapet
NJB Installation (as of 21/04/2013)
Total Completed : 5,140 / 9,750 (52.71%)
Balance : 4,610 nos
Prod : Current 56 nos/day, Target 66 nos/day
Target to complete by June 2013
Parapet Installation (as of 21/04/2013)
Total Comp : 23,650 / 29,796 (79.33%)
Balance : 6,146 nos
Prod : Current 193 nos/day, Target 154 nos/day
Target to complete by en of May 2013
Package 2
Completed
NJB
Installation of Parapet and NJB in progress.
Street Lighting Poles Installation (as of
22/04/2013)
Total Comp : 200 / 578 (34.6%)
Balance : 378 nos
Target to complete by July 2013
Completed Street
Lighting Pole
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
Completed Deck Slab
Ramp 1 : R1/P7-M2/P1
Ramp 2 : R2/P11-M1/P1 & R2/A-R2/P3
Ramp 3 : Completed
Ramp 4 : Completed
Ramp 4Ramp 2 Ramp 1
Ramp 3
Completion date on 30 June 2013
TNB
Substation
Construction of deck slab, box girder & RE wall is in progress
Package 3A
LATEST PROGRESS PHOTO
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
LATEST PROGRESS PHOTO
M1/P2
M1/P3
M1/P4
M1/P5
M1/P6
Land access ready on 30 March 2013
Deck Slab Work is in progress
M1/P7
M1/P8
Completion Deck Slab
M1/P1 – P0 : 30 Nov 12 – 15 May 13
M2/P2 – P0 : 21 Nov 12 – 30 Mar 13
Launching completed on 16
March 2013 (P0)
M1/P10
M1/P9
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
Package 3B – Earthwork
CH 18500
CH 17900
CH 18400
DBM
Roadbase
Overall view from CH 17900 – CH 18500
DBM
LATEST PROGRESS PHOTO
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
54
CONCLUSION
JAMBATAN KEDUA SDN BHD.Wholly own by Ministry of Finance
Despite its implementation in a fast track manner, the Penang Bridge Second Crossing is being constructed to the highest quality, considering health, safety, cost, sustainability and environmental conservation.
The Second Penang Bridge when completed will be the longest bridge in Malaysia and South East Asia when it opens for traffic in September 2013.
Thank You