1 de 2
PLANILLA DE METRADOS DE OBRA
Obra
FormulaFecha
ITEM DESCRIPCION DE PARTIDA UND UBICACIÓN / DETALLE CANTIDADLARGO ANCHO ALTO
PARCIAL METRADO(M) (M) (M)
03.04 PRIMER, SEGUNDO PISO Y AZOTEA03.04.00 LOSA ALBAÑILERIA
03.04.01 concreto f'c = 210 kg/cm2 m3 PRIMER PISO 7.45C-1 13.00 0.25 0.25 3.20 2.60C-2 4.00 0.25 0.15 3.20 0.48
SEGUNDO PISO
C-1 13.00 0.25 0.25 2.80 2.28AZOTEA
C-1 12.00 0.25 0.25 2.80 2.10
03.04.02 encofrado y desencofrado m2 PRIMER PISO 84.58C-1 EJE A1 Y C1 2.00 0.70 3.20 4.48
C-1 EJE B1, A2 Y C5 3.00 0.55 3.20 5.28C-1 EJE C2, B2, A3, C3, A4, C4 Y A5 7.00 0.70 3.20 15.68
C-1 EJE B5 1.00 0.85 3.20 2.72C-2 EJE B4' 1.00 0.50 3.20 1.60
C-2 EJE A6, B6 Y C6 3.00 0.65 3.20 6.24
SEGUNDO PISO
C-1 EJE C1 1.00 0.70 2.80 1.96C-1 EJE C2, B2, A3, C3, C4, A5, B1, A2, B5, A1 Y C5 11.00 0.70 2.80 21.56
C-1 EJE A4 1.00 0.55 2.80 1.54
AZOTEA
C-1 EJE C1 1.00 0.70 2.80 1.96C-1 EL RESTO 11.00 0.70 2.80 21.56
2 de 2
PLANILLA DE METRADOS DE OBRA
Obra
FormulaFecha
ITEM DESCRIPCION DE PARTIDA UND UBICACIÓN / DETALLE CANTIDADLARGO ANCHO ALTO
PARCIAL METRADO(M) (M) (M)
03.04.03 acero f'y = 4200 kg/cm2 kg 2,004.91PRIMER PISO Ø (kg/ml) cantidad
C-1 13.00 5.25 1.552 6.00 635.54Estribos 13.00 0.85 0.559 30.00 185.31
C-2 4.00 5.25 0.993 4.00 83.41Estribos 4.00 0.65 0.559 30.00 43.60
SEGUNDO PISO
C-1 13.00 4.00 1.552 6.00 484.22Estribos 13.00 0.85 0.559 23.00 142.07
AZOTEA
C-1 13.00 3.00 1.552 4.00 242.1113.00 3.00 0.993 2.00 77.45
Estribos 13.00 0.85 0.559 18.00 111.19