The design of the Mabey Compact 200 bridge allows the system to be used in a logistic role throughout the support area. As a Line of Communication bridge it can carry loads of up to Class 110 over gaps of up to 60m (200ft). The bridge is ideally suited for areas where speed of deployment is vital.
Modern Improvements
Rapid Construction The bridge is designed to be built by hand. A 30m bridge can be assembled and conventionally launched by 29 men in two or three hours, depending on site conditions. Where cranes or materials handling equipment is available, the total number of man hours to assemble a bridge is substantially reduced.
Modern Improvements
Load Testing
Launching Nose
Modern Improvements
Modern Improvements
B Co, 23rd Engr Bn replacing the Brcko Bridge with the Compact 200 (MAR 96)
Modern Improvements
M2 BaileyMabey Compact
200MLC MLC 80(T) 70 (W) MLC 80 (T) 110 (W)
# of Bays 13 13
Construction DT DS
# of Panels156 -- 2 ½ Sets of
Bailey 52
# of Transoms 66 14
Roadway Width 12 ft. 6 in (3.8m) 13 ft. 9 in. (4.2m)
Type of Deck Timber Steel
Total Weight 87 t 55 tBased on the launch and erection of a 130ft (39.62m) clear span, single lane bridge.
Modern Improvements
M2 BaileyMabey
Compact 200# of Bridging Sets
Required2 ½ Sets 1
# Men Required 90 29
# of Trucks RequiredAt Least 15 PLS (7
PLS per Set)11 PLS
# of Crane Picks Required
222 66
HOURS REQUIRED 12-14 hours 8-9 hours
Based on the launch and erection of a 130ft (39.62m) clear span, single lane bridge to carry MLC80 (T). Note, the M2 Bailey is unable to accommodate MLC 96 (W) Traffic.