CUrrEnt PrOJECt CAPACIty StArt-UP rEGUlAtOry StAtUS
NORTH aTHaBaSCa REGION — mINING
Canadian Natural Resources Limited
• Horizon updated: apr 2012
Canadian Natural reports that it has successfully completed unplanned maintenance on the fractionat-ing unit in its primary upgrading facility and restarted operations. The outage lasted from February 5 to March 13.
Phase 1 135,000 2008 Operating
Phase 2A 10,000 2014 Approved
Phase 2B 45,000 TBD Approved
Phase 3 80,000 TBD Approved
Imperial Oil Limited
• Kearl updated: apr 2012
Imperial Oil says that construction of Kearl Phase 1 is approximately 87 per cent complete and progressing on schedule. Reassembly of modules reduced in size to be transported on U.S. interstate routes continues at site.
Phase 1 110,000 2012 Construction
Phase 2 110,000 2015 Construction
Phase 3 Debottleneck 70,000 2020 Approved
Shell albian Sands
Jackpine updated: Jan 2012
The Canadian Environmental Assessment Agency recently invited public comment on a revised draft agreement to establish a joint panel for review of the Pierre River Mine project, as well as revisions to the existing joint panel agreement for the review of the Jackpine Mine expansion project.
Expansion 100,000 2017 Approved
Phase 1A 100,000 2010 Operating
Phase 1B 100,000 TBD Approved
muskeg River updated: Jan 2012
Commercial 155,000 2002 Operating
Expansion & Debottlenecking 115,000 TBD Approved
Pierre River updated: Jan 2012
Phase 1 100,000 2018 Application
Phase 2 100,000 TBD Application
Suncor Energy Inc.
• Base Operations updated: apr 2012
Suncor reported in March that one of its two upgraders was being taken down for unplanned main-tenance due to fractionator performance issues. The work was expected to take three to five weeks to complete and is not anticipated to result in changes to production guidance. In the fourth quarter of 2011, Suncor began to mine ore from the North Steepbank Extension.
Millennium Debottlenecking 23,000 2008 Operating
Millennium Mine 294,000 1967 Operating
CUrrEnt PrOJECt CAPACIty StArt-UP rEGUlAtOry StAtUS
North Steepbank Extension 180,000 2012 Operating
Steepbank Debottleneck Phase 3 4,000 2007 Operating
fort Hills updated: Nov 2011
Current capital expenditures for Fort Hills are around design base memorandum engineering.
Debottleneck 25,000 TBD Approved
Phase 1 165,000 2016 Approved
Voyageur South updated: Nov 2010
Phase 1 120,000 TBD Application
Syncrude Canada Ltd.
mildred Lake/aurora North & South updated: mar 2012
Canadian Oil Sands reports that front-end engineering and design is now complete for its $4.6-billion Mildred Lake mine train replacements. The target in-service date for the $1.6-billion Syncrude Emissions Reduction Project has now been extended into the first quarter of 2012.
Aurora South Train 1 100,000 2016 Approved
Aurora South Train 2 100,000 2018 Approved
Base Mine Stage 1 & 2 Expansion 290,700 1978 Operating
Stage 3 Expansion 116,300 2006 Operating
Teck Recources Limited
• frontier updated: apr 2012
The Canadian Environmental Assessment Agency has announced that a period of public comment is underway and participant funding is being allocated. Comments are being accepted until June 4.
Phase 1 75,000 2021 Application
Phase 2 80,000 2024 Application
Phase 3 80,000 2027 Application
Phase 4 Equinox 40,000 2030 Application
Total E&P Canada Ltd.
Joslyn North mine updated: Nov 2011
Project partner Suncor Energy says that current capital expenditures are around geological, engineer-ing, regulatory and environmental studies.
Phase 1 100,000 2018 Approved
Joslyn South mine updated: Dec 2010
Phase 1 100,000 TBD Announced
Northern Lights mine updated: Nov 2010
Phase 1 57,250 TBD On Hold
Phase 2 57,250 TBD On Hold
Peace River Region
Athabasca Region
Northwestern Saskatchewan
Industrial Heartland Region
Cold Lake Region
Sourced from company releases, the Energy Resources Conservation Board and the Daily Oil Bulletin, with files from Strategy West. For changes and updates, please contact Deborah Jaremko at [email protected]. Disclaimer: Oilsands Review accepts no liability for errors or inaccuracies in the information provided in this report.
PROJECT STATUS05.12
For even more details on all of these projects, visit www.oilsandsreview.com.
NORTH ATHABASCA REGION
SOUTH ATHABASCA REGION
COLD LAKE REGION
SASKATCHEWAN REGION
INDUSTRIAL HEARTLAND REGION
NEW EXPORT PIPELINES
PEACE RIVER REGION NEW INFORMATION THIS MONTH•
P r O J E C t S tAt U S
may 2012 | OILSANDSREVIEW.COM 37
Operator Educational Programs
Oil Sands Educational Program™ (OSEP)
SAGD Principles and Concepts Series
Petrochemical Educational Series
Alberta OSH Lesson Series
Maintenance and Preventative Maintenance Educational Series
www.itctrng.com • 205-663-4960
CUrrEnt PrOJECt CAPACIty StArt-UP rEGUlAtOry StAtUS
E-T Energy Ltd.
Poplar Creek updated: feb 2012
E-T is now working on what it calls Step 3 of its pilot, intended to look at equipment reliability and fine tuning of its well patterns. The next step will be a commercial 10,000-barrel-per-day project. E-T plans to access the IPO market in 2012.
Phase 1 10,000 2014 Application
Phase 2 40,000 2016 Announced
Pilot 1,000 2007 Operating
Husky Energy Inc.
Sunrise updated: feb 2012
Husky says Phase 1 construction remains on schedule for first production in 2014. More than half of the 49 SAGD well pairs are complete and Husky says drilling costs are trending on budget. Installa-tion of foundations for the main plant and delivery of first major equipment began in January.
Phase 1 60,000 2014 Construction
Phase 2 50,000 2016 Approved
Phase 3 50,000 TBD Approved
Phase 4 50,000 TBD Approved
Ivanhoe Energy Inc.
• Tamarack updated: apr 2012
Ivanhoe says it expects to respond to a second round of supplemental information requests from the ERCB in the second quarter.
Phase 1 20,000 2013 Application
Phase 2 20,000 TBD Application
marathon Oil Corporation
Birchwood updated: Sep 2011
Pilot 12,000 2016 Announced
Oak Point Energy Ltd.
Lewis updated: Nov 2011
Oak Point Energy reports that engineering and procurement is ongoing.
Pilot 1,720 2013 Application
Southern Pacific Resource Corp.
STP mcKay updated: feb 2012
Southern Pacific says construction is nearing completion and it remains on track for first steam near the end of the second quarter of 2012, with production to commence three to four months from first steam date.
Phase 1 12,000 2012 Construction
Phase 2A 12,000 2015 Application
Phase 2B 12,000 TBD Application
CUrrEnt PrOJECt CAPACIty StArt-UP rEGUlAtOry StAtUS
NORTH aTHaBaSCa REGION — IN SITu
athabasca Oil Sands Corp.
• Birch updated: apr 2012
AOSC says the updated contingent resources on its Birch holdings total 1.9 billion barrels. The company plans to submit its Birch regulatory application in late 2012 based on additional drilling and 3-D seismic.
Phase 1 12,000 TBD Announced
• Dover West Clastics updated: apr 2012
Application for the 12,000-barrel-per-day Phase 1 was filed in December 2011. AOSC has initiated work on a 65-kilometre permanent access road to the Dover West area.
Phase 1 12,000 2015 Application
Phase 2 35,000 TBD Announced
Phase 3 35,000 TBD Announced
• Dover West Leduc Carbonates updated: apr 2012
AOSC says that the performance of electrical heaters as part of its TAGD test has exceeded expectations.
Phase 1 Demonstration 6,000 2014 Application
Phase 2 Demonstration 6,000 TBD Application
Canadian Natural Resources Limited
Birch mountain updated: mar 2012
Phase 1 60,000 2022 Announced
Phase 2 60,000 2026 Announced
Cenovus Energy Inc.
Telephone Lake Borealis updated: Jan 2012
Cenovus has filed the environmental impact assessment for a 90,000-barrel-per-day phase com-mercial project at Telephone Lake.
Phase A 45,000 TBD Application
Phase B 45,000 TBD Application
Dover Operating Corp.
• Dover updated: apr 2012
Dover OpCo says the project is in the final stages of the regulatory review process.
Phase 1 50,000 2015 Application
Subsequent Phases 200,000 TBD Application
• macKay River updated: apr 2012
ERCB project approval granted January 2012. Dover OpCo says construction is underway.
Phase 1 35,000 2014 Construction
Phase 2 40,000 2017 Approved
Phase 3 40,000 2019 Approved
Phase 4 35,000 TBD Approved
38 OILSANDS REVIEW | may 2012
P r O J E C t S tAt U S
Project: Oil Sands Review AdIssue date: ______________
Image size: 7.0625” x 2.25”Bleed: none
Proof 3
in traditional and solvent-aided SAGD projects
Learn more at projex.ca
OSR ad QtrPg ex words v3.indd 7 18-10-11 11:34 AM
CUrrEnt PrOJECt CAPACIty StArt-UP rEGUlAtOry StAtUS
West Ells updated: Jan 2012
Sunshine has received regulatory approval to proceed with a 10,000-barrel-per-day SAGD project at West Ells. Former Harvest CEO John Zahary has been appointed president and CEO.
Phase 1 5,000 2013 Approved
Phase 2 5,000 2013 Approved
Phase 3 40,000 2018 Announced
Phase 4 40,000 2024 Announced
Value Creation Inc.
Terre de Grace updated: mar 2012
Pilot 10,000 TBD Approved
SOuTH aTHaBaSCa REGION — IN SITu
alberta Oilsands Inc.
• Clearwater West updated: apr 2012
Alberta Oilsands says it responded to the second round of supplemental information requests from the ERCB in December 2011. The company anticipates approval for the Clearwater West pilot in 2012.
Phase 2 25,000 2016 Announced
Pilot 4,350 2012 Application
athabasca Oil Sands Corp.
Hangingstone updated: Jan 2012
AOSC says the engineering design basis memorandum is complete, and certain long-lead items have been procured such as evaporators and boilers. Construction is targeted to start in late 2012.
Phase 1 12,000 2014 Application
Phase 2 35,000 2017 Announced
Phase 3 35,000 2019 Announced
BlackPearl Resources Inc.
Blackrod updated: feb 2012
Alberta Environment and Water is preparing the final terms of reference for the commercial project phases. BlackPearl says production at the pilot is now over 300 barrels per day with an instantaneous SOR of less than 3:1, exceeding model expectations. The application for the 80,000-barrel-per-day commercial project is nearing completion and will be submitted to the regulator in the second quarter of 2012.
Phase 1 20,000 2016 Announced
Phase 2 30,000 TBD Announced
Phase 3 30,000 TBD Announced
Pilot 800 2011 Operating
Canadian Natural Resources Limited
Gregoire Lake updated: mar 2012
Phase 1 60,000 2024 Announced
Grouse updated: feb 2012
Regulatory application is targeted for early 2012. Alberta Environment and Water has issued its final terms of reference for the Grouse environmental impact assessment.
Commercial 50,000 2017 Application
CUrrEnt PrOJECt CAPACIty StArt-UP rEGUlAtOry StAtUS
Suncor Energy Inc.
firebag updated: feb 2012
Suncor says that exiting 2011, bitumen production from its in situ assets increased approximately 30 per cent over 2010, primarily due to the ramp up of operations from Firebag Stage 3 and new infill wells at the Firebag project.
Cogeneration and Expansion 25,000 2007 Operating
Stage 1 35,000 2004 Operating
Stage 2 35,000 2006 Operating
Stage 3 62,500 2011 Operating
Stage 3-6 Debottleneck 23,000 TBD Application
Stage 4 62,500 2013 Construction
Stage 5 62,500 2018 Approved
Stage 6 62,500 2019 Approved
Lewis updated: Dec 2010
Phase 1 40,000 TBD Application
Phase 2 40,000 TBD Application
macKay River updated: feb 2012
Suncor has commenced production from a new phase of six wells at MacKay River and initiated steam injection into additional wells. Production from these developments is expected to offset natural declines in the future.
MR2 40,000 2016 Application
Phase 1 33,000 2002 Operating
Sunshine Oilsands Ltd.
Harper updated: feb 2012
Sunshine Oilsands is mobilizing for a second cyclic steam stimulation cycle at its Harper pilot, report-edly with a number of production improvements to better understand and operate the scheme.
Carbonate Pilot 1,000 2011 Operating
Legend Lake updated: Nov 2011
Sunshine Oilsands has filed its application for the Legend Lake SAGD project.
Phase 1 10,000 2016 Application
Phase 2 10,000 TBD Announced
Phase 2 Expansion 10,000 TBD Announced
Phase 3 20,000 TBD Announced
Phase 3 Expansion 10,000 TBD Announced
Thickwood updated: Nov 2011
Sunshine Oilsands has submitted the regulatory application for its Thickwood SAGD project, antici-pating project start up in 2015.
Phase 1 10,000 2015 Application
Phase 2 20,000 2017 Announced
Phase 2 Expansion 20,000 2020 Announced
may 2012 | OILSANDSREVIEW.COM 39
P r O J E C t S tAt U S
Reliable Oil & GasBuilding Solutions
Leaseor
Purchase
Widths 30' to 200' by any length
On-site Warehousing
Bulk Storage
Direct Dial: 403 601.2292
[email protected] www.sprung.com
1 800 528.9899
Engineered & Manufactured by SPRUNG INSTANT STRUCTURES®
Aldersyde, Alberta
Optional 8" fiberglass insulation packages
Vehicle Maintenance
CUrrEnt PrOJECt CAPACIty StArt-UP rEGUlAtOry StAtUS
Kirby (North) updated: Jan 2012
CNRL has submitted the environmental impact assessment for all phases at Kirby North and South.
Phase 1 40,000 2016 Application
Phase 2 40,000 2019 Application
• Kirby (South) updated: apr 2012
Canadian Natural says construction remains on track and on budget. Drilling has been completed on the second of seven well pads and commenced on the third. The company says drilling is confirming geological expectations.
Phase 1 45,000 2013 Construction
Phase 2 15,000 2020 Application
Cavalier Energy Inc.
• Hoole updated: apr 2012
Near-term plans for Paramount Resources Ltd. subsidiary Cavalier Energy include finalizing the scope and design of the initial phase of development at Hoole, submitting an application for commercial development and evaluating funding alternatives.
Commercial 35,000 2015 Announced
Cenovus Energy Inc.
Christina Lake updated: feb 2012
Construction of Phase D is more than 70 per cent complete and production is expected in the fourth quarter. Construction of Phase E is more than 30 per cent complete, with initial production expected in the fourth quarter 2013. Ground preparation continues for Phase F. Production capacity for both Phase F and G has been increased by 10,000 barrels per day to 50,000 barrels per day each.
Phase 1A 10,000 2002 Operating
Phase 1B 8,800 2008 Operating
Phase C 40,000 2011 Operating
Phase D 40,000 2012 Construction
Phase E 40,000 2013 Approved
Phase F 50,000 2016 Approved
Phase G 50,000 2017 Approved
Phase H 40,000 2019 Announced
foster Creek updated: feb 2012
Ground preparation is now complete for Phases F-H. At Phase F, site preparation and the installation of pipe racks continues to progress on schedule.
Phase A 24,000 2001 Operating
Phase B Debottleneck 6,000 2003 Operating
Phase C Stage 1 10,000 2005 Operating
Phase C Stage 2 20,000 2007 Operating
Phase D 30,000 2009 Operating
Phase E 30,000 2009 Operating
Phase F 45,000 2014 Construction
Phase G 40,000 2015 Approved
Phase H 40,000 2016 Approved
Phase I 45,000 2017 Announced
Narrows Lake updated: feb 2012
Cenovus and partner ConocoPhillips Canada anticipate a response from the ERCB regarding the Narrows Lake application by mid-2012.
Phase 1 43,333 2016 Application
Phase 2 43,333 TBD Application
Phase 3 43,334 TBD Application
Pelican Lake Grand Rapids updated: Jan 2012
Cenovus has filed the environmental impact assessment for a commercial project at Pelican-Grand Rapids.
Phase A 60,000 2017 Application
Phase B 60,000 TBD Application
Phase C 60,000 TBD Application
Pilot 600 2011 Operating
40 OILSANDS REVIEW | may 2012
P r O J E C t S tAt U S
Once-Through Steam GeneratorsCustom Innovative DesignsSAGD and CSS Applications50 mm BTU/hr and LargerU.S. Manufacturing FacilitiesCanadian Pre-Assembly and Installation
www.ExpressGroupHoldings.com
• Heat Recovery Steam Generators• Waste Heat Recovery Units• Process Fired Heaters• Simple Cycle Catalyst Systems• Aftermarket Services
EIT also Engineers and Fabricates
Please contact us to learn more about our in-house engineering and fabrication capabilities.
Express Integrated Technologies (EIT) engineers and fabricates custom-designed equipment for the process and power industries, including mid-stream processes, cogeneration equipment, and Once-Through Steam Generators for in-situ oil production.
We are pleased to announce the opening of our Calgary office, EIT Canada Ltd., created specifically to serve the needs of the Canadian oil sands market.
CUrrEnt PrOJECt CAPACIty StArt-UP rEGUlAtOry StAtUS
Connacher Oil and Gas Limited
• Great Divide updated: apr 2012
Connacher has initiated a strategic review process, but says it has a number of capital projects with very good economics that are expected to increase production and/or improve netbacks that will continue to be evaluated and undertaken when free cash flow is available.
Algar Pod 2 10,000 2010 Operating
Expansion 1A 12,000 2014 Application
Expansion 1B 12,000 2016 Application
Pod 1 10,000 2007 Operating
ConocoPhillips Canada Limited
Surmont updated: mar 2012
Phase 1 27,000 2007 Operating
Phase 2 109,000 2015 Construction
Pilot 1,200 1997 Operating
Devon Canada Corporation
Jackfish updated: Dec 2011
Devon reports that Jackfish 3 construction is now underway, and that Jackfish 2 volumes are ramping up ahead of plan and on target to reach capacity of 35,000 barrels per day by late 2012.
Phase 1 35,000 2007 Operating
Phase 2 35,000 2011 Operating
Phase 3 35,000 2015 Construction
Pike updated: feb 2012
Devon is currently drilling appraisal wells and acquiring seismic on its Pike oilsands leases in order to determine the optimal development plan.
1A 35,000 2016 Announced
1B 35,000 2017 Announced
1C 35,000 2017 Announced
Grizzly Oil Sands ulc
algar Lake updated: feb 2012
Partial owner Gulfport Energy says Grizzly’s construction is on track for commissioning in the fourth quarter with first production in mid-2013. Grizzly will also likely soon file a regulatory application for a SAGD project at Thickwood.
Phase 1 5,650 2013 Construction
Phase 2 5,650 2014 Approved
Conklin (Whitesands) updated: Oct 2011
Expansion 1,900 TBD On Hold
Pilot 1,900 2006 Suspended
• may River updated: apr 2012
Grizzly has closed its acquisition of the May River asset from Petrobank Energy and Resources. Development plans are under review.
Phase 1 10,000 2013 Application
Subsequent Phases 90,000 TBD Disclosed
Harvest Operations Corp.
• BlackGold updated: apr 2012
Harvest says site preparation is complete and site construction will begin in 2012. Drilling has begun on the first surface holes for SAGD well pairs, and the company says all 15 well pairs will be complete in 2012.
Phase 1 10,000 2014 Construction
Phase 2 20,000 2015 Application
Husky Energy Inc.
mcmullen updated: feb 2012
Husky says that steam injection commenced in September 2011, followed by first air injection suc-cessfully initiated in December 2011.
Air Injection Pilot-Experimental 755 2012 Construction
may 2012 | OILSANDSREVIEW.COM 41
P r O J E C t S tAt U S
SUBMIT YOUR ANNUAL REPORT AND WEBSITEVisit us online before July 15, 2012, for more information and to complete the entry form.
Enter the oil and gas industry’s 37th Annual
Report Awards competition.
Be recognized as the best of the best for your annual report, sustainability report and corporate website. Award winners will be featured in the January 2013 edition of Oilweek magazine.
oilweek.com/araOILWEEK.COM/ARA
CUrrEnt PrOJECt CAPACIty StArt-UP rEGUlAtOry StAtUS
• Surmont updated: apr 2012
MEG has announced the launch of the regulatory process for Surmont. The proposed Terms of Reference from Alberta Environment and Water are available for public comment until May 4.
Phase 1 60,000 2016 Announced
Phase 2 60,000 TBD Announced
N-SOLV Corporation
Dover updated: aug 2011
N-Solv and partner Suncor Energy have been granted funding from the Government of Canada under Sustainable Development Technology Canada to develop the N-Solv pilot.
Demonstration Plant 500 2012 Announced
Nexen Inc.
Long Lake updated: feb 2012
Nexen says its focus at Long Lake continues to be to fill unused capacity at the upgrader. The com-pany is currently advancing 60 additional wells to achieve this task.
Long Lake South (Kinosis) Phase 1 40,000 TBD Approved
Long Lake South (Kinosis) Phase 2 40,000 TBD Approved
Phase 1 72,000 2008 Operating
Phase 2 72,000 TBD Approved
Phase 3 72,000 TBD Application
Phase 4 72,000 TBD Announced
Statoil
Kai Kos Dehseh updated: aug 2011
Corner 40,000 2015 Approved
Corner Expansion 40,000 TBD Application
Hangingstone 20,000 TBD Application
Leismer Commercial 10,000 TBD Approved
Leismer Demonstration 10,000 2010 Operating
Leismer Expansion 20,000 TBD Approved
Leismer Northwest 20,000 TBD Application
Leismer South 20,000 TBD Application
Thornbury 40,000 TBD Application
Thornbury Expansion 20,000 TBD Application
Suncor Energy Inc.
Chard updated: Dec 2010
Phase 1 40,000 TBD Announced
meadow Creek updated: Dec 2010
Phase 1 40,000 TBD Approved
Phase 2 40,000 TBD Approved
CUrrEnt PrOJECt CAPACIty StArt-UP rEGUlAtOry StAtUS
Japan Canada Oil Sands Limited
Hangingstone updated: Jan 2012
JACOS owner Japan Petroleum Exploration is delaying a decision on an expansion at Hangingstone until mid-2012 due to a delay in regulatory approval.
Expansion 35,000 2015 Application
Hangingstone Pilot updated: Jan 2012
JACOS owner JAPEX says regulatory approval for expansion is anticipated this fall, and an invest-ment decision will follow.
Pilot 11,000 1999 Operating
Koch Exploration Canada Corporation
• muskwa updated: apr 2012
Koch filed its application for the Muskwa project in February 2012.
Pilot 10,000 2015 Application
Laricina Energy Ltd.
Germain updated: Dec 2011
Civil site construction is complete. Well pair drilling has commenced. Procurement, engineering and module fabrication continues. Laricina has commenced an expansion of its camp to support project construction. Laricina has submitted the environmental impact assessment for its 150,000-barrel-per-day expansion at Germain.
Phase 1 Commercial Demonstration 5,000 TBD Construction
Phase 2 30,000 2015 Application
Phase 3 60,000 TBD Application
Phase 4 60,000 TBD Application
Saleski updated: Nov 2011
Laricina says the Saleski pilot sold 26,300 barrels of bitumen as of the end of the third quarter of 2011. Pilot testing continues with an additional steam cycle added to each operating pair. The company has received regulatory approval for the addition of a second steam generator. The Phase 1 application continues to move through the regulatory process, and now first steam is targeted for early 2014 rather than late 2013.
Phase 1 10,700 2014 Application
Pilot 1,800 2011 Operating
mEG Energy Corporation
Christina Lake updated: feb 2012
MEG says that detailed engineering on Phase 2B is 93 per cent complete. All materials and project modules have been ordered, with delivery and on-site construction scheduled to continue through 2012 with completion scheduled for 2013. The company has received regulatory approval for the multistage Phase 3.
Phase 1 Pilot 3,000 2008 Operating
Phase 2A 22,000 2009 Operating
Phase 2B 35,000 2013 Construction
Phase 3A 50,000 2016 Approved
Phase 3B 50,000 2018 Approved
Phase 3C 50,000 2020 Approved
42 OILSANDS REVIEW | may 2012
P r O J E C t S tAt U S
SAGD pilotsSpecializing inwww.specengineering.ca
CUrrEnt PrOJECt CAPACIty StArt-UP rEGUlAtOry StAtUS
Pengrowth Energy Corporation
Lindbergh updated: feb 2012
Pengrowth achieved first steam at the Lindbergh pilot in February.
Phase 1 Commercial 12,500 2014 Application
Phase 2 Commercial 17,500 2016 Announced
Pilot 1,200 2012 Operating
Royal Dutch Shell plc
Orion updated: Dec 2010
Phase 1 10,000 2007 Operating
Phase 2 10,000 TBD Approved
PEaCE RIVER REGION — IN SITu
andora Energy Corporation
• Sawn Lake updated: apr 2012
Andora Energy majority owner PanOrient Energy Corp. says the previously announced strategic review continues, but no bids have been received either to purchase the company or farm into the asset. The company has announced an updated geological and economic evaluation of the project by Sproule, showing best-case contingent resources of 214 million barrels with best-case net present value of $612 million.
SAGD Demonstration 1,400 TBD Approved
Northern alberta Oil Ltd.
Sawn Lake updated: Jan 2012
Company owner Deep Well Oil & Gas says DeGolyer & MacNaughton Canada has completed its reservoir modelling for a proposed horizontal cyclic steam stimulation pilot at Sawn Lake, concluding the project would yield commercially viable extraction. Deep Well is currently preparing a pilot plan and options for capitalization.
CSS Pilot 700 TBD Approved
Petrobank Energy and Resources Ltd.
• Dawson updated: apr 2012
Petrobank says that drilling of the well pairs for the demonstration project is complete, and construc-tion of the surface facilities will be complete later in 2012.
Phase 2 10,000 TBD Announced
THAI Demonstration-Experimental TBD TBD Construction
Royal Dutch Shell plc
Peace River updated: Dec 2011
Alberta’s environmental assessment director has deemed complete Shell Canada’s environmental impact assessment report for the Carmon Creek expansion.
Cadotte Lake 12,500 1986 Operating
Carmon Creek - Phase 1 40,000 2015 Application
Carmon Creek - Phase 2 40,000 TBD Application
CUrrEnt PrOJECt CAPACIty StArt-UP rEGUlAtOry StAtUS
Value Creation Inc.
TriStar updated: Jan 2011
Value Creation is providing the ERCB with additional information supporting its application.
Pilot 1,000 2012 Application
COLD LaKE REGION — IN SITu
Canadian Natural Resources Limited
• Primrose/Wolf Lake updated: apr 2012
Canadian Natural says production increased nine per cent in 2011 versus 2010 due to optimization of steaming technologies and the development of new low-cost pads. The company expects another nine per cent increase in 2012.
Primrose East 32,000 2008 Operating
Primrose North 30,000 2006 Operating
Primrose South 45,000 1985 Operating
Wolf Lake 13,000 1985 Operating
Husky Energy Inc.
Caribou updated: Nov 2010
Demonstration 10,000 TBD Approved
Tucker updated: feb 2012
Production at Tucker has increased significantly, exiting 2011 at over 9,000 barrels per day versus 4,000 barrels per day the previous year. Husky says it has addressed subsurface challenges by remediating older wells with new completion and stimulation techniques and initiating revised start-up procedures.
Phase 1 30,000 2006 Operating
Imperial Oil Limited
Cold Lake updated: mar 2012
Imperial says Cold Lake continues to achieve record production rates (162,000 barrels per day in the fourth quater of 2011) due to contributions from new wells steamed in 2010 and 2011, and increased recovery due to technology application.
Phase 1-10 110,000 1985 Operating
Phase 11-13 30,000 2002 Operating
Phase 14-16 40,000 2014 Construction
Koch Exploration Canada Corporation
• Gemini updated: apr 2012
A public hearing was planned on the project in February, but was cancelled after outstanding objec-tions were dropped. The project was granted approval in March.
Stage 1 1,200 TBD Approved
Stage 2 10,000 TBD Approved
OSum Oil Sands Corp.
• Taiga updated: apr 2012
The ERCB has scheduled a public hearing into the Taiga project for May 23.
Phase 1 17,500 2014 Application
Phase 2 17,500 2016 Application
may 2012 | OILSANDSREVIEW.COM 43
P r O J E C t S tAt U S
CUrrEnt PrOJECt CAPACIty StArt-UP rEGUlAtOry StAtUS
Value Creation Inc.
Terre de Grace updated: mar 2012
Pilot 8,400 TBD Approved
SOuTH aTHaBaSCa REGION — uPGRaDER
Nexen Inc.
Long Lake updated: feb 2012
Nexen says its focus at Long Lake continues to be to fill unused capacity at the upgrader. The com-pany is currently advancing 60 additional wells to achieve this task.
Phase 1 58,500 2008 Operating
Phase 2 58,500 TBD Approved
Phase 3 58,500 TBD Announced
Phase 4 58,500 TBD Announced
Value Creation Inc.
TriStar updated: Jan 2011
Value Creation is providing the ERCB with additional information supporting its application.
Pilot 840 TBD Application
INDuSTRIaL HEaRTLaND REGION — uPGRaDER
North West upgrading Inc.
Redwater upgrader updated: feb 2012
Final sanction is anticipated in 2012.
Phase 1 77,000 2013 Approved
Phase 2 77,000 2018 Approved
Phase 3 77,000 TBD Approved
Shell albian Sands
• Scotford upgrader 1 updated: apr 2012
The Canadian Environmental Assessment Agency is inviting the pulbic to comment on the screening report for the environmental impact asseessment of the Shell Quest carbon capture and storage project at the Scotford Upgrader. The screening report details federal conclusions about the project. Public comments will be accepted until April 13.
Commercial 158,000 2003 Operating
Expansion 91,000 2011 Operating
Value Creation Inc.
Heartland updated: Nov 2010
Construction was suspended in September 2008.
Phase 1 46,300 TBD On Hold
Phase 2 46,300 TBD Approved
Phase 3 46,300 TBD Approved
NEW ExPORT PIPELINES
Enbridge
• Northern Gateway updated: apr 2012
Public hearings ongoing. Enbridge has announced that president and CEO Patrick Daniel is retiring at or before the end of 2012. He will be succeeded by Al Monaco, currently president, gas pipelines, green energy and international.
Alberta to Kitimat, B.C.525,000 plus 70,000 diluent line
2017 Application
Kinder morgan Canada
• Trans mountain Expansion (Tmx) updated: apr 2012
The open season for the Kinder Morgan Trans Mountain Expansion was extended by two weeks to April 10, 2012.
Edmonton to Burnaby, B.C., Washington State and offshore
Expansion up to 700,000
n/q Announced
TransCanada Pipelines
Keystone Expansion updated: feb 2012
TransCanada says it is ready to re-apply for the project from the U.S./Canada border to Nebraska, supplemented by an alternative route through Nebraska once that is selected. It also plans to construct the Cushing to U.S. Gulf Coast portion of the line as a stand-alone project.
Cushing, Okla., to U.S. Gulf Coast 500,000 TBD Announced
CUrrEnt PrOJECt CAPACIty StArt-UP rEGUlAtOry StAtUS
Southern Pacific Resource Corp.
Red Earth updated: feb 2012
Southern Pacific is analyzing results from its latest CSS test at Red Earth. The company says it will finalize future development plans in the second quarter.
Commercial 10,000 TBD Announced
Pilot 1,000 2009 Operating
Pilot Expansion 3,000 TBD Announced
SaSKaTCHEWaN REGION — IN SITu
Oilsands Quest Inc.
• axe Lake updated: apr 2012
Oilsands Quest has signed the definitive loan agreements for debtor-in-possession financing of $2.85 million, which will fund operating costs and other expenses while the company continues its solicitation process.
Commercial 30,000 TBD On Hold
Reservoir Test 600 2008 On Hold
SAGD Pilot TBD TBD On Hold
NORTH aTHaBaSCa REGION — uPGRaDER
Canadian Natural Resources Limited
• Horizon updated: apr 2012
Canadian Natural reports that it has successfully completed unplanned maintenance on the fractionat-ing unit in its primary upgrading facility and restarted operations. The outage lasted from February 5 to March 13.
Phase 1 114,000 2009 Operating
Phase 2A 10,000 2014 Approved
Phase 2B 45,000 TBD Approved
Phase 3 80,000 TBD Approved
Ivanhoe Energy Inc.
• Tamarack updated: apr 2012
Ivanhoe says it expects to respond to a second round of supplemental information requests from the ERCB in the second quarter.
Phase 1 34,784 2014 Application
Suncor Energy Inc.
• Base Operations updated: apr 2012
Suncor reported in March that one of its two upgraders was being taken down for unplanned main-tenance due to fractionator performance issues. The work was expected to take three to five weeks to complete and is not anticipated to result in changes to production guidance. In the fourth quarter of 2011, Suncor began to mine ore from the North Steepbank Extension.
Millennium Coker Unit 97,000 2008 Operating
Millennium Vacuum Unit 35,000 2005 Operating
U1 and U2 225,000 1967 Operating
fort Hills updated: Nov 2011
Current capital expenditures for Fort Hills are around design base memorandum engineering.
Phase 1 145,000 TBD On Hold
Phase 2 & 3 145,000 TBD On Hold
Voyageur upgrader 3 updated: Nov 2011
Current capital expenditures are around remobilizing the workforce, confirmation of current design and modification of project execution plans.
Phase 1 127,000 2017 Approved
Phase 2 63,000 TBD Approved
Syncrude Canada Ltd.
mildred Lake/aurora North & South updated: mar 2012
Canadian Oil Sands reports that front-end engineering and design is now complete for its $4.6-billion Mildred Lake mine train replacements. The target in-service date for the $1.6-billion Syncrude Emissions Reduction Project has now been extended into the first quarter of 2012.
Base Plant Stage 1 & 2 Debottleneck 250,000 1978 Operating
Stage 3 Debottleneck 75,000 TBD Announced
Stage 3 Expansion (UE-1) 100,000 2006 Operating