CANDIAN TECHNOLOGY TRANSFERCANDIAN TECHNOLOGY TRANSFERCERNAVODA CANDU PROJECT CERNAVODA CANDU PROJECT
The International Nuclear Energy Congress, The International Nuclear Energy Congress, Istanbul, Turkey, April 11-12, 2007 Istanbul, Turkey, April 11-12, 2007
Dr. Sardar Alikhan, Alikhan Consulting Inc.Dr. Sardar Alikhan, Alikhan Consulting Inc.(Ex-AECL-Qinshan/Cernavoda Projects) (Ex-AECL-Qinshan/Cernavoda Projects)
Pg 2
Cernavoda CANDU Project
Pg 3
Cernavoda CANDU Project
Pg 4
Contents
Cernavoda Unit 1Scope of Work/Major ChallengesProject Management Team/StaffingEngineering ManagementConstruction ManagementStatus Verification/Remedial WorkPlanning and ControlCommissioning and OperationsOperations Staffing/TrainingTurnover to Operations
Pg 5
CONTENTS
Cernavoda Unit 2 Scope of Work Reference Design Project Management Team Current Progress
Localization of Technology Nuclear Infrastructure Fuel Fabrication Heavy Water Production
Key Factors to Success Concluding Remarks
Pg 6
Cernavoda 1 & 2 - Romania Cernavoda 1:
Unit completed in Dec. 199687% lifetime capacity factor
Cernavoda 2: Commissioning and testing is currently underway, ready for
first criticality and scheduled for commercial operation later in 2007
Pg 7
CERNAVODA UNIT 1
Pg 8
CERNAVODA UNIT 1 CONTRACT In 1992, Romania signed a new contract with AECL-ANSALDO
Consortium (AAC) authorizing AAC to manage the remaining work to complete Unit 1 and to preserve Unit 2-5
The new contract took full recognition of previous technology transfer agreements signed with AECL for NSP, with ANSALDO for BOP and with GE for T-G
At this time, Unit 1 and Units 2-5 were at various stages of completion. Most of the major equipment were already installed for Unit 1 and 2 but its status needed to be thoroughly verified to meet current quality and licensing requirements.
Pg 9
AAC SCOPE OF WORK
Manage completion of construction, installation, commissioning and early operation of Unit 1 and preservation of Unit 2-5.
Provide QA assistance to local nuclear component manufacturers Provide technical assistance and training to construction
contractors, especially in welding and NDE Engineering management and services covering all activities
required for Unit 1 completion, including coordination between NSP, BOP and Support Services
Procurement of goods and services locally and outside, maximizing Romanian content
Perform selection, training of Romanian operations staff Perform commissioning and operations services, extending up to
18 months after in-service
Pg 10
Project Management Team (PMT)
Customer delegated its full authority to AAC PMT to manage the project on its behalf and placed all resources required at its disposal.
PMT authorized to stop all or part of the work, reject any supplies or services, if it does not meet the safety and quality requirement.
Prior customer authorization required to commit funding in excess of the approved budget in foreign exchange and local currency
Pg 11
PMT STAFFING
• Project Management
- In Unit 1, led by AECL-ANSALDO and with participation of the Owner’s staff
Owner’s staff integrated in the Project Management Team and Commissioning Team to the fullest extent possible
Peak Expatriate staff of 400 (240 AECL, 160 Ansaldo) Over 2000 Romanian staff integrated in PMT and
Commissioning Team
Expatriate staff provided hands-on field supervision. Production and quality went hand in hand. If work is
not done right, it was rejected and redone correctly.
Pg 12
Engineering Management and Quality Surveillance
Overall direction, coordination and administration of all engineering services: Interpretation of technical documents Technical direction and resolution of all construction,
commissioning, and safety/licensing issues Approval of subcontract work packages Check compliance of as-constructed plant with design,
rejecting any non-conforming items Manage NDE inspection program Manage project change control process Certification of interim and final acceptances Approval of as-built drawings
Pg 13
Construction Management
Overall direction, coordination and administration of construction on Unit 1 and remedial work on Unit 2: Implementation of construction methods, schedules,
work packages and manpower schedules Technical assistance to local construction subcontractors Support implementation of inspection programs Management of construction subcontracts Establish a common labour policy with subcontractors Establish progress reporting system for subcontractors
Pg 14
Baseline Design and Construction Status Verification
AAC Engineering and Quality Surveillance team performed an in-depth verification of the status of NSP, BOP and Support Systems Check all design documentation for completeness Check all SSCs for correct installation per design Perform all NDE for systems that require to be qualified Check locally supplied equipment and materials for
compliance with equipment specification Prepare comprehensive status reports to perform remediation
Pg 15
Remedial Work
Examples of remedial work included: All piping welds inspected and repaired as required Piping system cleaned Cracked concrete on containment dome replaced Locally made diesel generators replaced with
imported units Refurbishment of support systems e.g. heating
boilers, WTP, Firewater, common pump house equipment etc.
Pg 16
Planning and Control
• Planning process started before the Contract effective date and continued for the lifecycle of the Project.– Establish project work breakdown structure and logic
– Develop level 2 coordination and control (C&C) schedule
– Establish realistic targets for each milestone
– Define project priorities
– Report actual progress
– Identify Critical issues
– Ensure all parties work to a common goal
• Use as-built schedule to input to future projects taking into account lessons learned and other developments.
Pg 17
Integration of Inputs to C&C Schedule
L2 Schedule(C&C)
Engineering Procurement
Construction(Area)
Commissioning(System) Conversion
Project Budget
Pg 18
COMMISSIONING AND OPERATION
AAC Commissioning/Operations staff: Led and supervised commissioning and initial operation including in-
service inspection and maintenance. Accepted systems turnover from construction Supervised commissioning for compliance with approved procedures Evaluated commissioning completion to declare availability for
service Supervised operations support programs: shift operation,
maintenance, chemistry control, materials control, radiation protection, industrial safety, safety and licensing, planning and scheduling
Assist in staff training Customer provided full complement of operation staff AAC staff transferred leadership and supervision to customer’s staff
gradually as a function of their demonstrated capability
Pg 19
OPERATIONS STAFFING PLAN
AAC developed staffing plan along with specific position specific requirements
Covered full complement of operations staff trained and available for commissioning and operation at least 18 months prior to Unit 1 connection to grid
Supported the customer to select personnel
Developed and conducted training program for key operations staff
Pg 20
OPERATIONS TRAINING
90 key Romanian staff identified for training in Canada. Management and senior supervisory 10 Shift operations 50 Maintenance 10 Computers 4 Technical support 12 Other 4
Training durations ranged from 4 to 24 months depending on job requirement
Classroom training in CANDU technology, skills training, in-plant training in Canada, and simulator training.
On-the-job coach and mentoring during commissioning and early operation
Pg 21
Unit 1 Turnover to Operations
Assessment of all structures, systems and components for compliance with design requirement
Assessment of each operations department along with recommendations to fill any gaps
Following formal turnover of Unit 1, WANO conducted a Peer Review in July-August 1997. One of the key strengths noted was: “ A very knowledgeable and professional management team is
established. The management team willingly embraces new ideas, and is highly motivated to achieving excellence in the operation of the plant.”
Unit 1 operated by Romanian operating staff since in service date has an excellent safety and performance record
Lifetime capacity factor for Unit 1 over the past 10 years is around 87%
Pg 22
June 30, 1997 at 17:00Sardar Alikhan handingover Unit 1 to Ionel Bucur
Pg 23 Unit 1 completed and operating at 87% CF since in-service
Pg 24
Cernavoda Unit 2
Pg 25
Unit 2 Contract Scope
The Contract between SNN, AECL and ANSALDO became effective on March 24, 2003
With CED, relevant financial agreements finalized, allowing rapid build up of expatriate staff
AECL and ANSALDO provided firm price home office support to: perform conceptual engineering procurement of sole source pre-assigned supply procurement of other items as a result of SNN international
tender process. Balance in Romanian scope including detailed
engineering, equipment and /material supply and construction
Pg 26
Unit 2 Reference Design
Unit 2 reference design took into account current licensing requirements and factored in: Unit 1 as-built design as of 30 June 1997 Assessment of Unit 1 commissioning reports Assessment of design changes implemented on Wolsong 3 and
4 and Qinshan 129 major design changes and 154 design improvements
Pg 27
Cernavoda 2 Project Management StructureCernavoda 2 Project Management Structure
OwnerSNN Construction
Site EngineeringProject Management
AECL (Lead)/Ansaldo/SNN
Commissioning
Conceptual Engineering AECL
Conceptual Engineering Ansaldo
Equipment- Ansaldo
Equipment- AECL
T/G - GE
Equipment - Alstom
Equipment - NEXANS
Construction– Romanian
Fuel– FCN
Heavy Water– RAAN
Equipment - Romanian
Detailed engineering– Romanian
Pg 28
Unit 2 Project Management
Engineering, Procurement and Construction- Led jointly by SNN and AECL-ANSALDO Required full integration and team effort of all parties including
AECL-Canada, ANSALDO-Italy and SNN-owner Project management though a site-based Management Team (MT) SNN providing deputies at all levels providing full integrated team
approach Peak staffing: 180 expatriates, and 1450 Romanians. Site
construction contractors staff peaked around 3000 Expatriate staff split 60/40 AECL/ANSALDO- More than 80% of project management staff were Romanian
Pg 29
Current Progress
Commissioning of all systems required for fuel load completed
Fuel loading completed Unit ready to achieve first criticality Commercial operation expected in fall 2007.
Pg 30
LOCALIZATION OF TECHNOLOGY
Pg 31
Nuclear Infrastructure
Nuclear Fuel Fabrication Plant in Pitesti. Heavy Water Production Plant in Drobeta-Turnu Severin
Heavy Nuclear Equipment Factory in Bucharest Nuclear Research Institute in Pitesti for R&D CITON engineering and technology centre for nuclear
project in Magurele, near Bucharest Romanian construction contractors in civil,
mechanical, electrical and C&I Other specific nuclear materials and devices
manufacturing plants
Pg 32
Fuel Fabrication Romania has localized nuclear fuel fabrication from
the mine to the fuel bundle since the start of Unit 1 operation
Local fuel has excellent quality and reliability Canadian Zircatec provided technical assistance The facilities are expanded to supply fuel to unit 1 and
2 starting in 2007 Local fuel supply results in domestic industrial benefit
Pg 33
Heavy Water Production
Produced by ROMAG-PROD located at Turnu Severin
All heavy water requirements for Unit 1 operation and Unit 2 initial load
350 tonnes of heavy water leased for Unit 1 initial load from Canada returned
Pg 34
Key Factors to Success
Extensive pre-project planning to reduce project risk Continuous development of human resources to
balance attrition to other industries Completion of design prior to start of work at Site Availability of project management tools to train staff Capable construction and installation contractors Smaller number of contracts minimize interface
complexities Development of “do it right first time” culture
Pg 35
Key Factors to Success
Ability to stop work to enforce quality All Site staff to act as quality surveyors Quality and safety culture accepted at every level All parties worked to international quality programs Effective and productive partnership and team work
through an integrated organization
Pg 36
Concluding Remarks Cernavoda 1 has resulted in reduction of oil imports of
around $150M a year Nuclear technology has introduces a higher level of
technology and QA Success of Unit 1 operation and Unit 2 completion
project has resulted in Romania's decision to complete Units 3 and 4: Project model is joint SNN and private sector investment Interest to invest by major European utilities Project expected to start in 2008 Romanian companies to play leading role in engineering,
construction, commissioning and project management.