0
Projek Menaiktaraf Bayan Lepas Expressway
Dari Batu Maung ke Jambatan Pulau Pinang
PROJECT ORGANIZATION CHART
2
Employer JKSB
Design and Build Contractor UEMB
Consulting Engineer (C & S) RB Perunding Sdn. Bhd.
Consulting Engineer (M & E) RAZ Associates
Contract Sum
RM 359,713,908.80 (Based on Tender Sum Analysis –
19th April 2013)[ RM 15,000,000.00 Provisional Sum for underground utilities relocation at Sungai Tiram]
Effective Date Of Contract TBA
Original Completion Date of Construction TBA
Construction Period Twenty Four (24) Months
CONTRACT INFORMATION
3
Completion Date of Defect Liability Period TBA
Defect Liability Period Twenty Four (24) Months
Liquidate And Ascertained Damages 0.0535%/day
Performance Bond TBA
Contractors All Risk Insurance
a) Policy No. : CCX03374565/64/01/YYY
b) Expiry Date : 14th May 2017
Workmen’s Compensation Insurance
a) Policy No. : LWX/03374566/64/01/YYY
b) Expiry Date : 30th April 2017
CONTRACT INFORMATION (CONT’)
4
The scope of works comprise of construction and completion of
a) 1 No. of Dual Two Elevated Structureb) 1 No. Roundabout at Southbay Junctionc) Road Wideningd) Drainagee) Walkwayf) Pedestriang) Relocation of Utilities and Servicesh) Street Lightingi) Landscapingj) Pavementk) Road Marking and Furniturel) Traffic Sign
PROJECT SCOPE OF WORKS
PROJECT LAYOUT PLAN
6
SUMMARY OF PROGRESS
Activities Completed at Site Actual Start Actual Finish
1. Mapping and Detection of Utilities Works 2-Jan-13 15-Jan-13
2. Total of 26 Boreholes Soil Investigation(Confirming Design)
25-Jan-13 19-Feb-13
3. Dilapidation Survey Works 27-Dec-12 15-Mar-13
4. Signboard Installation Works 12-Mar-13 25-Mar-13
5. Total of 26 Boreholes Soil Investigation(Alternative Design)
13-Apr-13 10-May-13
6. Removal of Trees at Median (CH 1800 – CH 5000)
6-May-13 21-May-13
7. Temporary Road Widening (CH 1800 – CH 5000) 21-May-13 22-Jun-13
8. Installation of Temporary Street Lighting Works(CH 1800 – CH 5000)
9-July-13 7-Aug-13
7
SUMMARY OF PROGRESS (Cont’)
Activities In Progress Total Quantity
Quantity Completed (As of 22nd
Aug 2013)
Actual Start
1. Total of 77 Boreholes Soil Investigation(Alternative Design)
77 35 12-June-13
2. Bored Piling Works 98 - 19-Aug-13 (Test Pile at
Pier P18)
8
SUMMARY OF PROGRESS (Cont’)
Activities In Progress
1. Casting Yard a) Site Clearance completed on 12th August 2013.b) Construction of Hoarding in progress.c) Construction of Internal Road in progress.
2. Batching Plant a) Site Clearing & Platform Preparation completed on 19-July-2013.b) Plant positioning pegging at site and piling works completed on 29-July-2013.c) Civil works-construct plant foundation, Toilet, Lab in progress.
3. Installation of Temporary Cofferdam Caisson in progress.
4. Remove Existing Median in progress. Total length to remove = 3200mTotal length completed remove = 2100m (As of 22nd August 2013)
9
SUMMARY OF PROGRESS (Cont’)
Activities In Progress
5. Protection / Relocation of Services at CH000 – CH525Trial hole (11kV and 33kV) completed on 22-Aug-13 morning. The result will be compiled and submit to TNB for confirmation of cable type.
6. Protection / Relocation of Services at CH5000 – CH6175Trial hole (33kV) in progress. The result will be compiled and submit to TNB for confirmation of cable type.
10
PROGRESS CLAIM
CLAIM AND PAYMENT STATUS
ICP No. 1 RM 2,533,231.00 (For Period Ending May 2013)
ICP No. 2 RM 4,220,263.17 (For Period Ending June 2013)
ICP No. 3 RM 5,123,283.49 (For Period Ending July 2013)
Total Billing to Date : RM 11,876,777.66
Latest Certification : -
Latest Payment Received : -
11
Status
Preliminary Drawings Submitted
DESIGN DEVELOPMENT STATUS
12
Summary of Method Statement for Erection
Note: The information as of 21st August 2013
Method Statement submission and approval
Nos. Remarks
Method Statement issued to RBP 9
Method Statement Accepted / Info by RBP 9
Method Statement Under Review by RBP 0
Method Statement UEMB to resubmit to RBP 0
Method Statement Submitted to JKSB 9
Method Statement Close Out / Info by JKSB 0
Method Statement Pending Close Out by JKSB 3Soil Investigation
Bored Pile Cast In Situ Construction
Bored Pile Testing using O-Cell Test
Method Statement Pending Close Out by UEMB 6
Temporary Widening Existing Road
Temporary Street Lighting Pole
Hacking of Parapet (Temporary works)
Temporary Cofferdam – Caisson
Toe Grouting of Bore Pile In-Situ
Sonic Logging of Bored Pile In-Situ
13
NO.SAFETY, HEALTH &
ENVIRONMENT ACTIVITIESNUMBERS/FREQUENCY PARTIES INVOLVED
1 Safety Meeting Nil Nil
2 Tool Box Meeting 14 Sub Contractors
3 Safety Induction 9 Sub Contractors
4 Safety Training (e.g. fire drill) Nil Nil
5 HSE Improvement Notice Nil Nil
6 HSE Violation Notice 1 Sub Contractors
7 Housekeeping 24/ Daily Sub Contractor
8 Accident/ Incident Nil Nil
9 Penalty Issued Nil Nil
10 Stop Work Order Nil Nil
HSE MONTHLY BRIEF REPORT FOR JULY 2013
14
NO. ACCIDENT/INCIDENT PREVIOUS MONTH THIS MONTH
1 Fatality Nil Nil
2 Injuries Nil Nil
3 Occupational Disease Nil Nil
4Accident / Incident Involving
Machinery Nil Nil
5 Damage Loss of Property Nil Nil
6 Near Misses Nil Nil
TOTAL Nil Nil
SUMMARY OF SAFETY AND HEALTH ISSUES FOR JULY 2013
15
UEMC Statistic of Safety Incident / Accident for the Month of July 2013
0 0 0 0 0 0 0 0 0 0 0 00
1
2
3
4
5
Jan '13 Feb '13 March '13 April '13 May '13 June '13 Jul '13 Aug '13 Sep '13 Oct '13 Nov '13 Dec'13
QU
AN
TIT
Y
MONTH
Note : No accident/incident reported.
16
UEMC Statistic of Environment Incident / Accident for the Month of July 2013
0 0 0 0 0 0 0 0 0 0 0 00
1
2
3
4
5
Jan '13 Feb '13 March '13 April '13 May '13 June '13 Jul '13 Aug '13 Sep '13 Oct '13 Nov '13 Dec'13
QU
AN
TIT
Y
MONTH
Note : No accident/incident reported.
17
Manpower Statistic
Item Description Quantity
1 Total Accident / Incident for the Month 0
2 Total Manpower 97
3 Total Man Days worked 2,328
4 Total Man Hours Worked 23,280
5 Man Hours worked (WLTI) from June 2013 to July 2013 38,640
6 Man Hours worked from June 2013 to July 2013 38,640
7 Number of Lost Time Injury (LTI) from Jan 2013 – June 2013 0
UEMC Safety & Health Performance – July 2013
0
50
100
Jan Mar May Jul Sep Nov
Total Manpower for Year 2013
Manpower
18
ISSUES TO HIGHLIGHT
Status
Letter of Award Pending Issuance
Preliminary Drawings Pending Approval
Land Acquisition Pending from JKSB
19
PROGRESS PHOTOGRAPH
Soil Investigation Works in progress
20
Soil Investigation Works in progress
PROGRESS PHOTOGRAPH
21
PROGRESS PHOTOGRAPH
Installation Temporary Cofferdam Caisson Works in progress
22
Temporary Cofferdam Caisson Works completed at P23
PROGRESS PHOTOGRAPH
23
PROGRESS PHOTOGRAPH
1st Drilling for Bored Piling Works in progress
24
Bored Piling Works in progressSilos for Bored Piling Works
PROGRESS PHOTOGRAPH
25
Construction of Hoarding at Casting Yard in progress
PROGRESS PHOTOGRAPH
26
Cabin for site office casting yard Civil works – construction of plant foundation, EMS, Toilet, Lab and
Batching Plant in progress
PROGRESS PHOTOGRAPH
27
PROGRESS PHOTOGRAPH
Remove Existing Median in progress
28
Trial Hole for TNB cable at CH000 – CH525
PROGRESS PHOTOGRAPH
29
THANK YOU