September 2013
1
Contents
1. Procedure for the Submission of FDPs
2. Presentation of FDPs and Electronic File Instructions
2
After the completion of the Works of the Project Contractor is obliged to submit to DESFA the Final Technical Documentation Package (FDP) of the Project.
The Contractor is collecting and preparing on DESFA ’ s behalf , all the technical documentation related to the Project regardless of the documents issued by other parties.
The technical documents are submitted to DESFA in Final As Built Status. Those documents can be originated by contractor, study group, supplier, inspector , etc . and are submitted in volumes (Final Documentation Packages).
FDP are the Final Technical Documentation of a Contractor / vendor / engineer ,which is separated into volumes containing all types of document s necessary related to a specific activity such as Civil Works, Mechanical Works, Building constructions etc.
3
The final technical documents are separated into the following categories :
1. Documents for Operation and Maintenance - DFOM
“Documents for Operation and Maintenance - DFOM “are the technical documents with information regarding the operation of a system (operating manual ) . Included in this category are the documents that provide instruction for the operation of a project such as the maintenance manual .
2. Quality Records - QR
“Quality Records – QR” are the documents that verify the quality of equipment materials or constructed work . These documents are in conformance with approved standards ( material certificate , welding log book ) .
3. Final “ as built ” documents and drawings - FAB
“Final “ as built ” documents and drawings – FAB” are the final issue of drawings and documents of a project such as various equipment list and drawings regarding a specific section completed ( as - built drawings ) .
4. Retained documents – RD
“Retained documents – RD” are the technical documents regarding the basic study of a project (basic design ) . This category also includes contract articles , basic drawings of the network , calculations , environmental study , etc .
4
1. During the preparation phase of the FDP by the Contractor , the SUPERVISING ENGINEER carries out periodic audits and offers additional instructions to ensure the compliance of the FDP with DESFA Requirements under the responsibility of the Project Manager. The project ‘ s SUPERVISING ENGINEER is responsible for the completeness, correctness and acceptance of all final technical documentation from the Contractor.
DESFA ’s representative ( DCC Manager ) in cooperation with the Project Manager executes
periodic documentation audits during the construction phase of the Project and in
collaboration with the SUPERVISING ENGINEER give proper instruction to ensure
compliance with DESFA Requirements.
Contractor is obligated to adjust his documentation filing system in accordance to the
remarks and suggestions of DESFA’s DCC Manager, Project Manager and Supervising Engineer
and make available any information - documentation requested throughout the project .
5
2. Final Documentation Package Registers – Final Lists – Overall Indexes are submitted by Contractor in advance in electronic format for review and approval by DESFA.
3. The Project ‘ s Contractor delivers the volumes to the Supervision (1 original and 3 copies of the documents are submitted) . The Supervision signs all the detailed FDP Registers. TPI has the obligation to verify the completeness and the correctness of the FDP’s that are under the scope of work of TPI contract with DESFA. During the FDP Audits, DESFA DCC issue a report of which FDP files are according to DESFA Requirements.
4. Contractor submits the approved by Supervision, TPI and DESFA DCC FDP files in physical and electronic format to DESFA DCC . An acceptance protocol is signed by all parties. The delivery , control and acceptance of the FDP can be accomplished in cooperation with Supervision, Project Manager and DESFA / DCC representative for time conservation.
6
All Packages submitted are in binders (files) with transparency folders outside.
The FDP cover sheet identifies the Project, the section, the sub-section, the Contractor, the Supervision Engineer, the contract number, the contracts W.B.S, package description, package number, volume number, total number of volumes, copy number.
The front page is dated and is identifying the Project, the section, the sub-section, the FDP description, the FDP number, the FDP Revision, the FDP revision date
The index is dated and is identifying the Package description, package number, section, sub-section, volume number and for each document the Contractors document number, title, revision number, revision date, status, total number of pages per document and total number of pages per package. The Index is also identifying the computerised file number of each document, if this exists.
The As built drawings in paper are issued to DESFA like all other technical documents, that is in A4 binders (files) folded in A4 size.
7
For the submitted X-ray films a cover page and index is included. The cover page is dated and identifies the unit, section, sub-section, the Km, the number of the box and the first and last joint. The index is also dated and identifies the number of each weld, the X-ray report, the number of the films, the necessary re-shots and the total number of films.
The X-ray films is issued to DESFA together with a radiographic film register, which contains data of the weld, the NDT report, the result, date of test, welder, reference drawings, reference K points, Km, section, sub-section and the box number in which the X-ray is included.
All final technical documents that are required in a computer based format should be in accordance to contract specifications, procedures and agreements concluded between Contractor, Supervision and DESFA. The information in electronic format must always be easily accessible. The Contractor has to ensure that this form of final documentation (documents / drawings) has been properly tested for validity of data, for readability of media (CD – DVD –HARD DISKS) and that all system problems that may occur have been corrected. All technical documents / drawings in digital format have to be identical to the physical hard copy and their file name to reflect the contents so that by the file name for easy recognition of the document / drawing (traceability).
All drawings are in AutoCAD format (.dwg). The drawings are designed in original coordinates.
8
All Final Technical Documentation (Final Documentation Package) are also scanned by Contractor (structured according to the FDP Register) and digital files (TIFF format) are submitted by Contractor for review by Supervising Engineer / Project Manager and final acceptance by DESFA.
All approved Final “As-Built” drawings and the various Lists included in the Final Technical Documentation are submitted to DESFA / Project Manager also in a processable digital file format in standard DXF or DWG format for “AutoCAD” latest release in CD or DVD-ROM’s. The drawings are submitted in standard DXF or DWG format for “AutoCAD” latest release. The lists are submitted in “Microsoft Office Word/ Excel” files.
Final instructions for the type and structure of Final Documentation Packages are given by DESFA’s DCC.
9
LIST OF FINAL DOCUMENTATION PACKAGES CONTRACT TITLE: DETAILED ENGINEERING PROCUREMENT OF MATERIALS & CONSTRUCTION OF THE DESFA'S PROJECT "H.P. NATURAL GAS PIPELINE STEFANI - ALIVERI" CONTRACT NUMBER: ELEM.CODE: HPPL-ALIVERI W.B.S.: 37.53.01.204
HIGH PRESSURE PIPELINE ALIVERI DATE : 20/09/2011 REVISION NUMBER : 1
FDP No. Description Protocol
No. Date to PMN
Date To DEPA
VOL No
Comments
GEN DFOM
HPPL-ALIVERI/ FDP/PL-S/GEN/DFOM/001
BASIC PIPELINE OPERATION & MAINTENANCE MANUAL By DESFA
HPPL-ALIVERI/FDP/PL-S/GEN/DFOM/002
SYSTEM OPERATION & MAINTENANCE MANUAL By DESFA
HPPL-ALIVERI/FDP/PL-S/GEN/DFOM/003
VENDORS MANUALS
OPERATING MANUAL
MAINTENANCE MANUAL SPARE PARTS LIST AND SCHEDULE
HPPL-ALIVERI/FDP/PL-S/GEN/DFOM/004
EFD'S
HPPL-ALIVERI/FDP/PL-S/GEN/DFOM/005
VARIOUS LIST
VALVE LIST
EQUIPMENT LIST INSTRUMENT LIST AND SCHEDULE LIST OF K POINTS
LIST OF MARKER POSTS
LIST OF CROSSINGS LIST OF MEASURING POSTS
PROCUREMENT LIST RECEIVED
PIPE & MATERIAL LIST - SPARE PIECES INSTALLED
GUARANTEE WELD LIST
TELECOMUNICATION CABLE JOINTS LIST NOT APPLICABLE
HDPE JOINT LIST
INSULATING JOINT LIST
LIST OF HOT BENDS
LIST OF FIELD BENDS
LIST OF SADDLES
LIST OF LEVELS OF PIPE AND GROUND TOP BETWEEN SYMBOLS
OF DETAIL DRAWING
CLASS LOCATION LIST 10
LIST OF FINAL DOCUMENTATION PACKAGES CONTRACT TITLE: DETAILED ENGINEERING PROCUREMENT OF MATERIALS & CONSTRUCTION OF THE DESFA'S PROJECT "H.P. NATURAL GAS PIPELINE STEFANI - ALIVERI" CONTRACT NUMBER: ELEM.CODE: HPPL-ALIVERI W.B.S.: 37.53.01.204
HIGH PRESSURE PIPELINE ALIVERI DATE : 20/09/2011 REVISION NUMBER : 1
GEN FAB
HPPL-ALIVERI/FDP/PL-S/GEN/FAB/001 MATERIAL REQUISITIONS
HPPL-ALIVERI/FDP/PL-S/GEN/FAB/002 JOB SPECIFICATIONS
HPPL-ALIVERI/FDP/PL-S/GEN/FAB/003 STANDARD DRAWINGS
HPPL-ALIVERI/FDP/PL-S/GEN/FAB/004 AS BUILT DRAWINGS ,PIPE & WELD LOG BOOK ,VARIOUS LIST ,OVERALL
& DETAIL FDP REGISTER IN COMPUTERIZED FORMAT
GEN QR
HPPL-ALIVERI/FDP/PL-S/GEN/QR/001 QUALITY ASSURANCE MANUAL/PLAN / PROCEDURES
HPPL-ALIVERI/FDP/PL-S/GEN/QR/002 SAFETY MANUAL / PROCEDURES / PLAN
HPPL-ALIVERI/FDP/PL-S/GEN/QR/003 AUDIT REPORT (INTERNAL/EXTERNAL)
HPPL-ALIVERI/FDP/PL-S/GEN/QR/004 NON-CONFORMANCE REPORTS-CORECTIVE ACTION REPORTS /
TECHNICAL QUERIES
HPPL-ALIVERI/FDP/PL-S/GEN/QR/005 W.P.S. & P.Q.R
HPPL-ALIVERI/FDP/PL-S/GEN/QR/006 WELDER QUALIFICATION CERTIFICATES
HPPL-ALIVERI/FDP/PL-S/GEN/QR/007 CERTIFICATE OF NDT OPERATOR
HPPL-ALIVERI/FDP/PL-S/GEN/QR/008 DESTRUCTIVE TEST RECORDS
HPPL-ALIVERI/FDP/PL-S/GEN/QR/009 PIPE & MATERIAL RECEIPT REPORT
HPPL-ALIVERI/FDP/PL-S/GEN/QR/010 PIPE & MATERIAL RELEASE REPORT
HPPL-ALIVERI/FDP/PL-S/GEN/QR/011 INSPECTION DATA BOOKS / PIPE AND MATERIAL CERTIFICATES /
CALIBRATION CERTIFICATES
SUPPLY BY CONTRACTOR
HPPL-ALIVERI/FDP/PL-S/GEN/QR/012 INSPECTION DATA BOOKS / PIPE AND MATERIAL CERTIFICATES /
CALIBRATION CERTIFICATES SUPPLY BY DEPA
HPPL-ALIVERI/FDP/PL-S/GEN/QR/013 PIPE COATING CERTIFICATES BY VENDOR IF SEPARATE
HPPL-ALIVERI/FDP/PL-S/GEN/QR/014 PRECOMMISSIONING RECORDS BY DESFA
TELECOMUNICATION CABLE MEASUREMENT & DIAGRAM OPERATIONAL TEST FOR MOTOR OPERATING VALVES OPERATIONAL TEST FOR PILARS
HPPL-ALIVERI/FDP/PL-S/GEN/QR/015 COMMISSIONING RECORDS BY DESFA 11
LIST OF FINAL DOCUMENTATION PACKAGES CONTRACT TITLE: DETAILED ENGINEERING PROCUREMENT OF MATERIALS & CONSTRUCTION OF THE DESFA'S PROJECT "H.P. NATURAL GAS PIPELINE STEFANI - ALIVERI" CONTRACT NUMBER: ELEM.CODE: HPPL-ALIVERI W.B.S.: 37.53.01.204
HIGH PRESSURE PIPELINE ALIVERI DATE : 20/09/2011 REVISION NUMBER : 1
GEN RD
HPPL-ALIVERI/FDP/PL-S/GEN/RD/001 OVERALL AND DETAIL FDP REGISTER - EDR
HPPL-ALIVERI/FDP/PL-S/GEN/RD/002 CONTRACTUAL DOCUMENT-BASIC DESIGN
HPPL-ALIVERI/FDP/PL-S/GEN/RD/003 STUDIES-CALCULATIONS
HPPL-ALIVERI/FDP/PL-S/GEN/RD/004 DETAILED DESIGN DRAWINGS (AFC)
HPPL-ALIVERI/FDP/PL-S/GEN/RD/005 PERMITS/LICENCES/ACCEPT.CERTIFICATES
HPPL-ALIVERI/FDP/PL-S/GEN/RD/006 DAILY SITE LOG BOOKS
HPPL-ALIVERI/FDP/PL-S/GEN/RD/007 CONSTRUCTION PLANS FOR SPECIAL WORKS - METHOD STATEMENT
HPPL-ALIVERI/FDP/PL-S/GEN/RD/008 FIBRE OPTIC INSTALL. PROTOC. OF WORKS COMPLETION NOT APPLICABLE
HPPL-ALIVERI/FDP/PL-S/GEN/RD/009 MECHANICAL COMPLETION FILE-T.P. INSPECTION CERTIFICATE
HPPL-ALIVERI/FDP/PL-S/GEN/RD/010 CLOSE OUT REPORT BY SV -AND PM
HPPL-ALIVERI/FDP/PL-S/GEN/RD/011 PHOTO DOCUMENTATION FOR PIPELINE & STATIONS
SECTION 6300 FAB
HPPL-ALIVERI/FDP/PL/6300/FAB/001 AS-BUILT DRAWINGS FOR PIPELINE Recording Plans 1:1000)
HPPL-ALIVERI/FDP/PL/6300/FAB/002 AS-BUILT DRAWINGS FOR PIPELINE Longitudinal sections 1:1000)
HPPL-ALIVERI/FDP/PL/6300/FAB/003 AS-BUILT DRAWINGS FOR PIPELINE Detail Drawings 1:200, 1:500)
HPPL-ALIVERI/FDP/PL/6300/FAB/004 AS-BUILT DRAWINGS FOR PIPELINE Longitudinal sections of Detail
Drawings 1:100, 1:200, 1:500)
HPPL-ALIVERI/FDP/PL/6300/FAB/005 AS-BUILT DRAWINGS FOR PIPELINE Maps 1:50000, & Recording plan
1:5000)
HPPL-ALIVERI/FDP/PL/6300/FAB/006 AS-BUILT DRAWINGS FOR STATIONS (Piping
Arrangement & Isometric Piping Arrangement Drawings)
HPPL-ALIVERI/FDP/PL/6300/FAB/007 AS-BUILT DRAWINGS FOR STATIONS (Plot Plans,
Gabion, Reinf. Concrete Retaining Walls)
HPPL-ALIVERI/FDP/PL/6300/FAB/008 AS-BUILT DRAWINGS FOR STATIONS (Area
Classification Drawings)
HPPL-ALIVERI/FDP/PL/6300/FAB/009 X-RAY FILM HAND OVER PROTOCOLS FOR PIPELINE AND STATIONS 12
LIST OF FINAL DOCUMENTATION PACKAGES CONTRACT TITLE: DETAILED ENGINEERING PROCUREMENT OF MATERIALS & CONSTRUCTION OF THE DESFA'S PROJECT "H.P. NATURAL GAS PIPELINE STEFANI - ALIVERI" CONTRACT NUMBER: ELEM.CODE: HPPL-ALIVERI W.B.S.: 37.53.01.204
HIGH PRESSURE PIPELINE ALIVERI DATE : 20/09/2011 REVISION NUMBER : 1
SECTION 6300 QR
HPPL-ALIVERI/FDP/PL/6300/QR/001 MARKING THE ROW
PERMITS FOR WORKS IN ROW ROW PREPARATION REPORTS
HPPL-ALIVERI/FDP/PL/6300/QR/002 PERMITS FOR TRENCHING NOT APPLICABLE
TRENCHING REPORTS
HPPL-ALIVERI/FDP/PL/6300/QR/003 BEDDING REPORTS NOT APPLICABLE
HPPL-ALIVERI/FDP/PL/6300/QR/004 WELDING LOG (DAILY ) NOT APPLICABLE
HPPL-ALIVERI/FDP/PL/6300/QR/005 PIPE AND WELD LOG BOOK (FINAL )
HPPL-ALIVERI/FDP/PL/6300/QR/006 TIE-IN REPORTS NOT APPLICABLE
HPPL-ALIVERI/FDP/PL/6300/QR/007 GUARANTEE WELD
HPPL-ALIVERI/FDP/PL/6300/QR/008 WELDING REPORTS
RADIOGRAPHIC INSPECTION REPORTS ULTRASONIC EXAMINATION REPORTS DYE PENETRANT REPORTS MAGNETIC PARTICLE REPORT
HPPL-ALIVERI/FDP/PL/6300/QR/009 FIELD BENDING CONTROL SHEETS
HPPL-ALIVERI/FDP/PL/6300/QR/010 PIPE COATING REPORTS (FIELD JOINT)
HOLIDAY TEST REPORT
HPPL-ALIVERI/FDP/PL/6300/QR/011 PERMITS FOR LOWERING PIPE NOT APPLICABLE
LOWERING LAYING REPORTS
HPPL-ALIVERI/FDP/PL/6300/QR/012 PERMITS FOR BACKFILLING NOT APPLICABLE
BACKFILLING REPORTS
HPPL-ALIVERI/FDP/PL/6300/QR/013 PERMITS FOR REISTATMENT NOT APPLICABLE
REINSTATEMENT REPORT
HPPL-ALIVERI/FDP/PL/6300/QR/014 PERMITS FOR CROSSING
HPPL-ALIVERI/FDP/PL/6300/QR/015 PROTOCOL FOR AUGER BORED CROSSINGS PERMITS ONLY
HPPL-ALIVERI/FDP/PL/6300/QR/016 BORING REPORT CHECK LISTS,SURVEYING DATA
HPPL-ALIVERI/FDP/PL/6300/QR/017 PROTOCOLS FOR RIVER CROSSINGS PERMITS ONLY
HPPL-ALIVERI/FDP/PL/6300/QR/018 INSTALL. OF HDPE PIPE (CONDUIT)FOR FIBRE OPTIC CABLE
HPPL-ALIVERI/FDP/PL/6300/QR/019 HDPE PIPE TESTS REPORTS (CHECKS)
HPPL-ALIVERI/FDP/PL/6300/QR/020 QUALITY CONTROL FOR CONCRETE WORKS
HPPL-ALIVERI/FDP/PL/6300/QR/021 CONCRETE SADDLES INSPECTION REPORTS
HPPL-ALIVERI/FDP/PL/6300/QR/022 COMPACTION REPORTS
HPPL-ALIVERI/FDP/PL/6300/QR/023 GRANULOMETRIC GRADUATION OF AGGREGATE
HPPL-ALIVERI/FDP/PL/6300/QR/024 PIPELINE HYDROTEST REPORTS / DRYING
HPPL-ALIVERI/FDP/PL/6300/QR/025 QA FORMS & RECORDS FOR STATIONS 13
LIST OF FINAL DOCUMENTATION PACKAGES CONTRACT TITLE: DETAILED ENGINEERING PROCUREMENT OF MATERIALS & CONSTRUCTION OF THE DESFA'S PROJECT "H.P. NATURAL GAS PIPELINE STEFANI - ALIVERI" CONTRACT NUMBER: ELEM.CODE: HPPL-ALIVERI W.B.S.: 37.53.01.204
HIGH PRESSURE PIPELINE ALIVERI DATE : 20/09/2011 REVISION NUMBER : 1
SECTION 6300 RD
HPPL-ALIVERI/FDP/PL-S/6300/RD/001 REINSTATEMENT PROTOCOLS
HPPL-ALIVERI/FDP/PL-S/6300/RD/002 SURVEY WORKS-TECHNICAL DESCRIPTION
TRIANGULATION-DIAGRAM-SOLUTION OF TRIANGULATION
TABLE OF TRIANGULATION POINTS (CORDINATION & LEVELS)
DESCRIPTION & REFERENCE OF TRIAGULATION POINTS
TRIAGULATION POINTS PHOTO DOCUMENTATION
SOLUTION OF POLYGONOMETRY, NOT APPLICABLE
REFERENCE OF POLYGONOMETRY POINTS NOT APPLICABLE
TABLE OF POLYGONOMETRY POINTS (COORDINATES & LEVELS) NOT APPLICABLE
LEVELING-DIAGRAM OF LEVELING POINTS NOT APPLICABLE
DESCRIPTION & REFERENCE OF LEVELING POINTS NOT APPLICABLE
LIST OF GEODETICAL NETWORK NOT APPLICABLE
TABLE OF LEVELING POINTS NOT APPLICABLE
CP CATHODIC PROTECTION
CP-GEN DFOM
HPPL-ALIVERI/FDP/CP/GEN/DFOM/001 C.P. OPERATION & MAINTENANCE MANUAL NOT APPLICABLE
HPPL-ALIVERI/FDP/CP/GEN/DFOM/002 CONFIGURATION DIAGRAM FOR C.P.SYSTEM
HPPL-ALIVERI/FDP/CP/GEN/DFOM/003 KEY-PLAN DRAWINGS FOR C.P. AREAS
HPPL-ALIVERI/FDP/CP/GEN/DFOM/004 VENDORS MANUALS
HPPL-ALIVERI/FDP/CP/GEN/DFOM/005 SPARE PARTS
14
LIST OF FINAL DOCUMENTATION PACKAGES CONTRACT TITLE: DETAILED ENGINEERING PROCUREMENT OF MATERIALS & CONSTRUCTION OF THE DESFA'S PROJECT "H.P. NATURAL GAS PIPELINE STEFANI - ALIVERI" CONTRACT NUMBER: ELEM.CODE: HPPL-ALIVERI W.B.S.: 37.53.01.204
HIGH PRESSURE PIPELINE ALIVERI DATE : 20/09/2011 REVISION NUMBER : 1
CP-GEN FAB
HPPL-ALIVERI/FDP/CP/GEN/FAB/001
MATERIAL REQUISITIONS
HPPL-ALIVERI/FDP/CP/GEN/FAB/002
JOB SPECIFICATIONS
HPPL-ALIVERI/FDP/CP/GEN/FAB/003
STANDARD DWGS
CP-GEN QR
HPPL-ALIVERI/FDP/CP/GEN/QR/001 QUALITY ASSURANCE PROCEDURES
HPPL-ALIVERI/FDP/CP/GEN/QR/002 INSPECTION DATA BOOKS
HPPL-ALIVERI/FDP/CP/GEN/QR/003 NON CONFORMANCE RECORDS IF ANY
HPPL-ALIVERI/FDP/CP/GEN/QR/004 COMMISSIONING RECORDS IF ANY
CP-GEN RD
HPPL-ALIVERI/FDP/CP/GEN/RD/001 BASIC DESIGN
HPPL-ALIVERI/FDP/CP/GEN/RD/002 STUDIES - CALCULATIONS
HPPL-ALIVERI/FDP/CP/GEN/RD/003 DETAILED DESIGN DRAWINGS
HPPL-ALIVERI/FDP/CP/GEN/RD/004 DAILY SITE LOG BOOKS COPY OF ORIGINAL
CP AREA 30 FAB
HPPL-ALIVERI/FDP/CP/AREA 30/FAB/001
AS-BUILT DRAWING
15
LIST OF FINAL DOCUMENTATION PACKAGES CONTRACT TITLE: DETAILED ENGINEERING PROCUREMENT OF MATERIALS & CONSTRUCTION OF THE DESFA'S PROJECT "H.P. NATURAL GAS PIPELINE STEFANI - ALIVERI" CONTRACT NUMBER: ELEM.CODE: HPPL-ALIVERI W.B.S.: 37.53.01.204
HIGH PRESSURE PIPELINE ALIVERI DATE : 20/09/2011 REVISION NUMBER : 1
CP AREA 30 QR
HPPL-ALIVERI/FDP/CP/AREA 30/QR/001 CATHODIC PROTECTION PIN BRAZING & CABLE CONNECTION FOR
MEASURING POST REPORTS
HPPL-ALIVERI/FDP/CP/AREA 30/QR/002 CP PROTECTION,INSTALLATION OF MEASURING POSTS & CABLE
CONNECTIONS RECORD SHEET NOT APPLICABLE
HPPL-ALIVERI/FDP/CP/AREA 30/QR/003 CATHODIC PROTECTION CHECK & CALIBRATION OF POLARIZATION
PROBES REPORT (POST TYPE K9) NOT APPLICABLE
HPPL-ALIVERI/FDP/CP/AREA 30/QR/004 CATHODIC PROTECTION SOIL RESISTIVITY MEASUREMENTS FROM STUDY
HPPL-ALIVERI/FDP/CP/AREA 30/QR/005 CATHODIC PROTECTION TEST REPORTS FOR RIVER CROSSING NOT APPLICABLE
HPPL-ALIVERI/FDP/CP/AREA 30/QR/006 CATHODIC PROTECTION TEST REPORTS FOR ROAD/RAILWAY CROSSINGS
WITH CASING
HPPL-ALIVERI/FDP/CP/AREA 30/QR/007 TEMPORARY C.P. SACRIFICIAL ANODE INSTALLATION MEASUREMENTS
SHEETS
HPPL-ALIVERI/FDP/CP/AREA 30/QR/008 CATHODIC PROTECTION NATURAL POTENTIAL RECORDS SHEETS
HPPL-ALIVERI/FDP/CP/AREA 30/QR/009 CATHODIC PROTECTION GROUNDBED INSTALLATION RECORD SHEETS
HPPL-ALIVERI/FDP/CP/AREA 30/QR/010 CP, TRANSFORMER RECTIFIER INSTALLATION & FUNCTION RECORD
SHEET
HPPL-ALIVERI/FDP/CP/AREA 30/QR/011 CP, AS-BUILT TRANSFORMER RECTIFIER & ANODE BED INSTALLATION
SKETCH
HPPL-ALIVERI/FDP/CP/AREA 30/QR/012 CP, INSULATION JOINT TEST RESULTS
HPPL-ALIVERI/FDP/CP/AREA 30/QR/013 CP, PERMANENT GROUNDING INSTALLATION NOT APPLICABLE
HPPL-ALIVERI/FDP/CP/AREA 30/QR/014 PRECOMMISIONING RECORDS BY DESFA
CP AREA 32 FAB
HPPL-ALIVERI/FDP/CP/AREA 32/FAB/001 AS-BUILT DRAWING
16
LIST OF FINAL DOCUMENTATION PACKAGES CONTRACT TITLE: DETAILED ENGINEERING PROCUREMENT OF MATERIALS & CONSTRUCTION OF THE DESFA'S PROJECT "H.P. NATURAL GAS PIPELINE STEFANI - ALIVERI" CONTRACT NUMBER: ELEM.CODE: HPPL-ALIVERI W.B.S.: 37.53.01.204
HIGH PRESSURE PIPELINE ALIVERI DATE : 20/09/2011 REVISION NUMBER : 1
CP AREA 32 QR
HPPL-ALIVERI/FDP/CP/AREA 32/QR/001
CATHODIC PROTECTION PIN BRAZING & CABLE CONNECTION FOR MEASURING POST REPORTS
HPPL-ALIVERI/FDP/CP/AREA 32/QR/002
CP PROTECTION,INSTALLATION OF MEASURING POSTS & CABLE CONNECTIONS RECORD SHEET
NOT APPLICABLE
HPPL-ALIVERI/FDP/CP/AREA 32/QR/003
CATHODIC PROTECTION CHECK & CALIBRATION OF POLARIZATION PROBES REPORT (POST TYPE K9)
NOT APPLICABLE
HPPL-ALIVERI/FDP/CP/AREA 32/QR/004
CATHODIC PROTECTION SOIL RESISTIVITY MEASUREMENTS FROM STUDY
HPPL-ALIVERI/FDP/CP/AREA 32/QR/005
CATHODIC PROTECTION TEST REPORTS FOR RIVER CROSSING NOT APPLICABLE
HPPL-ALIVERI/FDP/CP/AREA 32/QR/006
CATHODIC PROTECTION TEST REPORTS FOR ROAD/RAILWAY CROSSINGS WITH CASING
HPPL-ALIVERI/FDP/CP/AREA 32/QR/007
TEMPORARY C.P. SACRIFICIAL ANODE INSTALLATION MEASUREMENTS SHEETS
HPPL-ALIVERI/FDP/CP/AREA 32/QR/008
CATHODIC PROTECTION NATURAL POTENTIAL RECORDS SHEETS
HPPL-ALIVERI/FDP/CP/AREA 32/QR/009
CATHODIC PROTECTION GROUNDBED INSTALLATION RECORD SHEETS
HPPL-ALIVERI/FDP/CP/AREA 32/QR/010
CP, TRANSFORMER RECTIFIER INSTALLATION & FUNCTION RECORD SHEET
HPPL-ALIVERI/FDP/CP/AREA 32/QR/011
CP, AS-BUILT TRANSFORMER RECTIFIER & ANODE BED INSTALLATION SKETCH
HPPL-ALIVERI/FDP/CP/AREA 32/QR/012
CP, INSULATION JOINT TEST RESULTS
HPPL-ALIVERI/FDP/CP/AREA 32/QR/013
CP, PERMANENT GROUNDING INSTALLATION NOT APPLICABLE
HPPL-ALIVERI/FDP/CP/AREA 32/QR/014
PRECOMMISIONING RECORDS BY DESFA
17