Successful construction with PERI
Building Rehabilitation, LisbonAdvanced Seminar 26-10-2009
Alexandre Jacinto
PERI Portugal, Queijas
Building Rehabilitation, Lisbon
CITY MAP
3
4
Building Rehabilitation, Lisbon
JOBSITE Location: Av. da Republica ( Main Street ) Height: 59 m High pedestrian flow
5
Building Rehabilitation, Lisbon
SOLUTION PLAN Top View
6
Building Rehabilitation, Lisbon
SOLUTION PLAN Av. da Republica
7
Building Rehabilitation, Lisbon
GENERAL DATA Scaffold Maximum Height = 59 m
Scaffold Total Area = 3342 m²
Scaffold Total Weight = 63091 Kg Scaffold = 18.878 Kg/m²
Assembly Team = 12 PERI workers
Assembly Time = 3 weeks (15 work days) Scaffold moved ≈ 350.50 Kg/day/worker
Scaffold assembled ≈ 18.56 m²/day/worker
Building Rehabilitation, Lisbon
JOBSITE PICTURES
8
Building Rehabilitation, Lisbon
FINAL RESULT
9
Building Rehabilitation, Lisbon
THANK YOU FOR YOUR ATTENTION.
10
Formwork Scaffolding Engineering | www.peri.pt