UC San DiegoNorth Torrey Pines Living Learning Neighborhood
Summer 2018 - Fall 2020 Construction
Rev 8
UC San DiegoNorth Torrey Pines Living Learning Neighborhood
A New CommunityPROJECT INFORMATION
Goals:
Address EnrollmentGrowth
Integrate Living andLearning in oneCommunity
Permanent Home forSixth College
Key Elements
1,636,000 GSF
2,000 UndergraduateBeds
1,200 undergroundparking stalls
General AssignmentClassrooms
Academic Space forDivisions of SocialSciences and Arts &Humanities
Rev 8
UC San DiegoNorth Torrey Pines Living Learning Neighborhood
ResourcesRESOURCES
Rev 8
UCSD Living & Learning Website:livinglearning.ucsd.edu
UCSD Campus Map:maps.ucsd.edu/map
NTPLLN Construction Website:livinglearning.ucsd.edu/construction
NTPLLN Frequently Asked Questions:livinglearning.ucsd.edu/construction/faq
UCSD Transportation Website:transportation.ucsd.edu
UCSD Parking and Shuttle Alert:transportation.ucsd.edu/engage/firsttoknow
UCSD Transportation Virtual Town Hall:transportation.ucsd.edu/engage/virtualtownhall
UCSD Live Shuttle Map:ucsdbus.com/map
Const.Site
UC San DiegoNorth Torrey Pines Living Learning Neighborhood
Trucking Route & Worker Vehicle Route
Summer
2018 2019 2020
Fall Winter Spring Summer Fall Winter Spring Summer
KEY
Trucking Route
Worker Vehicle Route
Construction Site
Contractor Parking
Gen
esee
Ave
La J
olla
Vill
age
Dr
N Torrey Pines Rd
Gilman Dr
Contractor Parking
Trucks from the south willexit I-5 at Gilman Driveand stage on GilmanDrive. Trucks from thenorth will exit I-5 atGenesee Avenue andtravel along North TorreyPines Road.
NOTES
N
Rev 8
UC San DiegoNorth Torrey Pines Living Learning Neighborhood
Off Site Construction Logistics Plan
Summer
2018 2019 2020
Fall Winter Spring Summer Fall Winter Spring Summer
KEY
Contractor Morning ShuttleRoute
Contractor AfternoonShuttle Route
Trucking Route
Alternate Trucking Route
Construction Site Fence
Const.SiteP302
P303
P206
P304
P384
P357
PangeaParking
Structure
Typical Work Hours: 7:00 AM - 3:30 PMMonday - Friday
Construction workers willarrive at the contractorparking area (glider port)5:30 AM - 7:00 AM andshuttle to the constructionsite.
An afternoon shuttle willbe utilized from 3:00 PM - 4:30 PM fromthe site to the glider port.
NOTES
N
Rev 8
ContractorParking
UCSD Parking
UC San DiegoNorth Torrey Pines Living Learning Neighborhood
Shuttle Routes & Available Parking
Summer
2018 2019 2020
Fall Winter Spring Summer Fall Winter Spring Summer
KEY
UCSD West CampusConnector Shuttle Route
Alternate UCSD WestCampus ConnectorShuttle Route DURINGCONSTRUCTION
UCSD South CampusShuttle Route
UCSD SIO Shuttle Route
UCSD Shuttle Stop
UCSD Shuttle StopUnavailable DURINGCONSTRUCTION
PangeaParking
StructureCraig
VenterInstitute
Const.Site
MuirCollege
MuirField
GalbraithHall
FutureOsler
ParkingStructureFall 2018
Veterans AffairsMedical Center
GeiselLibrary
AtkinsonHall
ThurgoodMarshallCollege
HopkinsParking
Structure
P102
P103
P206
P303P304
P302
P310
N
MandevilleCenter
UCSD Shuttle Tracking:
ucsdbus.com/map
Walking Times from theMandeville Center ShuttleStop:
2 Minutes to Faculty Club
3 Minutes to Muir College
4 Minutes to Peterson
NOTES
Rev 8
UC San DiegoNorth Torrey Pines Living Learning Neighborhood
Conditions Prior to the Start of Construction
Summer
2018 2019 2020
Fall Winter Spring Summer Fall Winter Spring Summer
Parking LotP208
Parking LotP207
P302P303KEY
Pedestrian Route
Existing UCSDShuttle Route
Existing UCSDShuttle Stop
N
Rev 8
MUIR COLLEGE LN
UC San DiegoNorth Torrey Pines Living Learning Neighborhood
Conditions During Construction
Summer
2018 2019 2020
Fall Winter Spring Summer Fall Winter Spring Summer
P302P303
KEY
Pedestrian Route
Construction Fence
Periodic Lane Closureswith Traffic Control
UCSD Shuttle StopUnavailable DURINGCONSTRUCTION
N
Construction Hours:
Mon - Fri, 7 AM - 3:30 PM
There will be a 6' tall chainlink fence with green screensurrounding theconstruction site, job sitetrailers, and contractorparking lot at the glider port.
There will be no site lightingafter hours. Contractor willbe required to light the newbuilding's stair towers atnight.
NOTES
Construction Site
Periodic laneclosures duringSUMMERS for
utility work
NewEntrance and
Exit Lanes
Rev 8
NewSidewalk
Periodic laneclosures duringSUMMERS for
utility work
UC San DiegoNorth Torrey Pines Living Learning Neighborhood
Excavation & Early Foundations
Summer
2018 2019 2020
Fall Winter Spring Summer Fall Winter Spring Summer
2021
Fall Winter Spring
Rev 8
UC San DiegoNorth Torrey Pines Living Learning Neighborhood
Late Foundations & Above Ground Structure
Summer
2018 2019 2020
Fall Winter Spring Summer Fall Winter Spring Summer
2021
Fall Winter Spring
Rev 8
UC San DiegoNorth Torrey Pines Living Learning Neighborhood
Above Ground Structure & Building Envelope
Summer
2018 2019 2020
Fall Winter Spring Summer Fall Winter Spring Summer
2021
Fall Winter Spring
Rev 8
UC San DiegoNorth Torrey Pines Living Learning Neighborhood
Building Envelope & Interior Finishes
Summer
2018 2019 2020
Fall Winter Spring Summer Fall Winter Spring Summer
2021
Fall Winter Spring
Rev 8
UC San DiegoNorth Torrey Pines Living Learning Neighborhood
Sitework Completion
Summer
2018 2019 2020
Fall Winter Spring Summer Fall Winter Spring Summer
2021
Fall Winter Spring
Rev 8
SCHOLARS DRIVE
UC San DiegoNorth Torrey Pines Living Learning Neighborhood
Project Completion
Summer
2018 2019 2020
Fall Winter Spring Summer Fall Winter Spring Summer
2021
Fall Winter Spring
N. TORREY PINES ROADMUIR
COLL
EGE DRIV
E
Rev 7