Orange County Public Schools
Site 133-K8-N-6Project Update
Community Meeting February 1st, 2016
WINNER
Orange County Public SchoolsOrange County Public Schools
Site 133-K8-N-6Meeting AgendaFebruary 1st, 2016 Audubon Park Elementary, 6:00 pm
•Welcome – School Board Member: Nancy Robbinson
•Introductions
•Project Update –
•Questions and Answers
•Adjournment
2
Facilities Meeting OrganizerOCPS Program Management TeamGeotechnical Consultant: Ardaman & Associates, Inc.
Orange County Public Schools
Existing – Aerial View
North
3
Orange County Public Schools
Conceptual Site Plan
North
4
Orange County Public Schools
Geotechnical Due Diligence
Geotechnical Engineering – Due Diligence
• History of the Site
5
TH - 19
Orange County Public Schools
Boring Location Plan 6
Date & Total Count
SPT & Auger Borings
Depth (FT)
4/1
6/1
5.
TH
To
tal:
13
TH-1 40TH-7 20TH-9 20
TH-10 20TH-11 20TH-12 20TH-13 20TH-14 20TH-15 20TH-16 20TH-17 20TH-18 20
TH-19 45
9/1
1/1
51
5.
TH T
ota
l: 1
7 ,
AB
To
tal:
7
TH-2 40TH-3 70TH-4 40TH-5 40TH-6 20TH-8 20
TH-20 40TH-21 40TH-22 30TH-23 30TH-24 30TH-25 30TH-26 30TH-27 30TH-28 30TH-29 30TH-30 30AB-1 15AB-2 15AB-3 15AB-4 15AB-5 15AB-6 15
AB-7 15
10
/22
/15
. TH
To
tal:
1,
C
PT
Tota
l: 1
0
TH-3WB 200CPT-1 145
CPT-2 70
CPT-3 70
CPT-4 70
CPT-5 70
CPT-6 100
CPT-7 120
CPT-8 140
CPT-9 135
CPT-10 130
Orange County Public Schools
Geotechnical Due Diligence
Geotechnical Engineering – Due Diligence
• Preliminary Geotechnical Evaluation (Report – May 2015)
• Design Level Interim Evaluation (Reports – September & October 2015)
• Final Report – December 2015
• Findings – Unsuitable Soil Condition for Building Loads (North Side of the Property)
7
Orange County Public Schools
Geotechnical Due Diligence
Geotechnical Engineering – Due Diligence
8
TH – 3
Orange County Public Schools
Additional Geotechnical Due Diligence
Additional Geotechnical Due Diligence• Additional Borings
9
Orange County Public Schools
Additional Geotechnical Due Diligence
Additional Geotechnical Due Diligence
• Ground Penetrating Radar
10
Ground-penetrating radar (GPR) is a nondestructive geophysical method that uses radar pulses to image the subsurface.
Orange County Public Schools
Remedial Plan
Moving Forward
Based on the additional Due Diligence
• Consider Site Plan Redesign Options
• Consider Soil Improvement Options
11
Orange County Public Schools
Completion Date
Demolition – Notice to Proceed 01/28/2016
Demolition of Existing Structures 03/18/2016
Additional Subsurface Soil Exploration & GPR 04/15/2016
Redesign Site Plan & Approvals 08/30/2016
Procure Construction Contract (Bid Day) 10/11/2016
Construction – Notice to Proceed Early 2017
Construction – Substantial Completion Summer of 2018
Tentative Work Plan Timeline 12
Orange County Public Schools
Student Enrollment 13
Student Enrollment
Orange County Public Schools
Schools for 2017-2018 14
Schools for 2017-18Current 2017-18
Audubon Park ES Audubon Park ES
Brookshire ES Brookshire ES
Killarney ES zoned to 133-K8-N-6 Killarney ES
Killarney ES zoned to Lakemont ES Lakemont ES
Fern Creek zoned to 133-K8-N-6 Princeton ES
Current Middle School Current Middle School
Orange County Public Schools
Questions and Answers 15