Code of Practice for Timber Production 2014
Consultation draft of proposed 2019 amendments
Cover Photo
Mountain Ash (Eucalyptus regnans) forest, La Trobe State Forest, Central Highlands of Victoria.
© The State of Victoria Department of Environment, Land, Water and Planning 2019 This work is licensed under a Creative Commons Attribution 4.0 International licence. You are free to re-use the work under that licence, on the condition that you credit the State of Victoria as author. The licence does not apply to any images, photographs or branding, including the Victorian Coat of Arms, the Victorian Government logo and the Department of Environment, Land, Water and Planning (DELWP) logo. To view a copy of this licence, visit creativecommons.org/licenses/by/4.0/ ISBN 978-1-76077-655-8 (pdf) Disclaimer This publication may be of assistance to you but the State of Victoria and its employees do not guarantee that the publication is without flaw of any kind or is wholly appropriate for your particular purposes and therefore disclaims all liability for any error, loss or other consequence which may arise from you relying on any information in this publication.
Accessibility
If you would like to receive this publication in an alternative format, please telephone the DELWP Customer Service Centre on 136 186, or email [email protected] or via the National Relay Service on 133 677, www.relayservice.com.au. This document is also available on the internet at www.delwp.vic.gov.au
Acknowledgment
We acknowledge and respect Victorian Traditional Owners as the
original custodians of Victoria's land and waters, their unique ability to care for Country and deep spiritual connection to it. We honour Elders
past and present whose knowledge and wisdom has ensured the
continuation of culture and traditional practices.
We are committed to genuinely partner, and meaningfully engage, with Victoria's Traditional Owners and Aboriginal communities to support the
protection of Country, the maintenance of spiritual and cultural practices and their broader aspirations in the 21st century and beyond.
2 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
Foreword
Our beautiful forests and ecosystems are fundamental to the health
and wellbeing of all Victorians. They provide clean air, water and a
place for us to connect with our natural environment.
In partnership with Traditional Owners and the community, and
informed by science, the Victorian Government is undertaking a
rigorous and ambitious program of forest management reform to
ensure the best possible outcomes for the environment and
community. In 2018 I requested an Independent Review of Timber
Harvesting Regulation to ensure that timber harvesting is conducted
in such a manner to ensure that environmental, cultural and economic
values of State forests are protected and enhanced. An outcome of
that review includes updating the Code of Practice for Timber Production 2014 (Code) and incorporated
Management Standards and Procedures for timber harvesting operations in Victoria’s State forests
2014.
I am pleased to present a draft Code with updates that focus on creating clear, accurate, and
enforceable regulation for timber production in State forests that is aligned with Government policies
and strategies. The proposed changes mean better enforcement of regulations, greater clarity and
improved compliance by industry.
The proposed changes to the Code formalise the protection of large trees with a diameter greater than
2.5 metres, as I announced in March last year, and protecting the Large Brown Tree Frog in accordance
with its Action Statement. A Regulatory Impact Statement has been developed to ensure these
protections are efficient and effective and uses data and information to calculate the benefits to
biodiversity. The calculated benefits are, of course, just one aspect to consider and do not capture the
full value of protecting these plants and animals.
Large trees provide habitat for a range of hollow-dependant animals including the Greater Glider,
Leadbeater's Possum, Yellow-bellied Glider, Mountain Brush-tailed Possum, Masked Owl, Sooty Owl
and Powerful Owl. The Large Brown Tree Frog is listed as threatened under the Flora and Fauna
Guarantee Act 1988, and in Victoria it has only been found in a small number of sites in East Gippsland.
These proposed protections in the Code require immediate action to ensure large trees and Large
Brown Tree Frogs are protected now and into the future.
This update precedes a more comprehensive review of the Code commencing later this year. The
comprehensive review will be informed by robust science derived from work streams such as the Forest
Protection Survey Program, and broader regulatory and forest management planning reviews.
I invite all Victorians to contribute their views on the draft Code to ensure that forests are effectively
managed now and for future generations. Visit https://engage.vic.gov.au/future-of-our-forests/code-of-
practice for more information and to help shape the future of Victoria’s forests.
The Hon Lily D’Ambrosio MP
Minister for Energy, Environment and Climate Change
Contents
Foreword ....................................................................................................... 2
Glossary: ....................................................................................................... 6
1. General ......................................................................................... 22
1.1. Background ........................................................................................................ 22
1.2. The Code of Practice for Timber Production .................................................. 22
1.2.1 Why a Code of Practice for Timber Production? ............................................ 22
1.2.2 Purpose of the Code .......................................................................................... 23
1.2.3 How is the Code made? .................................................................................... 23
1.2.4 Scope of the Code ............................................................................................. 23
1.2.5 Policy and Laws governing timber harvesting operations in Victoria ......... 23
1.2.6 Application of the Code ..................................................................................... 23
1.2.7 Description of Land to which Code Applies ................................................... 24
1.2.8 Long-term (Strategic) Forest Management Planning ..................................... 25
1.2.9 Compliance on State forest .............................................................................. 26
1.2.10 Compliance on Private Land ............................................................................. 27
1.2.11 Terminology ........................................................................................................ 27
1.3. Code Principles .................................................................................................. 27
2. Code Application – State Forests .............................................. 32
2.1 ***** Revoked ***** (Relevant content moved to Section 1.2.8) ..................... 32
2.2 Environmental Values in State forests ............................................................ 32
2.2.1 Water Quality, River Health and Soil Protection ............................................. 32
2.2.2 Conservation of Biodiversity ............................................................................ 34
2.3 Operational Planning and Record Keeping ..................................................... 35
2.3.1 Operational Planning ......................................................................................... 35
2.3.2 Record Keeping.................................................................................................. 36
2.4 Roading for Timber Harvesting Operations .................................................... 36
2.4.1 Road Planning .................................................................................................... 37
2.4.2 Road Design ....................................................................................................... 37
2.4.3 Road Construction ............................................................................................. 38
2.4.4 Road Maintenance ............................................................................................. 39
2.4.5 Suspension of Haulage ..................................................................................... 39
2.4.6 Road Closure ...................................................................................................... 39
2.5 Timber Harvesting ............................................................................................. 40
2.5.1 Coupe Management ........................................................................................... 40
2.5.2 Coupe Infrastructure ......................................................................................... 41
2.5.3 Operational Restrictions ................................................................................... 42
2.6 Forest Regeneration and Management ........................................................... 42
2.6.1 Regeneration ...................................................................................................... 42
2.6.2 Tending ............................................................................................................... 43
4 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
3. Code Application – Private Native Forests ............................... 44
3.1 Forest Planning .................................................................................................. 44
3.1.1 Timber Harvesting Plan ..................................................................................... 44
3.2 Environmental Values in Private Native Forests ............................................ 46
3.2.1 Water Quality, River Health and Soil Protection ............................................. 46
3.2.2 Conservation of Biodiversity ............................................................................ 49
3.2.3 Forest health ....................................................................................................... 50
3.3 Roading for Timber Production ........................................................................ 50
3.3.1 Road Planning .................................................................................................... 51
3.3.2 Road Design ....................................................................................................... 51
3.3.3 Road Construction ............................................................................................. 52
3.3.4 Road Maintenance ............................................................................................. 52
3.3.5 Suspension of Haulage ..................................................................................... 52
3.3.6 Road Closure ...................................................................................................... 52
3.4 Timber Harvesting ............................................................................................. 52
3.4.1 Timber Harvesting ............................................................................................. 53
3.4.2 Coupe Infrastructure ......................................................................................... 54
3.4.3 Operational Restrictions ................................................................................... 54
3.5 Forest Regeneration and Management ........................................................... 55
3.5.1 Regeneration ...................................................................................................... 55
3.5.2 Stocking Assessment and Remedial Treatment............................................. 55
3.5.3 Tending ............................................................................................................... 56
4 Code Application – Plantations .................................................. 57
4.1 Plantation Planning and Design ....................................................................... 57
4.1.1 Plantation Planning and Design ....................................................................... 57
4.2 Environmental Values in Plantations ............................................................... 58
4.2.1 Water Quality, River Health and Soil Protection ............................................. 58
4.2.2 Conservation of Biodiversity ............................................................................ 59
4.3 Establishment and Management of Plantations ............................................. 60
4.3.1 Site Preparation.................................................................................................. 60
4.3.2 Chemical Usage ................................................................................................. 60
4.3.3 Plantation Health ................................................................................................ 60
4.4 Plantation Roading ............................................................................................ 61
4.4.1 Road Planning .................................................................................................... 61
4.4.2 Road Design ....................................................................................................... 61
4.4.3 Road Construction ............................................................................................. 62
4.4.4 Road Maintenance ............................................................................................. 62
4.4.5 Suspension of Haulage ..................................................................................... 63
4.4.6 Road Closures .................................................................................................... 63
4.5 Timber Harvesting ............................................................................................. 63
4.5.1 Timber Harvesting Plan ..................................................................................... 63
4.5.2 Timber Harvesting ............................................................................................. 64
4.5.3 Plantation Infrastructure ................................................................................... 65
4.5.4 Operational Restrictions ................................................................................... 65
Appendix A ................................................................................................. 66
6 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
Glossary:
‘Action Statement’ means an Action Statement prepared as part of the Flora and Fauna Guarantee
Act 1988 (Vic) for any listed taxon or community of flora or fauna or potentially threatening process as
soon as possible after that taxon, community or process is listed.
‘agroforestry’ means the simultaneous and substantial production of forest and other agricultural
products from the same land unit (defined in the Victoria Planning Provisions).
‘Allocation Order’ means an order made in accordance with Part 3 of the Sustainable Forests
(Timber) Act 2004 (Vic).
‘approved’ means unless otherwise stated means a plan or practice that is:
a) in the case of State forest, approved by the Minister or delegate in accordance with this
Code and its incorporated document; or
b) in the case of private land, approved by the responsible authority (usually local
government) in accordance with a planning scheme or a permit issued under a planning
scheme.
‘Approved road’ means the section of a road or extent of a significant road improvement operation
to be constructed within Special Protection Zone that is authorised by the Minister or delegate.
‘Ash’ means any one or more of Mountain Ash (Eucalyptus regnans), Alpine Ash (Eucalyptus
delegatensis) or Shining Gum (Eucalyptus nitens).
‘Authorised officer’ has the same meaning as in section 3 of the Conservation Forests and Lands
Act 1987 (Vic).
‘basal area’ means the sum of the cross-sectional areas measured at breast height (1.3m) of the
trees in a given stand (or plot). Usually expressed as square metres per hectare (m2/ha).
‘biodiversity’ means the natural diversity of all life: the sum of all our native species of flora and
fauna, the genetic variation within them, their habitats, and the ecosystems of which they are an
integral part.
‘blading-off’ means the use of a machine to sweep drifts of loose mud, slush, vegetation or soil from
the surface of a road or coupe infrastructure (landings etc.).
‘Box Ironbark’ means forest characterised by a canopy of box, ironbark and gum-barked eucalypts,
growing to 25 m in height, over a sparse understorey of wattles, small-leaved and prostrate shrubs,
herbs and grasses. The main trees are White Box (Eucalyptus albens), Red Box (Eucalyptus
polyanthemos), Red Ironbark (Eucalyptus tricarpa), Mugga Ironbark (Eucalyptus sideroxylon),
Yellow Gum (Eucalyptus leucoxylon) and Red Stringybark (Eucalyptus macrorhyncha). In some
areas they may grow with, or be replaced by, Yellow Box (Eucalyptus melliodora), Long-leaf Box,
Silver Bundy (Eucalyptus nortonii), Forest Red Gum (Eucalyptus tereticornis), Coast Grey Box
(Eucalyptus bosistoana), Gippsland Grey Box (Eucalyptus bosistoana), Blue Box (Eucalyptus
baueriana) and Yellow Stringybark (Eucalyptus muelleriana).
‘buffer’ means a protective margin of vegetation excluded from any timber harvesting operations
abutting a waterway or an area of rainforest or other special area or value, which protects it from
potentially detrimental disturbances in the surrounding forest. Buffer width or radius is defined as
horizontal distance from which various timber harvesting operations are excluded.
‘cable harvesting’ means a hauling system using towers, winches, blocks and cables to extract
harvested timber.
‘canopy’ means the uppermost layer of a forest, characterized by the crowns of the trees.
‘Central Highlands FMAs’ means the area of the Central Gippsland, Central and Dandenong FMAs
which fall within the Central Highlands Regional Forest Agreement boundary.
‘chemical control agent’ refer to pesticide.
‘clearfall’ means a silvicultural method of harvesting a coupe whereby all merchantable trees, apart
from those to be retained for wildlife habitat, are removed.
‘Code’ means The Code of Practice for Timber Production 2014.
‘compartment’ means a specific area of State forest usually bounded by natural features. One
compartment is often broken up into several coupes.
‘confluent stream’ means where two or more flowing bodies of water join together to form a single
stream.
‘cording’ means log material, eucalypt and non-eucalypt, with a diameter greater than 15cm placed
in a corduroy fashion on landings and snig tracks to distribute machine loading over a larger area.
‘coupe’, in relation to :
a) State forest, has the same meaning as in the Sustainable Forests (Timber) Act 2004 (Vic);
and
b) private land, means a single area of forest or plantation of variable size, shape and
orientation from which timber is harvested in one operation.
‘coupe diary’ means the key means of communicating and documenting information relevant to the
management of timber harvesting operations and subsequent silvicultural treatment during the life
of a coupe. The coupe diary forms part of the Forest Coupe Plan and entries can be made by the
harvesting entity, the contractor/logging team leader, or additional contractors working during the life
of the coupe.
‘coupe-access road’ means a temporary road constructed to link existing permanent roads to in-
coupe roads, sometimes referred to as a coupe driveway and is considered part of a coupe.
‘coupe infrastructure’ means log landings, log dumps / storage facilities, snigging and forwarding
tracks and boundary trails.
‘crown’ (tree) means the main canopy of a tree, including the main branches and leaves.
‘crown’ (roading) means the slope of a road surface to the outside for drainage.
‘Crown’ (governance) means the State of Victoria.
8 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
‘cultural heritage significance’ means archaeological, anthropological, contemporary, historical,
scientific, social or spiritual significance, and significance in accordance with Aboriginal tradition.
‘dead’ (Leadbeater’s Possum habitat) means a tree that is obviously (physiologically) dead. It must
be self-supporting (rooted into the ground) and would remain standing should any supporting
material be removed. Dead trees must be mature and more than 6 m in height and greater than
1.5 m in diameter at breast height. Dead trees must be one of the Ash species and where species
cannot be determined all dead eucalypts in areas known to be in an Ash area are assumed to be
Ash.
‘Dead’ (other contexts) means a self-supporting (rooted into the ground) tree that is physiologically
dead.
‘delegate’ means a person or role to whom the Minister or Secretary has delegated responsibilities
and functions under Part 2 of the Conservation, Forests and Land Act 1987 (Vic) or has been
authorised by the Minister to consider applications sought in accordance with the Code and the
Management Standards and Procedures.
‘Department’ means the Department of Environment, Land, Water and Planning (DELWP), or its
successor.
‘diameter’ means the width measurement of a tree or log. On a standing tree it is measured at 1.3
m above the upper ground level.
‘domestic’ (firewood) means firewood that is collected for personal use and is not sold to a third party
or used in a commercial enterprise.
‘drainage lines’ means depressions that have visible evidence of periodically flowing water (including
obvious sedimentation or other clear evidence of overland flow) that feed into temporary or
permanent streams. A defined channel may or may not be present. Visible water flow would be
expected after storm events or briefly in the wettest times of the year. Distinctive riparian vegetation
is not likely to be present.
Artificial drainage lines that do not discharge directly into waterways are not considered within the
above definition.
In native forests, drainage lines will generally be protected from harvesting by a filter strip
(Glossary Figure 1). Refer to the Management Standards and Procedures.
Glossary Figure 1 – Drainage Lines in Native Forests
This figure demonstrates the use of filter strips and modified harvesting to minimise soil disturbance within drainage lines. Note:
Diagram not to scale. Zone widths vary according to circumstances.
‘ecologically similar locality’ means from a similar elevation, aspect, soil type and/or climate, as
close as possible to the harvested area.
‘ecological vegetation class (EVC)’ means an area delineated and published by the Department
(available on data.vic.gov.au) that contains one or more native plant communities with similar
floristic, life form and ecological characteristics and represents a grouping of broadly similar
environments such as biogeographic range, and although differing in species, have similar habitat
and ecological processes operating.
‘erosion risk’ means the likelihood of erosion occurring due to soil erodibility, rainfall erosivity,
slope and soil disturbance.
‘even-aged’ means forests or stands that are predominantly of the one age. Usually originating as
a result of a wildfire or timber harvesting activity.
‘exotic’ means introduced to Australia, not native.
‘extraction’ means removing produce from stump to log landing or storage area.
‘exclusion area’ means a term used in this Code to represent specific areas where timber
harvesting operations are excluded in accordance with this Code, as distinct from existing Special
Protection Zones, or areas requiring buffers.
‘existing road’ means a permanent or temporary road of any class that with or without road
maintenance may be used for timber haulage. A road is not considered an existing road if road
construction or significant road improvement operations are required for it to be usable for
haulage.
‘extraction track’ means a track along which logs are extracted from the forest to the roadside or a
landing. Also called a forwarding track or a snig track.
‘fauna’ means any animal including reptiles, birds, mammals, marsupials and fish.
‘fill disposal area’ means a site where surplus soil and rock material produced as a by-product of
road construction may be stockpiled or disposed of.
Channel of drainage line
Harvest Zone Harvest Zone C
h
a
n
n
el Filter strip
(modified harvesting) Filter strip
(modified harvesting)
10 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
‘filter’ or ‘filter strips’ means an area of vegetated ground adjacent to a forest attribute (where
merchantable overstorey may have been removed, if present), designated to minimise soil
disturbance and/or disturbance to the forest attribute. Trees may be felled from within a filter or filter
strip subject to certain conditions, however machinery entry is not permitted unless related to
sanctioned activities.
‘flora’ means any type of plant.
‘floristics’ means the proportion of species and distribution within a particular area.
‘forest’ means an area with a high density of trees typically composed of an overstorey (canopy or
upper tree layer) and an understorey.
‘Forest Coupe Plan’ means a plan that must be prepared for each timber harvesting operation in
State forest, containing a map identifying the area and a schedule incorporating the specifications
and conditions under which the timber harvesting operation is to be administered and controlled.
The coupe diary is considered part of the Forest Coupe Plan.
‘Forest Management Area’ (FMA) means a territorial unit for planning and management of State
forests in Victoria. The approximate location and extent of FMA boundaries are defined by the
Department’s corporate spatial dataset FMA25.
‘Forest Management Zoning Scheme’ (FMZS) means an administrative planning scheme
comprising zones that set priorities and permitted uses in different parts of State forest. The FMZS
is established by the Forest Management Plans, which are working plans pursuant to section 22 of
the Forests Act 1958 (Vic).
‘forest type’ means the classification of forests according to their life form and height of the tallest
trees, projected foliage cover of the tallest trees and the main component species and elevation.
‘forwarding’ means the movement of logs in a forwarder machine.
‘forwarding track’ means an extraction track along which logs are carried in a forwarder.
‘fuel hazard rating’ is as defined by the Department’s Overall fuel hazard assessment guide. For
the purpose of this Code, the forest fire danger index threshold rating is < 50. ‘High’ fuel hazard
rating means a high level of difficulty suppressing a bushfire at forest fire danger index <50, while
‘moderate’ fuel hazard rating means a moderate level of difficulty suppressing a bushfire at forest
fire danger index <50.
‘General Management Zone (GMZ)’ means the component of Forest Management Zoning Scheme
(FMZS) managed for a range of uses and values, with sustainable timber production a major use.
‘Gippsland FMAs’ means the area of the Central Gippsland, North East and Tambo FMAs which
fall within the Gippsland Regional Forest Agreement boundary.
‘gross coupe area’ means the entire coupe area within the coupe boundary including harvesting
exclusions.
‘growth stage’ means the a system used to describe the life cycle of trees based mainly on crown
form – the main growth stages being regeneration, regrowth, mature and senescent.
‘habitat tree’ means a tree identified and protected from harvesting to provide habitat or future habitat
for wildlife. A habitat tree may include living trees or dead stags, and often contains hollows that
are suitable shelter and/or nesting sites for animals such as possums and parrots.
‘harvesting entity’ means an organisation or person responsible for conducting a timber harvesting
operation. In State forest the harvesting entity is either VicForests or the holder of a licence
granted under section 52 of the Forests Act 1958 (Vic).
‘harvesting team leader’ means, on private land, the principal licensee or harvesting contractor, or
a person appointed by the principal licensee or harvesting contractor, responsible for supervising and
controlling the timber harvesting operation in the forest.
‘haulage’ means delivering timber from the coupe to a buyer or transporting timber on a truck to a
place for collection by a buyer or sale to a buyer.
‘heathland’ means ecosystems that are characterised by a dense layer of small-leafed shrubs,
usually 1-2 m tall, over a ground layer of sedges, coarse lilies, rope-rushes, prostrate shrubs and
herbs. In most places there are occasional small, short-trunked, spreading trees, to 15 m tall, which
may form a sparse canopy on deeper soils.
‘historic place’ means a building, a garden, a tree, the remains of a ship or part of a ship, an
archaeological site, a precinct, a site or the land associated with any of these things that has cultural
heritage significance.
‘hollow’ means an opening in the trunk or branches of a tree. Hollows often form after a branch dies
and falls off a tree. Hollows must have an entrance diameter in excess of 4 cm and not have a height
in excess of 30 cm. However in the context of Leadbeater’s Possum habitat hollows are cavities
formed in the trunk or branches of a live or dead tree. They are formed in Ash eucalypt trees through
a variety of processes but are generally related to ageing and decay, although physical injury and
insect damage may also contribute. They vary in size, both in cavity opening diameter and cavity
depth and volume, from small openings of 4 - 8 cm to very large with entrance diameters of 18 - 30
cm or more.
‘hollow bearing tree’, in the context of Zone 1A habitat, means living mature or senescent trees
of Ash eucalypt species containing hollows. Hollow bearing tree in the context of Zone 1B habitat
means dead mature or senescent living trees of Ash eucalypt species containing hollows.
‘in-coupe road’ means a timber extraction road of class 5E or above constructed specifically for use
during harvesting and associated activities and usually closed at the completion of timber harvesting
operations. It is located completely within the approved coupe boundary.
‘landing’ means a place where trees or parts of trees are sorted, processed and/or loaded for
transport from the forest. Areas where there has been no significant soil disturbance associated with
landing establishment, and where no further processing takes place, are not regarded as landings.
Conversion sites that do not involve earthworks or clearing, or where there has been no significant
soil disturbance, are also not regarded as landings.
‘land manager’ means the government department, agency, corporation or statutory authority
responsible for managing public land for or on behalf of the Crown.
‘land owner’ means the person who is the owner or authorised occupier of freehold land.
12 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
‘Landscape sensitivity area’ means areas identified as having a high scenic quality and visual
sensitivity. They are usually areas that are readily visible from high-usage recreational facilities such
as look-outs, walking tracks, tourist roads, or campsites.
‘large tree’ means a living tree of any species that has a diameter at breast height over bark (DBHOB)
equal to or greater than 2.5 metres.
‘local government’ means the relevant Council or Municipal District as defined in the Local
Government Act 1989 (Vic).
‘Management Standards and Procedures’ means the Management Standards and Procedures for
timber harvesting operations in Victoria’s State forests, 2019.
‘managing authority’ means the organisation responsible for the planning and management of a
timber harvesting operation. In State forests, VicForests is the managing authority for timber
harvesting operations.
‘matting’ means smaller head material (branches), bark or other vegetation that is used to cover
cording on snig tracks and landings.
‘mature’ means a growth stage of trees. Mature Ash species have the following characteristics, in
order of assessment priority. Note that no single characteristic defines maturity on its own, although
the first characteristic (apical dominance) holds the most significant assessment weight:
1. Lack of clear apical dominance within the upper crown
2. Presence of permanent shaping branches with diameters at least one third of the bole
diameter at their junction with the bole (clear of collar)
3. Shaping branches are not related either to the presence of long term natural gaps in the
canopy, or to an open grown tree position. In the case of a natural gap, such branches often
occur only on one side of the tree, and the ‘assessment weight’ given to this characteristic
may need to be downgraded (i.e. the need for other indicators increases as part of the
overall assessment)
4. The shaping branches contribute significantly to lateral crown shape and may be competing
with other shaping branches for tree height position, creating a rounded crown appearance
(related to (1) above)
5. Apical dominance will also cease at the shaping branch level (having reached maximum
length), and can induce secondary (epicormic) branch development along shaping
branches, and
6. Some branch death (dieback) and breakage is typical, but not a dominant feature. This loss
of leaf area (photosynthetic capacity) can also induce secondary (epicormic) growth to
replace lost photosynthetic capacity
Diameters of early mature trees may occur between 90 to 200 cm DBHOB, with typical heights of 50
to 100 m. Diameters of full mature trees may be expected between 150 to 300 cm, with typical heights
of 60 to 100 m. This overlap of ranges between trees in different stages indicates why diameter and
height are not good indicators of growth stage.
‘merchantable’ means a tree or part of a tree from which saleable forest produce can be obtained.
‘mature individuals’ when used in reference to flora, means individuals which are capable of
producing reproductive material such as buds, flowers, fruits, cones or seeds. Note that this
terminology is distinct from age classes or growth stages of trees or stands of trees (see mature in
growth stages).
‘microclimate’ means the climate of a small, localised part of a forest. Vegetation, soil conditions and
local topography may create pronounced microclimatic differences.
‘Minister’ means the Minister for Energy, Environment and Climate Change or their successor.
‘mixed species’ means mountain mixed species, alpine mixed species, foothill mixed species and
coastal mixed species.
‘Montane Riparian Thicket (MRT)’ means an area containing at least 40 % canopy cover of
Mountain Tea-tree (Leptospermum grandifolium). Where other rainforest canopy species are
present MRT is sometimes confused with rainforest. However areas with 40 % or more Mountain
Tea-tree canopy cover are defined as MRT not rainforest. Key understorey species typically
consist of a cover of 5 % Mountain Pepper (Tasmannia lanceolata), 1 % Common Bird-orchid
(Chiloglottis gunnii s.l.), 40 % Red-fruit Saw-sedge (Gahnia sieberiana) and Billabomg Rush (Juncus
usitatus), 1 % of at least 2 of either Mountain Club-sedge (Isolepis subtilissima) or tasman Flax-lily
(Dianella tasmanica) or Forest Sedge (Carex alsophila), 20 % of at least 3 of either Common Finger-
fern (Grammitis Billardierei) or Hard Water-fern (Blechnum nudum) or Mother Shield-fern
(polystichum proliferum) or fishbone Water-fern (Blechnum wattsii), 5 % Austral King-fern (Todea
Barbara) or Soft Tree-fern (Dicksonia Antarctica), 1 % Kangaroo Fern (Microsorum pustulatum ssp.
Pustulstum) or Alpine Filmy fern (Hymenophyllum pelatum) and 20 % Bryophytes/Lichens.
‘native forest’ means an area originally naturally occurring, that is dominated by trees having usually
a single stem and a mature or potentially mature stand height exceeding two metres and with existing
or potential crown cover of overstorey strata about equal to or greater than 20 per cent. This definition
includes areas of trees that are sometimes described as woodlands, but does not include plantations
(which may exhibit the characteristics of a native forest but are established for commercial purposes).
‘native vegetation’ means plants that are indigenous to Victoria, including trees, shrubs, herbs and
grasses.
‘net coupe area’ means the gross coupe area less allowances made for harvesting exclusions.
‘net harvested area’ means the net coupe area less areas that were not harvested.
‘new plantation’ means a plantation development where the previous land use was not plantation.
‘North East FMAs’ means the areas of the North East, Benalla-Mansfield and Central FMAs which
fall within the North East Regional Forest Agreement boundary.
‘old growth’ means forest which contains significant amounts of its oldest growth stage - usually
senescent trees - in the upper stratum and has been subject to any disturbance, the effect of which
is now negligible. For a stand to qualify as old-growth, the regrowth growth stage, if present, must
be sparse (less than 10% of the total crown cover of the stand). Negligibly disturbed forest is that
in which disturbance is known to have occurred, but the disturbance is unlikely to have altered the
structure (growth stage and crown cover) or the usual species composition which characterises a
given vegetation class; or, if the alteration did occur in the past, it is no longer measurable.
‘operator’ means a person who conducts a timber harvesting operation. Typically a machine or
chainsaw operator.
14 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
‘Outrows’ means roughly parallel, narrow corridors within a coupe from which all trees are
harvested to allow access and egress by the harvesting machinery.
‘overwood’ means mature trees that are taller than trees at a lower level.
‘overstorey’ means the larger, taller trees in a forest, forming the canopy.
‘permanent road’ means a road or track of class 5E and above, and includes roads, tracks, bridges,
crossings and culverts which are permanently required for the continuing management of the forest,
including timber harvesting operations.
‘permanent stream’ means a river or stream that flows throughout the year. Permanent streams
may stop flowing or dry out in extremely dry years. Permanent streams will support distinctive
riparian vegetation (except where previously removed by human activity, and not including E
camaldulensis), indicative of extended periods of saturation and distinguishable from vegetation
communities in surrounding areas. Streams have a well-defined incised permanent channel. See also
pools and wetlands.
In native forests, permanent streams, pools and wetlands are buffered from harvesting (Glossary
Figure 2). Refer to the Management Standards and Procedures.
Glossary Figure 2 – Permanent Streams, Pools or Wetlands in Native Forests
Permanent streams, pools or wetlands are shown in Figure 2. A saturated zone exists, which is a well-defined incised
permanent channel. These must be protected by a buffer at all times where no harvesting is excluded. Note: Diagram not to
scale. Zone widths vary according to circumstances.
‘pesticide (and/or chemical control agent)’ means a chemical product that is used to control pest
plants or animals. Includes herbicides, insecticides, fungicides, rodenticides and other similar
products. Their registration for sale and use is controlled by State and Commonwealth legislation.
‘permeability’ means the ability of soils to directly absorb water. Soils with high permeability and
low potential for overland flow are able to directly absorb large quantities of water without producing
any significant run-off. These soils will be generally well structured with a friable surface and a high
organic matter content. Soils with low permeability and high potential for overland flow will not readily
absorb heavy falls of rain nor small surface flows of water. The soils will be generally poorly
structured with poorly defined aggregation.
‘planned burning’ has the same meaning as in the Code of Practice for Bushfire Management on
Public Land, 2012.
‘plantation’ means managed stands of trees of either native or exotic species, planted or sown
primarily for timber harvesting operation purposes.
‘Plantation Development Notice’ means a notice that must be prepared and lodged with local
government before a plantation is established for the first time. The notice must contain the
information set out in Section 4.1 of this Code.
Stream, pool or wetland
Saturated Zone Harvest Zone Buffer
(no harvesting) Harvest Zone Buffer
(no harvesting)
‘pool’ means an area of still water of at least 4 metres in diameter within or adjacent to the main
channel of a permanent or temporary stream. A pool may dry out in extremely dry years. In native
forests, pools are buffered from harvesting (refer to Table 2).
‘population’ means a group (2 or more) of individuals of the same species that are demographically,
genetically, or spatially distinct from other groups of individuals.
‘precautionary principle’ means when contemplating decisions that will affect the environment,
careful evaluation of management options be undertaken to wherever practical avoid serious or
irreversible damage to the environment; and to properly assess the risk-weighted consequences of
various options. When dealing with threats of serious or irreversible environmental damage, lack of
full scientific certainty should not be used as a reason for postponing measures to prevent
environmental degradation.
‘private land’, for the purposes of this Code, private land comprises:
i) land alienated from the Crown;
ii) unalienated land of the Crown managed and controlled by a person or body other than the
Minister for Energy, Environment and Climate Change, the Minister for Agriculture, or the
Secretary or their equivalents;
iii) unalienated land of the Crown occupied under a lease from the Crown; or
iv) land licensed or vested under the Victorian Plantations Corporation Act 1993 (Vic).
‘provenance (of seed)’ means the original geographic source or place from which that seed was
obtained.
‘public land’ means unalienated land of the Crown managed and controlled by the Minister for
Environment and Climate Change, the Minister for Agriculture and Food Security, or the Secretary,
whether or not occupied under a licence or other right (but not including land occupied under a licence
under the Victorian Plantations Corporation Act 1993 (Vic)).
‘rainfall erosivity’ means the potential of rainfall to cause soil erosion and is directly related to rainfall
amount and rainfall intensity.
‘rainforest’ means closed (>70 per cent projected foliage cover) broadleaved forest vegetation with
a more or less continuous rainforest tree canopy of variable height, and with a characteristic
composition of species and life forms, of at least 0.1 ha in area and 20 metres width. Rainforest
includes closed transitional and seral communities with emergent eucalypts (including Cool
Temperate Mixed Forest as a recognised subset of rainforest), that are of similar botanical
composition to mature rainforests in which eucalypts are absent.
‘rare’ in so far as it relates to biodiversity, means a group of species that are very uncommon,
scarce, or infrequently encountered.
‘Recovery Team (Regent Honeyeater)’ means a team of experts established to guide, evaluate,
review progress, and implement recommendations which may arise from research under the Regent
Honeyeater Action Statement.
‘regeneration’ (forestry) means the renewal or re-establishment of native forest flora by natural or
artificial means following disturbance such as a timber harvesting operation or fire.
16 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
‘regeneration’ (growth stage) means a growth stage of trees. Eucalypt seedlings that haven’t
reached reproductive maturity (typically less than 10 years old) are classified as regeneration.
‘Regional Forest Agreements (RFAs)’ means agreements between the State of Victoria and the
Commonwealth for the conservation and sustainable management of native forests. The RFAs
provide certainty for forest-based industries, forest-dependent communities and conservation. They
are the result of years of scientific study, consultation and negotiation covering a diverse range of
interests.
‘regrowth’ is a growth stage of trees. Regrowth eucalypts have narrow, conical crowns (pointed)
with relatively high individual crown densities. The majority of branches lie at an acute angle to the
main stem and overall height is still increasing.
‘regularly used sites (Regent Honeyeater)’ means a site known to have been used by Regent
Honeyeaters at some time in at least three of the past six years.
‘rehabilitation’ means the restoration of a site of disturbance usually associated with landings and
other within-coupe infrastructure.
‘reproductive maturity’ means the life stage when an organism can reproduce. In the case of
trees it means when a tree can set enough seed to repopulate the area occupied by the parent tree
if the parent tree were removed. Ash species typically reach reproductive maturity after 10 years
of age.
‘responsible authority’ means the person or body that is specified to be the responsible authority in
accordance with s.13 of the Planning and Environment Act 1987 (Vic).
Note. Generally (but not always) the responsible authority is the local government responsible for
administering the local planning scheme. It is the responsible authority that administers the operation
of the Code on private land and for plantations.
‘restricted access catchments’ means catchments managed by agreement between Melbourne
Water and the Department.
‘retained trees’ means trees retained on a coupe during a timber harvesting operation because
they are unmerchantable, are to serve as seed trees or wildlife habitat trees, or have been selected
to grow on after thinning.
‘riparian vegetation’ means vegetation that requires free or unbound water, or conditions that are
noticeably moist along the margins of streams, drainage lines, and lakes.
‘river health’ means an ecologically healthy river where the major natural features, biodiversity
and/or functions of the river are still present and will continue into the future. Some change from the
natural state may have occurred to provide for human use.
‘road’ means an area of land generally developed for the purpose of the driving or riding of motor
vehicles.
‘road construction’ means the establishment and extension of a new road or new section of road;
this does not include road maintenance or significant road improvement on already existing
temporary or permanent roads.
‘road maintenance’ means works designed to restore the serviceability of the surface, drainage and
verges of an existing temporary or permanent road to the condition of its original road class and
within the original road footprint. Road maintenance works include:
I. Grading / re-forming road carriage way surface;
II. Re-surfacing / re-sheeting / or armouring carriage way surface with rock;
III. Clearing table-drains and culverts to maintain water runoff;
IV. Blading off of roads, where measures are in place to prevent adverse impacts on water quality;
and
V. the management of sight lines and road drying by the cutting of vegetation within the road
verge to the maximum allowable width for original intended road class.
‘road works’ includes road construction, significant road improvement operations and road
maintenance.
‘rotation’ means the planned number of years between the regeneration of a forest stand and its
final harvesting, taking into account the full range of values and uses the owner wishes to derive from
the forest.
‘run-off' with regard to road construction means a short graded channel angled away from road
edges to divert road drainage water off the road into undisturbed vegetation. Sometimes called a
mitre drain.
‘salvage harvesting operation’ means timber harvesting operations conducted to recover timber
following wildfire, storms, floods, disease, insect attack or other events that cause significant tree
mortality or damage.
‘sanctioned’ means an action or practice that has been assessed and approved by the managing
authority unless otherwise stated.
‘sanctioned road’ means a road authorised by the managing authority to be constructed for the
purpose of coupe access within buffers or filters identified in a forest coupe plan.
‘saturation’, associated with waterways, means the area where the soil is muddy or permeated with
water attributable to the water body. The saturation zone ends where moisture is no longer visibly
present in the soil. This saturation zone is often delineated by riparian vegetation.
‘Seasonally Closed Road’ means a road which is temporarily closed on a seasonal basis usually for
environmental reasons, under s21 (1) of the Forests Act 1958 (Vic).
Note: the Department, as a registered State road authority, may also close a roadway or pathway, or
part of a roadway or pathway, for a particular period during the year under provisions in the Road
Management Act 2004 (Vic)
‘Secretary’ means the body corporate established by Part 2 of the Conservation, Forests and Lands
Act 1987 (Vic).
‘seed tree’ means a tree retained on harvested coupes to provide seed for natural regeneration of
that coupe. May also be a habitat tree.
18 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
‘seed tree harvesting’ means an even-aged silvicultural system in which all live trees are felled apart
from a number of uniformly distributed trees retained to provide seed for regeneration and habitat.
Seed trees generally comprise 10-15 % of the basal area of the original stand.
‘selective harvesting’ means a silvicultural system used to harvest and regenerate particular forest
types. Trees are harvested either singly or in small groups at intervals indefinitely. Regeneration is
established continually in the gaps produced and an uneven-aged stand is maintained.
‘senescent’ means a growth stage of trees. Senescent eucalypts are characterised by dead
branches and declining crown leaf area, with the trunk of the tree likely to contain burls and bumps.
The top of the tree is invariably broken off with the remaining crown more than 95 % secondary,
being composed of branches of epicormic origin.
‘shelterwood coupes’ means an area that is harvested using the shelterwood silvicultural method
where the original stand is removed in two separate timber harvesting operations. Firstly a
proportion of the mature trees are cut to allow the establishment of essentially even-aged
regeneration under sheltered conditions (this is called Shelterwood 1), followed by a second cut
(usually about 10 years later) of the remainder of the mature (seed) trees (this is called Shelterwood
2).
‘significant road improvement operations’ means operations on an existing road that
• improve the road to a higher road classification (e.g., 5D to 5B); and/or;
• correct excess adverse (uphill >10%) and/or favourable (downhill >15%) road grades;
and/or
• widens and/or correct the geometry of existing corners beyond the minimum clearance
widths of a higher road class; and/or
• requires removal of native vegetation greater than the following thresholds:
o 0.5 ha of native vegetation in an EVC with Bioregional Conservation Status of
Endangered, Vulnerable or Rare: and
o 1 ha of native vegetation in an EVC with Bioregional Conservation Status of
Depleted or Least Concern.
In general these works include operations such as major resurfacing, major corner widening,
significant bridge or other stream crossing structure works, including bridge replacement.
‘silviculture’ means the science and practice of managing harvesting, forest establishment,
composition, and growth, to achieve specified objectives.
‘site preparation’ means the preparation of the ground to provide conditions suitable for seedling
establishment by either seed or planted seedlings.
‘Sites of Significance for Rainforest’ means areas designated by the Department as containing
the most significant rainforest stands.
‘snigging’ means the towing or winching of a log from the stump to the landing site, usually along a
snig track.
‘snig track’ means the track along which a log is snigged.
‘soil erodibility’ means the susceptibility of a soil to erosion when exposed and/or disturbed.
Classified into low, medium or high according to prescribed techniques.
‘Special Management Zone (SMZ)’ means a component of Forest Management Zoning Scheme
(FMZS) which are managed to conserve specific features and values, while catering for sustainable
timber production and other utilisation activities under certain conditions, specified in SMZ plans.
‘Special Protection Zone (SPZ)’ means a component of Forest Management Zoning Scheme
(FMZS) which are managed primarily for conservation values, forming a part of Victoria’s
Comprehensive, Adequate and Representative reserve system. Timber harvesting operations are
generally excluded from SPZ.
‘Special Water Supply Catchment’ means land declared to be a special water supply catchment
area under Division 2 of Part 4 or otherwise listed in Schedule 5 of the Catchment and Land Protection
Act 1994 (Vic), subject to any relevant amendments or revocations published in the Government
Gazette.
‘stand’ means a group of trees in a forest that can be distinguished from other groups on the basis
of age, species composition, condition, etc. Usually at least 1 ha in size.
‘State forest’ has the same meaning as in the Forests Act 1958 (Vic) and any other category of public
land where timber harvesting operations are a permitted land use but does not include land
occupied under a licence under the Victorian Plantations Corporation Act 1993 (Vic).
‘stocking’ means a measure of density of any given forest stand, which can be expressed in a
variety of terms, such as the number of trees per hectare, the basal area per hectare, and the
percentage of stocked plots.
‘temporary effluent’ has the same meaning as temporary stream.
‘temporary road’ means a road or track and any associated bridges, crossings and culverts that does
not form part of the permanent road network. A temporary road is usually constructed for the purpose
of accessing a coupe(s) (or part thereof) to undertake a timber harvesting operation and will be
closed and rehabilitated on the completion of the timber harvesting operation in that coupe(s). A
temporary road can include in-coupe roads and coupe access roads or driveways.
‘temporary stream’ means a stream that has a clearly defined continuous channel or streambed and
flow during certain seasonal periods of the year, such as following snowmelt, but not throughout the
year. Temporary streams contain distinctive riparian vegetation (except where previously removed
by human activity, and not including E camaldulensis), indicative of periods of saturation and
distinguishable from vegetation communities in surrounding areas. Note: in native forests,
temporary streams may be protected from harvesting by buffers or filter strips (Figure 3). Refer to
the Management Standards and Procedures.
Figure 3 – Temporary Streams in Native Forests
Saturated
Zone Buffer (no
harvesting) or Filter
(modified harvesting) Harvest Zone Harvest Zone
Channel of temporary stream
Buffer (no harvesting)
or Filter
(modified harvesting)
20 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
Temporary Streams have a clearly defined continuous channel or streambed, that flows subject to seasonal periods throughout
the year. These may be protected by a buffer where harvesting is excluded. Note: Diagram not to scale. Zone widths vary
according to circumstances.
‘tending’ means the treating of a forest stand to protect, maintain, or improve its stand health and/or
timber production potential. Thinning and selective harvesting are types of tending.
‘thinning’ means the removal of part of a forest stand or crop, with the aims of increasing the growth
rate and/or health of retained trees and, in commercial thinning, obtaining timber from trees that
would otherwise eventually die before final harvest. Thinning is a type of tending.
‘timber’ means a general term used to describe standing trees or felled logs before processing into
wood products. This includes timber from trees or parts of trees which are specified as available for
timber harvesting operations, but does not include firewood collected for domestic use.
‘timber harvesting operation’ has the same meaning as in the Sustainable Forests (Timber) Act
2004 (Vic).
‘Timber Harvesting Plan’ means a plan prepared under this Code for private native forests (Section
3.1.1) and plantations (Section 4.5.1), usually consisting of a map identifying the area(s) to be
harvested and a statement of conditions applying to the timber production activity, and lodged with
the responsible authority. The plan may apply to a single coupe or to an area in which a number of
coupes are to be harvested.
‘timber release plan’ has the same meaning as timber release plan defined in the Sustainable
Forests (Timber) Act 2004 (Vic).
‘understorey’ means the layer of vegetation that grows below the canopy formed by the tallest trees
in a forest.
‘uneven-aged’ means forests or stands where at least two distinct age groups of trees are present.
‘verified’ means verified by the Department according to established survey standards.
‘VicForests’ has the same meaning as it has in the Conservation, Forests and Lands Act 1987 (Vic).
‘water supply protection area’ means a catchment from which water is used for domestic water
supply purposes, and includes Special Water Supply Catchments, designated catchments identified
in forest management plans and catchments protected under the statutory planning provisions in the
Planning and Environment Act 1987 (Vic).
‘waterway’ includes (but is not limited to) a permanent stream, temporary stream, drainage line,
pool or wetland as those terms are defined in this Code.
‘wetland’ means a permanent spring, swampy ground, wetland or other body of standing water. A
wetland may dry out seasonally. A wetland will support distinctive riparian vegetation (not including
E camaldulensis), indicative of extended periods of saturation and distinguishable from vegetation
communities in surrounding areas.
‘wildlife’ has the same meaning as in the Wildlife Act 1975 (Vic).
‘wildlife corridor’ means a strip of forest of varying width reserved from harvesting, to facilitate fauna
movement (including gene movement) between patches of forest of varying ages and stages of
development.
22 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
1. General
1.1. Background
Wood products have long been harvested from our native forests. Over the past several decades,
other users and uses of forests, such as biodiversity protection, clean water and recreation
opportunities have become increasingly important to the community. An expanded network of national
parks and other conservation reserves has been declared in areas that were once available for timber
harvesting, and public scrutiny of timber harvesting operations is now acknowledged as integral to
the right to use this natural resource.
Plantations are now the largest producer of timber in Victoria. Plantations provide commercial returns
while potentially improving the health of catchments, diversifying farm income or providing another
productive use for agricultural land.
Victoria has benefited significantly from a long period of scientific research and field-based forest
management experience. As knowledge of forest ecosystems continues to develop, there will be a
corresponding improvement in the management of forests that will ensure activities are undertaken
within sound ecological limits to ensure a sustainable long-term path for this industry.
In 1989, the Victorian Parliament ratified the first Code of Forest Practices for Timber Production. The
Code set out standards for timber harvesting operations in State forests, to better manage the
potential impacts of timber harvesting. The Code was revised in 1996 to take account of new research
information, field experience over the previous six years, and the implementation of the Code on private
land in late 1993. The Code was further reviewed and published in 2007 and 2014.
In 2018, at the request of the Minister for Energy, Environment and Climate Change, the Department
commissioned an independent review of timber harvesting regulations to ensure that environmental,
cultural and economic values of State forests are protected and enhanced for future generations. The
review panel developed a report outlining 14 recommendations, all of which were accepted in full by
the Department. Recommendation 10 of the report outlined the need to improve regulatory tools,
including by engaging with stakeholders to develop a common understanding of the Code. As such,
the 2019 proposed variations of the Code aim to provide greater regulatory certainty and improve
environmental outcomes. This variation of the Code builds on previous reviews, further clarifying the
legal requirements of the managing authority, harvesting entities and operators when conducting
and planning timber harvesting operations. The objectives of the 2019 Code variation are to ensure
it is clear, accurate, enforceable and aligned to existing commitments. The Code will continue to be
reviewed on a regular basis, informed by a comprehensive review of relevant forestry science.
1.2. The Code of Practice for Timber Production
1.2.1 Why a Code of Practice for Timber Production?
Maintaining the benefits to society provided by the timber industry depends on balancing community
needs and concerns with careful stewardship and responsible management. The effective
implementation of a Code helps to ensure that timber production is compatible with the conservation of
the wide range of values associated with forests, and of any such values associated with land on which
commercial plantation development is proposed.
1.2.2 Purpose of the Code
The purpose of the Code is to provide direction to the managing authority, harvesting entities and
operators to deliver sound environmental performance when planning for and conducting commercial
timber harvesting operations in a way that:
• permits an economically viable, internationally competitive, sustainable timber industry;
• is compatible with the conservation of the wide range of environmental, social and cultural
values associated with forests;
• provides for the ecologically sustainable management of native forests proposed for
cyclical timber harvesting operations; and
• enhances public confidence in the management of timber production in Victoria's forests
and plantations.
1.2.3 How is the Code made?
The Code is made by the Minister under Part 5 of the Conservation Forests and Lands Act 1987 (Vic).
As the Code is a prescribed legislative instrument under the Subordinate Legislation (Legislative
Instruments) Regulations 2011 the Subordinate Legislation Act 1994 (Vic) also applies to the making
of the Code.
1.2.4 Scope of the Code
The Code applies to the planning and conducting of all commercial timber production and timber
harvesting operations on both public land and private land in Victoria. Timber harvesting
operations are defined in the Sustainable Forests (Timber) Act 2004 (Vic) as any felling, cutting,
removing and haulage activities carried out for the purposes of sale or processing and sale of timber.
The Code does not apply to the collection or production of firewood for domestic use. Unless stated
otherwise, any haulage, road construction, significant road improvement or road maintenance
works, tending, regeneration or rehabilitation activities conducted in association with a timber
harvesting operation are by definition, also a timber harvesting operation.
1.2.5 Policy and Laws governing timber harvesting operations in Victoria
Timber harvesting in Victoria is governed by a wide range of Commonwealth and State legislation,
regulations and policies. The Code addresses the legal obligations that the managing authority,
harvesting entities and operators must comply with during the planning and conducting of timber
harvesting operations in addition to existing relevant law. Therefore, the Code does not duplicate the
legal obligations of the managing authority, harvesting entities and operators already existing in
Commonwealth or State legislation including the relevant laws (legislation) listed in the Conservation,
Forests and Lands Act 1987 (Vic). Appendix A provides a list of the existing legislation, regulations and
policies that apply to timber harvesting operations that are in addition to the Code. Appendix A is
not an exhaustive list.
1.2.6 Application of the Code
This Code and any document incorporated into this Code (including the Management Standards and
Procedures) apply only to the managing authority, harvesting entities and operators.
24 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
1.2.7 Description of Land to which Code Applies
The Code applies to all land in the State of Victoria that is either being used for or is intended to be
used for timber production or timber harvesting operations.
On public land, the land to which this Code applies is State forests (Chapter two). On private land
and leased Crown land, (chapters three and four), the land to which this Code applies includes land
occupied under a licence under the Victorian Plantations Corporation Act 1993 (Vic), land alienated
from the Crown, unalienated land of the Crown occupied under a lease from the Crown, or unalienated
land of the Crown managed and controlled by other than the Minister for Environment, Energy and
Climate Change, the Minister for Agriculture, or the Secretary.
The Code does not apply to domestic firewood collection or production, agroforestry, windbreaks or
other amenity plantings, or to the occasional felling of trees for local uses on the same property or by
the same landowner or manager. Small plantations and woodlots of five hectares or less (total area
existing or proposed on contiguous land which is in the same ownership) are also exempt from the
Code, as are plantings established for non-commercial purposes. The Code does not apply to
revegetation conducted for the purposes of erosion or salinity control.
The Secretary to the Department is a referral authority for timber harvesting operations applications
as specified in Clause 66 of the Victoria Planning Provisions (VPPs) and all planning schemes. The
Code is consistent with the VPPs in recognising that plantations are established primarily for timber
harvesting operations. Thus, planning controls concerned with the development of plantations
explicitly allow for their subsequent management and harvesting.
Figure 4: Indicative map of forest management areas relevant to the Code.
Several administrative management and planning and forest management areas exist across Victoria. These are
important as they identify use of land and the how these areas of forest are managed.
1.2.8 Long-term (Strategic) Forest Management Planning
As a matter of broad policy, sound planning ensures that the full range of State forest values are
managed sustainably for current and future generations. These values include ecological diversity,
cultural heritage, landscape, provision of recreation and educational opportunities as well as a range of
renewable forest products. It is important to ensure that forest management is responsive to changing
community expectations, expanding knowledge of forest ecosystems and techniques to improve
planning approaches.
Long-term (strategic) forest management planning is undertaken in accordance with legislation and
processes such as Regional Forest Agreements (RFA’s) and includes outputs like policies relating to
specific forest values (e.g. threatened species) and forest management plans.
The Forest Management Zoning Scheme (FMZS) is a product of broad strategic planning and is a
spatial representation of forest values which are managed in Victoria’s State forests. The FMZS seeks
to achieve a balance between a range of value inputs, conservation and forest use objectives, including
consideration of legislative and policy constraints.
The FMZS identifies three management zones within State forest: the Special Protection Zone (SPZ);
the Special Management Zone (SMZ); and the General Management Zone (GMZ). SMZs are
managed to conserve specific features and values, while catering for sustainable timber production and
other utilisation activities under certain conditions, specified in SMZ plans. SPZs are managed primarily
for conservation values, forming a part of Victoria’s Comprehensive, Adequate and Representative
26 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
reserve system. Timber harvesting operations are generally excluded from SPZ. GMZs are managed
for a range of uses and values, with sustainable timber production a major use.
Long-term forest management planning aims to maintain an ecologically sustainable timber resource
that mitigates the impacts on all forest values. Effective and inclusive long-term forest management
planning processes provide the setting for which the Code and the Management Standards and
Procedures have been established, and seek to:
- provide for the perpetuation of native biodiversity;
- maintain a range of forest age classes and structures;
- identify and mitigate impacts on all cultural heritage values;
- minimise impact on water quality and quantity within any particular catchment;
- minimise adverse visual impact in landscape sensitivity areas; and
- facilitate effective regeneration of harvested forest.
1.2.9 Compliance on State forest
Under the Sustainable Forests (Timber) Act 2004 (Vic), compliance with this Code is mandatory for any
person planning for or conducting a timber harvesting operation on State forest. Penalties for non-
compliance may apply if timber harvesting operations on State forest are not in accordance with the
Code.
Timber harvesting operations on public land other than State forest are governed by lease and
licence conditions which may specify a requirement to comply with this Code.
The Code is a prescribed legislative instrument made and enforced under relevant law listed in the
Conservation, Forests and Lands Act 1987 (Vic). For the purposes of each relevant law the Secretary
is an authorised officer and is therefore responsible for ensuring compliance with the Code on State
forest. The Department’s Chief Conservation Regulator may be delegated by the Secretary to
discharge these responsibilities and monitor compliance with authorised officers appointed by the
Secretary pursuant to the Conservation, Forests and Lands Act 1987 (Vic).
Certification schemes
In addition, timber producers on State forest may choose to adopt independent product accreditation
under national and international systems, which have associated performance criteria and auditing
requirements that meet or exceed the requirements of this Code.
Incorporated Documents
The Management Standards and Procedures for timber harvesting operations in Victoria’s State forests
2019 (Management Standards and Procedures) are incorporated into this Code to provide detailed
mandatory operational instructions, including region specific instructions for timber harvesting
operations in Victoria’s State forests.
The Management Standards and Procedures are consistent with the Operational Goals and
Mandatory Actions of this Code and must be complied with for timber harvesting operations in
Victoria’s State forests.
The Management Standards and Procedures are informed by relevant policy documents including
policies relating to specific forest values such as threatened species, guidelines and strategies within
forest management plans made under the Forests Act 1958 (Vic) and Action Statements made under
the Flora and Fauna Guarantee Act 1988 (Vic). The Management Standards and Procedures replace
any directions relating to timber harvesting operations contained within these documents.
1.2.10 Compliance on Private Land
Timber production is a defined land use in the VPPs and all planning schemes. Clause 53.11 specifies
the provisions relating to timber production and this Code is an incorporated document which must
be considered.
Local government is responsible for ensuring compliance with the planning system. The Code must
be complied with to the satisfaction of the responsible authority (usually local government),
whether or not a permit is required.
Certification schemes
In addition, timber producers on private land may choose to adopt independent product accreditation
under national and international systems, which have associated performance criteria and auditing
requirements that meet or exceed the requirements of this Code.
Associated Documents
The Management Guidelines for the Code of Practice for Timber Production on Private Land (native
vegetation and plantations) in Victoria (MGs) aid interpretation of the Code on private land and
plantations. The MGs are consistent with the Operational Goals and Mandatory Actions of this Code.
Variations to the MGs must address the Operational Goals and Mandatory Actions of this Code.
1.2.11 Terminology
The following terms are used in the Code to provide a structure for the Code’s intended outcomes and
the mechanisms within the Code to achieve these. The glossary provides further definitions.
A Code Principle is a broad outcome that expresses the intent of the Code for each aspect of
sustainable forest management.
An Operational Goal states the desired outcome or goal for each of the specific areas of timber
harvesting operations, to meet the Code Principles.
Mandatory Actions are actions to be conducted in order to achieve each operational goal. The
Managing authority, harvesting entities and operators must undertake all relevant mandatory
actions to meet the objectives of the Code. Mandatory Actions are focussed on practices or activities.
Failure to undertake a relevant Mandatory Action would result in non-compliance with this Code.
1.3. Code Principles
Timber production on all native forest and plantations in Victoria are guided by the Code Principles
described in Table 1. The Code Principles express the broad outcomes of the intent of the Code for
each aspect of sustainable forest management.
The six Code Principles are developed from the internationally recognised Montreal Process criteria,
and are consistent with the objectives of the Sustainability Charter for Victoria's State forests. Reporting
mechanisms such as Victoria's State of the Forests Report use the same principles, and demonstrate
Victoria's commitment to being an international leader in sustainable forest management.
The six Code Principles are that:
28 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
1. Biological diversity and the ecological characteristics of native flora and fauna within forests
are maintained.
2. The ecologically sustainable long-term timber harvesting capacity of forests managed for
timber harvesting is maintained or enhanced.
3. Forest ecosystem health and vitality is monitored and managed to reduce pest and weed
impacts.
4. Soil and water assets within forests are conserved. River health is maintained or improved.
5. Cultural heritage values within forests are protected and respected.
6. Planning is conducted in a way that meets all legal obligations and operational requirements.
Timber production must always be planned and conducted according to knowledge developed from
research and management experience so as to achieve the intent of the Code Principles. Application
of this knowledge will ensure that timber can continue to be utilised while ensuring that impacts on soil,
water, biodiversity, forested landscapes and significant archaeological, historic and other cultural
heritage sites are avoided or minimised.
In Table 1, the Operational Goals of the Code are aligned with each Code Principle. These Operational
Goals are repeated in the body of the Code, with a variety of Mandatory Actions to achieve each Goal.
This framework translates the high level Principles into on-ground action.
Table 1 Relationship between Code Principles and Operational Goals
These high level operational principles each relate to achievable operational goals on the ground.
Code Principles Operational Goals Section
Biological diversity and ecological characteristics of native flora and fauna within forests is maintained.
Timber harvesting operations in State forests specifically address biodiversity conservation risks and consider relevant scientific knowledge at all stages of planning and implementation.
Timber harvesting operations in private native forests specifically address the conservation of biodiversity, in accordance with relevant legislation and regulations, and considering relevant scientific knowledge at all stages of planning and implementation.
2.2.2 and 3.2.2 Conservation
of Biodiversity
1.2.8, 2.3.1 Operational
Planning and 3.1.1 Forest
Planning
Chemicals are only used where appropriate to the site conditions and application is conducted with due care for the maintenance of forest health, water quality, biodiversity and soil values.
Fertiliser and chemicals are only used where appropriate to the site conditions and circumstances and with care for the maintenance and protection of water quality, biodiversity, soil values and neighbouring land uses.
2.2.2 and 3.2.2 Conservation
of Biodiversity
4.3.2 Chemical Usage
Planning and implementation of timber harvesting operations in plantations address the conservation of biodiversity, including rainforest, in accordance with relevant laws.
4.2.2 Conservation of
Biodiversity
Harvested native forest is managed to ensure that the forest is regenerated and the biodiversity of the native forest is perpetuated.
The natural floristic composition and representative gene pools are maintained when regenerating native forests by using appropriate seed sources and mixes of dominant species.
2.2.2 and 3.2.2 Conservation
of Biodiversity
2.6.1 and 3.5.1 Regeneration
The ecologically sustainable long-term timber production capacity of forests managed for timber harvesting operations is maintained or enhanced.
Timber harvesting operations are planned and conducted to maintain a long-term ecologically sustainable timber resource.
1.2.8, 2.3.1 Operational
Planning
Harvested native forest is managed to ensure that the forest is regenerated and the biodiversity of the native forest is perpetuated.
2.6.1 and 3.5.1 Regeneration
Stocking and early seedling growth is monitored and remedial action is taken where necessary to successfully regenerate harvested areas of native forests.
3.5.2 Stocking Assessment
and Remedial Treatment
Timber harvesting operations are recorded in a way that facilitates future public reporting and policy purposes.
2.3.3 Record Keeping
30 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
Code Principles Operational Goals Section
The productive capacity and other values of the forest are maintained or enhanced by appropriate tending of stands.
2.6.2 and 3.5.2 Tending
The planning and management of permanent and temporary roads for timber haulage and machinery transport is fit for intended purpose, and protects environmental and cultural values and the safety of all road users.
The management of all roads that are part of plantation timber harvesting operations takes account of environmental and cultural values, the safety of road users and the intended use of the road.
2.4 and 3.3 Roading
4.4 Plantation Roading
Timber harvesting operations are conducted in a manner appropriate to the site, and manages the impact on soil, water and other values, including biodiversity and cultural heritage.
Timber harvesting is conducted in a manner appropriate to the site, to manage the impact on soil, water and other values, including biodiversity and cultural heritage.
2.5 Timber Harvesting
3.4 and 4.5.2 Timber
Harvesting
Forest ecosystem health and vitality is monitored and managed to reduce pest and weed impacts.
Forest [plantation] health is monitored and maintained by employing appropriate preventative, protective and remedial measures.
2.2.2 and 3.2.2 Conservation
of Biodiversity
4.3.3 Plantation Health
Soil and water assets within forests are conserved. River health is maintained or improved.
Water quality and river health are maintained or improved by protecting waterways and aquatic and riparian habitat from disturbance.
Water pollution is minimised and soil productive capacity is maintained by avoiding harvesting in inappropriate areas or slopes and undertaking necessary preventive measures.
Water quality and river health are maintained or improved in plantations by protecting waterways from disturbance.
Soil erosion and water pollution are minimised by avoiding timber harvesting operations in plantations in inappropriate areas or slopes and undertaking necessary preventative measures.
2.2.1 Water Quality and 2.3.1
Operational Planning
2.2.1, 3.2.1 and 4.2.1 Water
Quality, River Health and Soil
Protection
Chemicals are only used where appropriate to the site conditions and is conducted with due care for the maintenance of forest health, water quality, biodiversity and soil values.
Fertiliser and chemicals are only used where appropriate to the site conditions and circumstances and with care for the maintenance and protection of water quality, biodiversity, soil values and neighbouring land uses.
2.2.1, 3.2.1 and 4.2.1 Water
Quality, River Health and Soil
Protection
4.3.2 Chemical Usage
Code Principles Operational Goals Section
During or following wet weather conditions, timber harvesting operations are modified or where necessary suspended to minimise risks to soil and water quality values.
2.2.1, 3.2.1 and 4.2.1 Water
Quality, River Health and Soil
Protection
2.5.3, 3.4.3 and 4.5.4 Timber
Harvesting
Site preparation is appropriate to the characteristics of the particular site, and take into account the maintenance of soil and water values as well as site productivity.
4.3.1 Site Preparation
Cultural heritage values within forests are protected and respected.
Long-term forest management planning maintains an ecologically sustainable timber resource that mitigates the impacts on all forest values.
Effective and inclusive planning processes are used for timber harvesting operations to meet the requirements of this Code and the Management Standards and Procedures.
1.2.8 and 2.3.1 Operational
Planning
Timber harvesting operations are conducted in a manner appropriate to the site, and manages impacts on soil, water and other values including biodiversity and cultural heritage.
2.5, 3.4.1 and 4.5.2 Timber
Harvesting
Planning is conducted in a way that meets all legal obligations and operational requirements.
Long-term forest management planning maintains an ecologically sustainable timber resource that mitigates the impacts on all forest values.
Effective and inclusive planning processes are used for timber harvesting operations to meet the requirements of this Code and the Management Standards and Procedures
1.2.8 and 2.3.1 Operational
Planning
Plantations on private land are designed, managed and operated in accordance with this Code.
Local government is appropriately informed of new plantation development on private land by the lodgement of either a Plantation Development Notice or a planning permit, in accordance with this Code.
4.1.1 Plantation planning and
design
Approval for timber production in native forests on private land is obtained through the relevant planning scheme.
3.1 Forest Planning
A Timber Harvesting Plan is prepared in accordance with the requirements of this Code and submitted to the relevant local government prior to the commencement of timber harvesting.
3.1.1 and 4.5.1 Timber
Harvesting Plan
A Forest Coupe Plan which specifies operational requirements is prepared in accordance with this Code prior to the commencement of each timber harvesting operation.
2.3.1 Operational Planning
32 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
2. Code Application – State Forests
This chapter applies to the planning, harvesting, roading, tending and regeneration of State forests
where timber harvesting operations are conducted, including both native forests and plantation
forests that are owned and managed by the State.
2.1 ***** Revoked ***** (Relevant content moved to Section 1.2.8)
2.2 Environmental Values in State forests
Timber harvesting operations in native forests may have local impacts on environmental values
such as water quality and biodiversity. Appropriate planning and management through the lifecycle of
the timber harvesting operation can minimise these impacts. This section includes requirements that
must be observed during planning, roading, harvesting, tending and regeneration of native forests.
2.2.1 Water Quality, River Health and Soil Protection
Operational Goals
Water quality and river health are maintained or improved by protecting waterways and aquatic and
riparian habitat from disturbance.
Water pollution is minimised and soil productive capacity is maintained by avoiding harvesting in
inappropriate areas or slopes and undertaking necessary preventive measures.
Chemicals are only used where appropriate to the site conditions and are applied with due care for the
maintenance of forest health, water quality, biodiversity and soil values.
During or following wet weather, timber harvesting operations are modified or where necessary
suspended to minimise risks to soil and water quality values.
Mandatory Actions
2.2.1.1 Planning and management of timber harvesting operations must comply with relevant water quality, river health and soil protection measures specified within the Management Standards and Procedures.
2.2.1.2 Management actions to protect waterways, river health and soil must be appropriate to the waterway class, soil category, and potential water quality risk posed by timber harvesting operations at each site.
2.2.1.3 Additional measures to protect water quality and aquatic habitat (including widening buffers or filter strips) must be adopted within coupes where there is a high local risk due to:
i. local topography;
ii. the intensity and magnitude of the timber harvesting operation;
iii. events such as wildfire that reduce the effectiveness of protection measures; or
iv. the location of the timber harvesting operation in a declared Special Water Supply Catchment or any other water supply protection area.
Protecting waterways and aquatic and riparian habitat
2.2.1.4 Use buffers and filters of effective width in forest adjacent to aquatic and riparian habitats to protect them from microclimate changes, sedimentation and disturbance.
2.2.1.5 Where practical exclude roads and snig tracks from aquatic and riparian habitats.
2.2.1.6 Where crossings are required, minimise the extent of habitat damage, constriction to stream flow and barriers to fish and other aquatic fauna.
2.2.1.7 Remove temporary crossings immediately after harvesting or any subsequent regeneration work is complete using a technique that minimises soil and habitat disturbance.
Minimising water pollution
2.2.1.8 Use drainage, artificial structures, buffers and filters of effective width to slow and disperse surface flows and deposit sediment before reaching waterways.
2.2.1.9 Locate coupe infrastructure, roads and other activities that generate sediment or other potential pollutants in places where risk of entry into waterways is lowest unless otherwise sanctioned.
2.2.1.10 Minimise the extent and duration of soil disturbance adjacent to or within waterways.
2.2.1.11 Use management practices such as modified harvesting techniques, scheduling, wet weather suspensions or progressive rehabilitation to minimise the potential for sediments and other pollutants to move into streams.
2.2.1.12 Design, construct and maintain roads, crossings, coupe infrastructure and drainage structures to withstand foreseeable rainfall events and traffic conditions, and protect water quality.
2.2.1.13 Ensure chemical use is appropriate to the circumstances and takes into account the maintenance of water quality.
Maintaining soil productive capacity
2.2.1.14 Minimise potential for soil erosion or mass movement by planning and using operational methods and restrictions appropriate to the assessed soil erosion risk and slope.
2.2.1.15 Locate coupe infrastructure and roads to minimise soil erosion and degradation.
2.2.1.16 Use appropriate equipment, harvesting techniques and operational management to minimise soil rutting, mixing or compaction.
2.2.1.17 Limit the area of soil affected by coupe infrastructure and roads to the minimum required to safely complete timber harvesting operations to the required standard.
2.2.1.18 Employ topsoil conservation techniques in timber harvesting areas affected by coupe infrastructure and roads.
2.2.1.19 During timber harvesting operations maintain effective drainage of coupe infrastructure and roads.
2.2.1.20 Minimise the time soil is left unvegetated, except at coupe infrastructure sites that are required in the longer term.
2.2.1.21 Ensure chemical use is appropriate to the circumstances and takes into account the maintenance of soil productive capacity.
34 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
2.2.2 Conservation of Biodiversity
Operational Goal
Timber harvesting operations in State forests specifically address biodiversity conservation risks
and consider relevant scientific knowledge at all stages of planning and management.
Harvested State forest is managed to ensure that the forest is regenerated and the biodiversity of
the native forest is perpetuated.
The natural floristic composition and representative gene pools are maintained when regenerating
native forests by protecting long-lived understorey species and using appropriate seed sources and
mixes of dominant species.
Forest health is monitored and maintained by employing appropriate preventative, protective and
remedial measures.
Chemicals are only used where appropriate to the site conditions and are conducted with due care for
the maintenance of forest health, water quality, biodiversity and soil values.
Mandatory Actions
Addressing biodiversity conservation risks considering scientific knowledge
2.2.2.1 Planning and management of timber harvesting operations must comply with relevant biodiversity conservation measures specified within the Management Standards and Procedures.
2.2.2.2 The precautionary principle must be applied to the conservation of biodiversity values. The application of the precautionary principle will be consistent with relevant monitoring and research that has improved the understanding of the effects of forest management on forest ecology and conservation values.
2.2.2.3 The advice of relevant experts and relevant research in conservation biology and flora and fauna management must be considered when planning and conducting timber harvesting operations.
2.2.2.4 During planning identify biodiversity values listed in the Management Standards and Procedures prior to roading, harvesting, tending and regeneration. Address risks to these values through management actions consistent with the Management Standards and Procedures such as appropriate location of coupe infrastructure, buffers, exclusion areas, modified harvest timing, modified silvicultural techniques or retention of specific structural attributes.
2.2.2.5 Protect areas excluded from harvesting from the impacts of timber harvesting operations.
2.2.2.6 Ensure chemical use is appropriate to the circumstances and provides for the maintenance of biodiversity.
2.2.2.7 Rainforest communities must not be harvested.
Perpetuating the biodiversity of harvested native forests
2.2.2.8 Long-term (strategic) forest management planning must incorporate wildlife corridors, comprising appropriate widths of retained forest, to facilitate animal movement between patches of forest of varying ages and stages of development, and contribute to a linked system of reserves.
2.2.2.9 Modify coupe size and rotation periods to maintain a diversity of forest structures throughout the landscape.
2.2.2.10 Retain and protect habitat trees or habitat patches and long-lived understorey species to provide for the continuity and replacement of old hollow bearing trees and existing vegetation types within each coupe.
2.2.2.11 Use silvicultural systems that suit the ecological requirements of the forest type.
2.2.2.12 Regenerate harvested areas using seed from overstorey species with provenances native to the area.
Maintaining forest health
2.2.2.13 Implement appropriate vehicle and equipment hygiene precautions when moving from areas of known pest plant, pest animal and pathogen infestations.
2.2.2.14 Implement appropriate control actions where timber harvesting operations have introduced or exacerbated a pathogen or weed.
2.2.2.15 Report the suspected introduction of new or unknown exotic agents to the Victorian Government’s Biosecurity section.
2.2.2.16 Where Myrtle Wilt (Chalara australis), Cinnamon Fungus (Phytophthora cinnamomi) or Root Rot (Armillaria) is known to exist, apply appropriate measures to minimise the spread of these pathogens.
2.3 Operational Planning and Record Keeping
2.3.1 Operational Planning
Planning associated with the establishment of timber harvesting operations is critical to achieving the
environmental outcomes encompassed by the Code. Operational planning includes a requirement for
clear documentation of intended measures to protect the environment during proposed timber
harvesting operations such as roading, harvesting, tending, haulage and regeneration.
Operational Goals
Effective and inclusive planning processes are used for timber harvesting operations to meet the
requirements of this Code and the Management Standards and Procedures.
A Forest Coupe Plan which specifies operational requirements is prepared in accordance with the
requirements of this Code prior to the commencement of each timber harvesting operation.
Mandatory Actions
2.3.1.1 All timber harvesting operations must be planned to meet the requirements of this Code and the Management Standards and Procedures.
2.3.1.2 A Forest Coupe Plan must:
i) be prepared by the managing authority prior to the commencement of a timber harvesting operation including road construction coupes or significant road improvement operation coupes;
ii) communicate the intended boundaries, activities and requirements in adequate detail to enable operators to complete work to the required standard, comply with the Code and comply with the Management Standards and Procedures for the life of the coupe, and to support the Secretary in reviewing compliance;
iii) be sanctioned by the managing authority;
36 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
iv) record evidence of timber harvesting operations being approved if occurring within SPZ or outside the area identified in an Allocation Order or licensed to the harvesting entity;
v) record details of the type of timber harvesting operation; and
vi) document all exemptions or temporary variations to operational requirements of the Management Standards and Procedures and any sanctioned activities or decisions made until the timber harvesting coupe is successfully regenerated and rehabilitated.
2.3.1.3 Coupes associated with roading, must be planned with adequate time to construct the required standard of access without compromising safety, water quality and other values
2.3.1.4 In addition to the requirements outlined in this Code, Forest Coupe Plans for salvage harvesting operations must complement any additional recovery strategies and rehabilitation plans.
2.3.2 Record Keeping
Timber harvesting operations records are routinely used for operational, policy and public information
purposes.
Operational Goals
Timber harvesting operations are recorded in a way that facilitates future compliance checks, public
reporting and policy development purposes.
Mandatory Actions
2.3.2.1 The following information must be recorded for all timber harvesting operations in a format that allows for future reference:
i) harvesting and tending location, silviculture system and timing;
ii) regeneration location, method, timing, seed source and final stocking rate; and
iii) pre and post-harvest basal area in tending operations.
2.4 Roading for Timber Harvesting Operations
This section covers the planning, design, construction, maintenance and use of permanent and
temporary roads for timber haulage and machinery transport. This section does not consider
requirements for snigging and forwarding tracks, which are covered under coupe infrastructure
(section 2.5.2).
Timber harvesting operation roads have the potential to create significant environmental impacts,
particularly on water quality and river health. This Code aims to protect a range of environmental
values while allowing safe and economic roading for timber harvesting operations.
Operational Goal
The planning and management of permanent and temporary roads for timber haulage and machinery
transport ensures that the roads are fit for purpose and protect environmental and cultural values and
the safety of all road users.
2.4.1 Road Planning
Mandatory Actions
2.4.1.1 Planning and management of timber harvesting operations must comply with this Code and relevant road planning measures specified within the Management Standards and Procedures unless the road is covered by a formal roading agreement with the Department that would supersede this requirement.
2.4.1.2 Road planning and design for new and substantially upgraded roads must ensure the road network is safe and adequate for the intended range of uses and users, while ensuring the protection of water quality and conservation values, including river health.
2.4.1.3 Road planning must:
i. locate roads so as to minimise risks to safety and environmental values, particularly soil, water quality and river health, during both construction and ongoing road use; and
ii. ensure that the timing of construction activities minimises risks associated with unsuitable weather conditions and provides for completion to the required standard in advance of timber harvesting operations.
2.4.1.4 Existing roads must be used for access to a coupe or work site and to haul timber, except where it can be clearly demonstrated that a new or relocated road further minimises or removes existing threats to soil, water quality or biodiversity.
2.4.1.5 Forest Coupe Plans for roads must be based on field surveys to ensure that all environmentally sensitive locations are identified and appropriate design and construction techniques are adopted.
2.4.2 Road Design
Good road design is vital to minimise construction and maintenance costs, reduce environmental risk
such as impacts to water quality, improve efficiency of haulage, and ensure public safety is maintained.
It is important when designing a new road or improvements to an existing road that water is moved off
the road into undisturbed vegetation to reduce the velocity (and hence erosivity) of water, and to provide
the greatest possible infiltration of water into soil to trap sediments before discharge into waterways.
Road design includes the consideration of location, use, traffic volume, aspect, soil type, slope,
topography, surface materials, road shape as well as road drainage and other coupe infrastructure
including culverts, drains, batters, bridges and fords.
Mandatory Actions
2.4.2.1 Planning and management of timber harvesting operations must comply with this Code and relevant road design measures specified within the Management Standards and Procedures unless the road is covered by a formal roading agreement with the Department that would supersede this requirement.
2.4.2.2 New or upgraded roads must be designed to a standard capable of carrying anticipated traffic with reasonable safety, and ensure the protection of water quality and river health, and biodiversity conservation values.
2.4.2.3 All fill disposal areas and embankments must be planned and designed to minimise soil erosion, mass soil movement, and potential water quality deterioration.
38 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
2.4.2.4 Stream crossings must be designed according to traffic requirements and the nature, size and period of flow (both pre and anticipated post-harvest) and characteristics of the bed and banks of the stream.
2.4.2.5 Appropriate drainage must be provided. Spacing of drainage outlets along a road must take into account the soil erodibility, rainfall frequency and intensity, and the proximity of the road to streams.
2.4.2.6 Energy dissipating structures or silt traps must be used where necessary to reduce water velocity and trap sediments.
2.4.2.7 Drainage onto exposed erodible soil or over fill slopes must be avoided where possible. Structures and earthworks required to avoid such discharges are to be identified during planning and construction as required.
2.4.2.8 Drainage must be prevented from discharging directly onto any road.
2.4.2.9 Before entering a waterway, road drainage must discharge onto vegetation or through a structure that effectively dissipates the velocity of drainage flows.
2.4.2.10 Materials or techniques with low sediment generating potential must be applied to the road area on bridge approaches and on unsurfaced bridges or culverts, when crossing permanent or temporary streams.
2.4.3 Road Construction
Mandatory Actions
2.4.3.1 Planning and management of timber harvesting operations must comply with this Code and relevant road construction measures specified within the Management Standards and Procedures unless the road is covered by a formal roading agreement with the Department that would supersede this requirement.
2.4.3.2 Road construction must be conducted in a manner consistent with plans and designs.
2.4.3.3 All fill disposal areas and embankments must be appropriately stabilised. Where revegetation is used to stabilise fills or embankments, the species must be suitable for the site and where possible indigenous to the area.
2.4.3.4 Erosion and sediment control must be an ongoing activity over the duration of the construction activity, integrated with the works schedule. Road construction sites must have erosion mitigation measures in place and appropriate temporary drainage to ensure that the site is left protected between construction activities.
2.4.3.5 Quarry materials known to be infected with any pest plant or pathogen must not be used.
2.4.3.6 Road construction must ensure that:
i. disturbance to stream beds and banks is kept to a minimum;
ii. soil and rock fill is not pushed into waterways, nor placed into a position where there is a risk that it can erode into a waterway; and
iii. cement, raw concrete, soil fill and other road making materials are not spilt or disposed of into waterways during road construction.
2.4.4 Road Maintenance
Mandatory Actions
2.4.4.1 Planning and management of timber harvesting operations must comply with this Code and relevant road maintenance measures specified within the Management Standards and Procedures unless the road is covered by a formal roading agreement with the Department that would supersede this requirement.
2.4.4.2 Roads used for timber haulage must be maintained in a manner that minimises erosion and protects water quality and other environmental values.
2.4.4.3 Road drainage systems must be maintained at sufficient frequency to minimise erosion and the discharge of sediment into waterways.
2.4.4.4 Blading-off of roads must be sanctioned and recorded in the coupe diary and is only permitted where measures are in place to prevent potential adverse impacts on water quality and where effective side drainage can be maintained.
2.4.5 Suspension of Haulage
Haulage may need to cease on forest roads for periods when wet weather or other adverse
conditions such as excessive dust affect the road surface and drainage and can compromise water
quality and public safety.
Mandatory Actions
2.4.5.1 Planning and management of timber harvesting operations must comply with relevant suspension of haulage measures specified within the Management Standards and Procedures unless the road is covered by a formal roading agreement with the Department that would supersede this requirement.
2.4.5.2 Heavy vehicle traffic associated with timber harvesting operations must not use roads in State forests when persistent wet weather or road stability compromise road drainage and water quality.
2.4.5.3 Heavy vehicle traffic associated with timber harvesting operations must not use roads in State forests when persistent dry weather causes the surface materials to disintegrate to a degree that poses a threat to water quality, in the absence of suitable preventative or remedial actions to manage the risk to water quality.
2.4.6 Road Closure
Mandatory Actions
2.4.6.1 Planning and management of timber harvesting operations must comply with relevant road closure measures specified within the Management Standards and Procedures unless the road is covered by a formal roading agreement with the Department that would supersede this requirement.
2.4.6.2 Roads no longer required for timber harvesting operations or other forest management purposes, must be permanently closed to vehicle traffic and effectively drained following completion of the timber harvesting operation.
40 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
2.5 Timber Harvesting
Timber harvesting operations in State forest are conducted in accordance with a Forest Coupe
Plan (Section 2.3.1).
Operational Goal
Timber harvesting operations are conducted in a manner appropriate to the site, and manages
impacts on soil, water and other values including biodiversity and cultural heritage.
Timber harvesting operations are conducted in a manner that mass soil movements do not occur.
2.5.1 Coupe Management
Mandatory Actions
2.5.1.1 Planning and management of timber harvesting operations must comply with relevant coupe management measures specified in the Management Standards and Procedures.
2.5.1.2 Timber harvesting operations must be conducted in accordance with the Forest Coupe Plan and all applicable Special Management Zone plans.
2.5.1.3 The location of coupe boundaries, Special Protection Zones, buffers, filters, exclusion areas, areas where special management applies and habitat trees must be easily distinguishable in the field.
2.5.1.4 Timber harvesting operations must only be undertaken within established coupe boundaries as indicated on the Forest Coupe Plan and where required marked in the field, unless the timber harvesting operation is specifically sanctioned or approved in accordance with this Code and the Management Standards and Procedures.
Timber harvesting operations within areas that are not available for harvesting
2.5.1.5 Timber harvesting operations (excluding road maintenance and haulage on existing roads, approved roads or sanctioned roads) are not permitted in Special Protection Zones, buffers, or exclusion areas identified on the Forest Coupe Plan, except where:
i. The managing authority has been approved to conduct timber harvesting operations, including the removal of a limited number of trees associated with the construction and use of a coupe-access road, snig track or associated stream crossings within a Special Protection Zone or exclusion area; or
ii. the operator has been sanctioned to construct and use an in-coupe road or coupe driveway, snig track or associated stream crossing, including the removal of a limited number of trees associated with these activities within a buffer or filter; or
iii. the operator has been sanctioned to remove a limited number of trees to protect public or worker safety; or
iv. the managing authority has been approved to conduct regeneration or rehabilitation works of harvested native forest areas or use existing associated coupe infrastructure located within Special Protection Zones or exclusion area; or
v. the operator has been sanctioned to conduct regeneration or rehabilitation works in buffers or filters; or
vi. the managing authority has been approved to conduct seed collection activities within Special Protection Zones or exclusion areas.
2.5.1.6 Areas outside the coupe boundary or within special protection zones, buffers and other exclusion areas must be protected from damage caused by trees felled in adjacent areas. Trees or debris accidentally felled into these areas may be removed only where sanctioned. Sanction will only be given if significant damage and disturbance of soil and vegetation outside the harvestable area can be avoided.
Timber harvesting operations within filter strips
2.5.1.7 Disturbance to soil and understorey vegetation from timber harvesting operations in filter strips must be minimised.
2.5.1.8 Trees may be felled from within filter strips where machinery does not enter the filter strip. The felling of trees into filter strips must be avoided where possible.
Timber harvesting operations on steep slopes
2.5.1.9 Timber harvesting operations must not occur on slopes where they cannot be conducted safely, or they threaten the stability of the soil or have high potential for adverse off-site effects. The potential for mass soil movement must be assessed by the managing authority and necessary preventative actions undertaken.
2.5.1.10 On slopes with a high soil erosion hazard or where there is an assessed risk of mass soil movement, additional measures must be taken to avoid movement of soil into streams, such as modification to harvesting methods or increasing of the widths of buffers and filter strips.
2.5.2 Coupe Infrastructure
Coupe infrastructure includes log landings, log storage facilities, snigging and forwarding tracks,
and boundary trails.
Mandatory Actions
2.5.2.1 Planning and management of timber harvesting operations must comply with relevant coupe infrastructure measures specified within the Management Standards and Procedures.
2.5.2.2 Log landings and log storage facilities must not be located in SPZ or exclusion areas unless approved and noted on the Forest Coupe Plan.
2.5.2.3 Coupe infrastructure must be rehabilitated on completion of timber harvesting operations, where not required for future timber harvesting operations or an authorised purpose for which native vegetation is not compatible. Rehabilitation techniques must ensure that suitable soil conditions are provided for the regeneration and growth of vegetation existing on the site prior to harvesting (refer to section 2.6.1). Progressive rehabilitation of coupe infrastructure during timber harvesting operations must be undertaken where operationally possible.
2.5.2.4 Snigging and forwarding tracks must be placed at the greatest practicable distance from waterways without compromising operator safety.
2.5.2.5 Tracks must have effective drainage to prevent soil erosion. Cross-drains, where used, must be spaced and angled as appropriate to the soil erosion hazard, to disperse surface run-off and prevent discharge of turbid water into streams or drainage lines.
2.5.2.6 Snigging and forwarding tracks and boundary trails must not be bladed off where this would result in an adverse impact on water quality or the loss of topsoil from the site. Any blading off of coupe infrastructure must be sanctioned and recorded in the coupe diary.
42 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
2.5.2.7 Rehabilitation of coupe infrastructure must be assessed within three years of initial treatment and, where found inadequate, remedial action must be taken.
2.5.3 Operational Restrictions
Operational Goal
During or following wet weather, timber harvesting operations are modified or suspended as
necessary to minimise risks to soil and water quality values.
Mandatory Actions
2.5.3.1 Planning and management of timber harvesting operations must comply with relevant operational restrictions specified within the Management Standards and Procedures.
2.5.3.2 Timber harvesting operations must be suspended when water begins to flow along tracks, threatening stream water quality or soil values, unless appropriate remedial actions are taken.
2.5.3.3 Timber harvesting operations that involve machine traffic must be suspended when significant rutting would be caused by such traffic, unless actions are taken to actively manage that risk.
2.5.3.4 Timber harvesting operations conducted on landings must be suspended when continuation would result in significant deterioration of the landing surface causing increased levels of compaction or mixing of bark through soil on the landing surface.
2.5.3.5 Snigging and use of heavy machinery must not increase water quality risks from roading.
2.6 Forest Regeneration and Management
This section covers the regeneration of State forests and the subsequent management of such
forest stands. Unless required for another approved purpose, all State forest areas subject to
timber harvesting operations will be regenerated to standards that approximate the original forest
composition.
2.6.1 Regeneration
Operational Goals
Harvested areas of native forest are successfully regenerated.
The natural floristic composition and representative gene pools are maintained when regenerating
native forests by using appropriate seed sources and mixes of dominant overstorey species.
Mandatory Actions
2.6.1.1 Planning and management of timber harvesting operations must comply with relevant regeneration measures specified within the Management Standards and Procedures.
2.6.1.2 State forest available for timber harvesting operations must not be cleared to provide land for the establishment of plantations.
2.6.1.3 Action must be taken by the managing authority to ensure the successful regeneration of a harvested coupe, except where:
i. the land is to be used for an authorised purpose for which native vegetation is not compatible (for example services, public infrastructure and structures); or
ii. timber has been harvested by thinning; or
iii. the naturally occurring regrowth is assessed as sufficient.
2.6.1.4 Following timber harvesting operations, State forest must be regenerated with overstorey species native to the area, wherever possible using the same provenances, or if not available, from an ecologically similar locality.
2.6.1.5 Regeneration must aim to achieve the approximate canopy floristics that were common to the coupe prior to harvesting, if known.
2.6.1.6 Silvicultural methods for regeneration must suit the ecological requirements of the forest type, taking into consideration the requirements of sensitive understorey species and local conditions.
2.6.1.7 Harvested coupes must be regenerated as soon as practical, including follow up or remedial action in the event of regeneration failure.
2.6.1.8 All practical measures must be taken to protect areas excluded from harvesting from the impacts of burns and other regeneration activities.
2.6.1.9 Where mechanical disturbance is used, it must be undertaken with due consideration of erosion risks and the proximity of waterways (refer to section 2.2.1).
2.6.2 Tending
Appropriate action may be taken to tend native forest stands where such actions are consistent with
environmental safeguards and offsite impacts can be minimised. Examples of such action include
stand improvement (such as selective overwood or underwood removal or reduction), thinning,
fertilising and other silvicultural practices to promote stand health and timber production.
Operational Goal
The productive capacity and other values of the forest are maintained or enhanced by appropriate
tending of stands.
Mandatory Actions
2.6.2.1 Planning and management of timber harvesting operations must comply with relevant tending measures specified within the Management Standards and Procedures.
2.6.2.2 Tending must comply with all relevant mandatory actions for timber harvesting operations.
2.6.2.3 Tending must:
i. enhance the ecologically sustainable long-term timber production capacity of the thinned stand;
ii. minimise impacts on understorey species, particularly long-lived elements; and
iii. avoid construction of roads, landings and associated coupe infrastructure that will not be required for subsequent timber harvesting operations.
44 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
3. Code Application – Private Native Forests
This chapter applies to all timber harvesting operations (including planning, harvesting, roading, tending
and regeneration) for native forests on private land. Private native forest landowners need to consider
potential impacts on soil and water quality, aquatic habitat, and biodiversity, Aboriginal and other cultural
heritage places and visual amenity when managing native forest for timber production.
3.1 Forest Planning
Proper planning is critical to achieving timber production requirements and the environmental outcomes
encompassed by the Code. Forest management planning provides clear documentation of intended
reservation of areas, measures to protect the environment and proposed timber harvesting operations.
Under the requirements of planning schemes, timber production on private land must comply with the Code.
Local government (the responsible authority) is required to consider the Operational Goals and Mandatory
Actions in this Code when issuing permits for timber harvesting operations.
Private native forest harvesting must be in accordance with ‘Guidelines for the removal, destruction or lopping
of native vegetation (2017)’, an incorporated document in the Victoria Planning Provisions and all planning
schemes.
Operational Goals
Approval for timber harvesting operations in native forest on private land is obtained through the relevant
planning scheme.
3.1.1 Timber Harvesting Plan
A Timber Harvesting Plan is the basic record of the forest manager’s intended activities in an area of forest.
It applies to a single coupe, a number of coupes or to an area in which a number of coupes are to be
harvested. It assists the managing authority, harvesting entities and operators and local government in
understanding and assessing:
• area to be harvested and operational requirements;
• compliance with the operational goals and mandatory actions of this Code;
• compliance with the planning scheme requirements; and
• compliance with relevant legislation.
Operational Goal
A Timber Harvesting Plan is prepared in accordance with the requirements of this Code and submitted to
the relevant local government prior to the commencement of the timber harvesting operation.
Mandatory Actions
3.1.1.1 A Timber Harvesting Plan must be submitted to local government not less than 28 days before the commencement of any timber harvesting operations. The 28 day minimum lodgement time may be waived with the agreement of the local government.
3.1.1.2 A Timber Harvesting Plan is current for 24 months following lodgement with the local government.
3.1.1.3 When preparing a Timber Harvesting Plan, the following issues must be addressed:
i. methods to minimise impacts on biodiversity, water quality and river health from timber harvesting operations including associated roads;
ii. ways to minimise impacts on significant visual landscape values; and
iii. ways to minimise impacts on cultural heritage values.
3.1.1.4 The Timber Harvesting Plan must include:
i. landowners name and address;
ii. estimated timber volumes to be harvested;
iii. the proposed haulage route;
iv. a map showing:
- the coupe location(s);
- the area(s) to be harvested;
- areas excluded from harvesting within the coupe boundary, including areas reserved or specifically managed for biodiversity conservation, waterway protection (including any buffers or filter strips), or protection of cultural heritage values;
- power lines; and
- new or upgraded roads and coupe infrastructure within the property.
v. conditions applying to the timber harvesting operation;
vi. fire protection measures;
vii. the period during which timber harvesting operation is to occur; and
viii. a regeneration program to follow harvesting, where required.
3.1.1.5 The size of clearfall, seed tree harvesting or shelterwood coupes should generally not exceed 40 hectares net harvested area. Coupes may be aggregated but not exceed 120 hectares net harvested area over a period of up to five years. Aggregated coupes must not be contiguous (forming a coupe greater than 120 hectares within a five year period).
3.1.1.6 Thinning coupes must not exceed 120 hectares net harvested area. Single tree selection coupes may be of any size, where landscape or environmental values are not affected.
3.1.1.7 Coupe boundaries must take advantage of topographic and/or artificial features (such as roads and property boundaries) where they exist, with due regard to safety, operational requirements, landscape values and environmental values. Where coupe boundaries do not follow obvious natural or artificial features, they must be clearly marked on site.
3.1.1.8 Characteristics of coupes for salvage of timber in forests damaged by fire, pests, pathogens or other events may differ from undamaged forests. A special (salvage) plan or an amended Timber Harvesting Plan must be developed, taking into account:
i. the need for urgency in timber recovery; and
ii. the need to modify prescriptions, as required, to meet environmental care goals and address
recovery strategies for other forest values such as fauna.
3.1.1.9 Salvage harvesting operations must take as much account of environmental care as any other timber harvesting operation.
3.1.1.10 A copy of the Timber Harvesting Plan and any supporting prescriptions must be provided to the harvesting team leader. The Plan’s implementation, including specific prescriptions to be applied to the coupe, must be discussed with him/her. These documents must be available on site while timber harvesting operation is in progress.
3.1.1.11 All amendments and variations to operational requirements (such as the removal of trees from buffers or outside the coupe for safety purposes) must be documented in the Timber Harvesting Plan and dated by the harvesting team leader.
46 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
3.2 Environmental Values in Private Native Forests
Timber harvesting operations in private native forests may impact on environmental values such as water
quality and biodiversity. Appropriate planning and management through the lifecycle of the timber
harvesting operation can minimise these impacts.
This section includes requirements that must be observed during planning, tending, roading, harvesting and
regeneration of native forests on private land.
3.2.1 Water Quality, River Health and Soil Protection
Operational Goals
Water quality and river health are maintained or improved by protecting waterways and aquatic and riparian
habitat from disturbance.
Water pollution is minimised and soil productive capacity is maintained by avoiding harvesting in inappropriate
areas or slopes and undertaking necessary preventative measures.
Chemicals are only used where appropriate to the site conditions and is conducted with due care for the
maintenance of forest health, water quality, biodiversity and soil values.
During or following wet weather conditions, the timber harvesting operation is modified or where necessary
suspended to minimise risks to soil and water quality values.
Mandatory Actions
Waterway Classification
3.2.1.1 Use the following categories when determining buffer and filter widths for waterways within and immediately adjacent to each coupe.
i. permanent streams, pools and wetlands;
ii. temporary streams;
iii. drainage lines.
Aids to the identification of each class of waterway are provided in the glossary. The classification of a
waterway is based on characteristics observed prior to harvesting, noting that stream flow may change
following harvesting.
Protecting waterways and aquatic and riparian habitat
3.2.1.2 Management actions to protect waterways, river health and soil must be appropriate to the waterway class, soil category, and potential water quality risk posed by timber harvesting operations at each site.
3.2.1.3 Water quality and river health must be protected by establishing and maintaining buffers and/or filter strips (to each side of the waterway). Buffers and filter strips must be specified on the basis of field risk assessments, and the outcomes shown in the Timber Harvesting Plan. As part of the field risk assessment, the potential risk to water quality is determined through consideration of:
i. soil erodibility;
ii. soil permeability;
iii. rainfall erosivity (including season of timber harvesting operation);
iv. topography;
v. type of timber harvesting operation; and
vi. location of coupe infrastructure.
3.2.1.4 Water quality and river health must be protected from microclimate changes, sedimentation and disturbance by maintaining buffers and/or filter strips (to each side of the waterway) of not less than the widths specified below in table 2.
Table 2 Minimum widths in metres for buffers and filter strips applicable to various waterway categories, in relation to water quality risk and slope
Notes:
- Slope is the average slope of the coupe area in the vicinity of the water body.
- Buffers and filter strips must be applied to each waterway class regardless of the origins of the channelling.
- The width of buffer areas and filter strips must be measured in the horizontal plane, from the edge of the saturated zone (at time of harvesting) or channel (whichever is greater), on each side of the waterway.
Sites with low or moderate water
quality risk
Sites with high or very high water quality risk
Waterway Class Slope 0-30o Slope 0-20o Slope 21o - 30o
1. Pools, permanent streams and wetlands
20m B 30m B 40m B
2. Temporary streams 10m F 10m B + 10m F 20m B
3. Drainage lines 10m F 10m F 15m F
48 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
3.2.1.5 Additional measures to protect water quality and aquatic habitat (including widening buffers or filter strips) must be adopted within coupes where there is a high local risk due to:
i. local topography;
ii. the intensity and magnitude of the timber harvesting operation; or
iii. the location of the timber harvesting operation in a declared Special Water Supply Catchment or any other water supply protection area.
3.2.1.6 To the maximum extent possible, exclude roads and snig tracks from aquatic and riparian habitats.
3.2.1.7 Where crossings are required, minimise the extent of habitat damage, constriction to stream flow and barriers to fish and other aquatic fauna.
3.2.1.8 Remove temporary crossings immediately after harvesting or any subsequent regeneration is complete using a technique that minimises soil and habitat disturbance.
Minimising water pollution
3.2.1.9 Use drainage, artificial structures, buffers and filters of effective width to slow and disperse surface flows and deposit sediment before reaching waterways.
3.2.1.10 Unless otherwise approved on the Timber Harvesting Plan, locate coupe infrastructure, roads and other activities that generate sediment and other potential pollutants in places where risk of entry into waterways is lowest.
3.2.1.11 Minimise the extent and duration of soil disturbance adjacent and within waterways.
3.2.1.12 Use management practices such as modified harvesting techniques, scheduling, wet weather suspensions or progressive rehabilitation to minimise potential for sediments and other pollutants to move into streams.
3.2.1.13 Design, construct and maintain roads, crossings, coupe infrastructure and drainage structures to withstand anticipated rainfall events and traffic conditions, and protect water quality.
3.2.1.14 Ensure chemical use is appropriate to the circumstances and takes into account the maintenance of water quality.
Maintaining soil productive capacity
3.2.1.15 Minimise potential for soil erosion and mass movement by planning and using operational methods and restrictions appropriate to the soil erosion risk and slope.
3.2.1.16 Locate coupe infrastructure and roads to minimise soil erosion and degradation.
3.2.1.17 Use appropriate equipment, techniques and operational management to minimise soil rutting, mixing and compaction.
3.2.1.18 Limit the area of soil affected by coupe infrastructure to the minimum required to safely complete timber harvesting operation to the required standard.
3.2.1.19 Employ topsoil conservation techniques in areas affected by coupe infrastructure.
3.2.1.20 Maintain effective drainage of coupe infrastructure and roads.
3.2.1.21 Ensure chemical use is appropriate to the circumstances and takes into account the maintenance of soil productive capacity.
3.2.2 Conservation of Biodiversity
Operational Goal
Planning, harvesting, roading and silvicultural treatment in private native forests specifically address the
conservation of biodiversity, in accordance with relevant legislation and regulations, and considering
relevant scientific knowledge.
Harvested native forest is managed to ensure that the forest is regenerated and the biodiversity of the
native forest is perpetuated.
The natural floristic composition and representative gene pools are maintained when regenerating native
forests by using appropriate seed sources and mixes of dominant species.
Mandatory Actions
Addressing biodiversity conservation risks
3.2.2.1 Where fire is used in timber harvesting operation, all practicable measures must be taken to protect all areas excluded from harvesting from the impacts of unplanned fire.
50 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
3.2.2.2 Rainforest communities in Victoria must not be harvested. Rainforest communities must be protected from the impacts of harvesting through the use of appropriate buffers to maintain microclimatic conditions and protect from disease and other disturbance.
Maintaining natural floristic composition and representative gene pools
3.2.2.3 Use silvicultural systems that suit the ecological requirements of the forest type.
3.2.2.4 Regenerate harvested areas using species and provenances native to the area.
3.2.3 Forest health
Maintaining forest health is important for ensuring the long-term ecological integrity and productivity of
forests. Forest health can be promoted through stand management practices such as fire application, timber
harvesting, including salvage felling and thinning and weed, pest and pathogen control. Some activities may
require a permit from relevant planning authorities.
Operational Goal
Forest health is monitored and maintained by employing appropriate preventative, protective and remedial
measures.
Chemicals are only used where appropriate to the site conditions and are conducted with due care for the
maintenance of forest health, water quality, biodiversity and soil values.
Mandatory Actions
3.2.3.1 Implement appropriate vehicle and equipment hygiene precautions when moving from areas of known pest plant, pest animal and pathogen infestations.
3.2.3.2 Implement appropriate control actions where timber harvesting operations have introduced or exacerbated a pathogen or weed.
3.2.3.3 Report the suspected introduction of new or unknown exotic agents to the Victorian Government’s Biosecurity section.
3.2.3.4 Where Myrtle Wilt fungus (Chalara australis), Cinnamon Fungus (Phytophthora cinnamomi) or Root Rot (Armillaria) is known to exist, apply appropriate measures to minimise the spread of these pathogens.
3.2.3.5 Ensure chemical use is appropriate to the circumstances and takes into account the maintenance of biodiversity.
3.3 Roading for Timber Production
This section covers the planning, design, construction, maintenance and use of permanent and temporary
roads for haulage and machinery transport. This section does not consider requirements for snigging and
forwarding tracks, which are covered under coupe infrastructure (section 3.4.2).
Timber production roads have the potential to create significant environmental impacts, particularly on water
quality and river health. The aim of this Code is to protect a range of environmental values while allowing
economic roading for timber production, management purposes and other uses.
Operational Goal
The planning and management of permanent and temporary roads for timber haulage and machinery
transport ensures that the roads are fit for intended purpose and protect environmental and cultural values
and the safety of road users.
3.3.1 Road Planning
Mandatory Actions
3.3.1.1 Road planning and design for new and substantially upgraded roads within the property must ensure the road is adequate for the intended use, while ensuring the protection of water quality and conservation values, including river health.
3.3.1.2 Road planning must:
i. locate roads to minimise risks to environmental values, particularly soil, water quality and river health, during both construction and ongoing road use; and
ii. time construction activities to minimise risks associated with unsuitable weather conditions.
3.3.1.3 Existing roads must, where practicable, be used for access to a coupe or work site and to haul timber, except where it can be clearly demonstrated that a new or relocated road minimises or removes existing threats to soil, water quality or biodiversity.
3.3.1.4 Plans for roads must be based on field surveys to ensure all environmentally sensitive locations are identified and appropriate design and construction techniques adopted.
3.3.2 Road Design
Good road design is vital to minimise construction and maintenance costs, reduce environmental risk such
as impacts to water quality, improve efficiency of haulage, and ensure public safety is maintained. It is
important when designing a new road or improvements to an existing road that water is moved off the road
into undisturbed vegetation to reduce the velocity (and hence erosivity) of water, and to provide the greatest
possible infiltration of water into soil to trap sediments before discharge into waterways.
Road design includes the consideration of road location, aspect, shape, traffic frequency, type and volume,
slope, topography, surface materials, as well as road infrastructure including culverts, drains, batters, bridges
and fords.
Mandatory Actions
3.3.2.1 New or upgraded roads must be designed to a standard capable of carrying anticipated traffic with reasonable safety, and ensuring the protection of water quality and river health, and biodiversity conservation values.
3.3.2.2 All fill disposal areas and embankments must be planned and designed to minimise soil erosion, mass soil movement, and potential water quality deterioration.
3.3.2.3 Stream crossings must be designed according to traffic requirements and the nature, size and period of flow (both pre and anticipated post-harvest) and characteristics of the bed and banks of the stream.
3.3.2.4 Appropriate drainage must be provided. Spacing of drainage outlets along a road must take into account of the soil erodibility, the rainfall erosivity, and the proximity of the road to streams.
3.3.2.5 Energy dissipating structures or silt traps must be used where necessary to reduce water velocity and trap sediments.
3.3.2.6 Drainage onto exposed erodible soil or over fill slopes must be avoided where possible. Structures and earthworks required to avoid such discharges are to be identified during planning and construction as required.
52 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
3.3.3 Road Construction
Mandatory Actions
3.3.3.1 Road construction must be conducted in a manner consistent with plans and designs.
3.3.3.2 All fill disposal areas must be stabilised and rehabilitated when no longer required. Where revegetation is used to stabilise fills or embankments, the species must be suitable for the site and task, and where possible indigenous to the area.
3.3.3.3 Erosion and sediment control must be an ongoing activity over the duration of the construction activity, integrated with the works schedule. Road construction sites must not be left unprotected between construction activities, as this constitutes an unacceptable water pollution risk.
3.3.3.4 Quarry materials known to be infected with any pest plant or pathogen must not be used.
3.3.3.5 Road construction must ensure that:
i. disturbance to stream beds and banks is kept to a minimum;
ii. soil and rock fill is not pushed into streams, nor placed into a position where there is a risk that it can erode into a stream; and
iii. cement, raw concrete, soil fill and other road making materials are not spilt into watercourses during any construction.
3.3.4 Road Maintenance
Mandatory Actions
3.3.4.1 Roads used for timber haulage must be maintained to minimise erosion and protect water quality and other environmental values.
3.3.4.2 Road drainage systems must be maintained to minimise erosion and the discharge of sediment into waterways.
3.3.4.3 Blading-off of roads is only permitted where measures are in place to prevent potential adverse impacts on water quality and where effective side drainage can be maintained.
3.3.5 Suspension of Haulage
Mandatory Actions
3.3.5.1 Heavy vehicle traffic must not use roads in private native forests when persistent wet weather or road stability compromise road drainage and water quality.
3.3.5.2 Heavy vehicle traffic must not use roads in private native forests when persistent dry weather causes the surface materials to unravel to a degree that poses a threat to water quality, in the absence of suitable preventative or remedial actions to manage the risk to water quality.
3.3.6 Road Closure
Mandatory Action
3.3.6.1 Roads no longer required for timber harvesting operations or other management purposes, must be permanently closed and effectively drained.
3.4 Timber Harvesting
3.4.1 Timber Harvesting
Operational Goal
Timber harvesting is conducted in a manner appropriate to the site, to manage the impact on soil, water and
other values including biodiversity and cultural heritage.
During or following wet weather conditions, timber harvesting operations are modified or where necessary
suspended to minimise risks to soil and water quality values.
Mandatory Actions
3.4.1.1 All timber harvesting, including thinning, must be consistent with the Timber Harvesting Plan.
Coupe boundaries
3.4.1.2 The location of coupe boundaries, buffers, areas excluded from harvesting and areas where special management applies must be easily distinguishable in the field.
3.4.1.3 Timber harvesting must only occur within the designated boundaries of the coupe as indicated on the Timber Harvesting Plan and where required, marked in the field, unless the timber harvesting is specifically exempted in accordance with this Code.
3.4.1.4 Timber must be directed to fall within the coupe boundary unless unsafe to do so. A decision to fall outside the coupe boundary must be documented on the Timber Harvesting Plan.
Timber harvesting within buffers
3.4.1.5 Timber harvesting is not permitted in buffers (identified on the Timber Harvesting Plan), except where the limited removal of the minimum number of trees is necessary for:
i. the protection of worker safety; or
ii. the construction of roads or stream crossings.
Removal of trees from these areas must be noted on the Timber Harvesting Plan
3.4.1.6 Buffers must be protected from damage caused by trees felled in adjacent areas. Trees accidentally felled into buffers may be removed if significant damage and disturbance of soil and vegetation in the buffer can be avoided.
3.4.1.7 Machinery must not enter a buffer area except for the construction and use of stream crossings specified in the Timber Harvesting Plan.
3.4.1.8 Pushing of fill or harvesting debris into a buffer or construction of drain structures within a buffer is not permitted except for construction of an approved stream crossing.
Timber harvesting within filter strips
3.4.1.9 Trees may be felled from within filter strips. The felling of trees into filter strips must be avoided where possible.
3.4.1.10 Disturbance to soil and understorey vegetation from timber harvesting in filter strips must be minimised.
3.4.1.11 Machinery must not enter a filter strip, except at stream crossings as specified in the Timber Harvesting Plan.
3.4.1.12 Pushing of fill or harvesting debris into a filter strip is not permitted except for the construction of an approved stream crossing.
54 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
Timber harvesting on steep slopes
3.4.1.13 Timber harvesting must not occur on slopes where it cannot be conducted safely, threatens the stability of the soil or has high potential for adverse off-site effects. The potential for mass soil movement must be assessed and necessary preventative actions undertaken.
3.4.1.14 Timber harvesting using ground-based machinery must be excluded from slopes greater than 30 degrees. Small areas within coupes (of less than 10 per cent of the net harvested area) that are greater than 30 degrees may be harvested where the land is assessed as capable of supporting activities without risk of soil movement.
3.4.1.15 Logging techniques specifically designed for steep slopes (such as cable logging) may be used on all steep slopes (exceeding 30 degrees) where the area is assessed as being capable of supporting harvesting activities without risk of soil movement.
3.4.1.16 On slopes with a high soil erosion hazard or where there is an assessed risk of mass soil movement, additional measures must be taken to avoid movement of soil into streams, such as modification to harvesting methods or increasing of the widths of buffers and filter strips.
3.4.2 Coupe Infrastructure
Coupe infrastructure includes log landings and dumps, snigging and forwarding tracks used as part of
timber harvesting operations.
Mandatory Actions
3.4.2.1 Log landings and dumps must not be located within areas excluded from harvesting.
3.4.2.2 Coupe infrastructure must be rehabilitated on completion of timber production, where not required for future timber harvesting operations, using rehabilitation techniques that provide suitable soil conditions for the regeneration and growth of vegetation existing on the site prior to harvesting. Refer to section 3.5 of this Code.
3.4.2.3 Snigging and forwarding tracks must be placed at the greatest practicable distance from buffers and filter strips, without compromising operator safety.
3.4.2.4 Tracks must have effective drainage to prevent soil erosion. Cross-drains, where used, must be spaced and angled according to any prescriptions in planning schemes, conditions of any planning permit or other approved plan to prevent surface run-off and subsequent discharge of turbid water into streams or drainage lines.
3.4.2.5 Snigging and forwarding tracks must not be bladed off where this would result in an adverse impact on water quality or the loss of topsoil from the site.
3.4.2.6 Rehabilitation of coupe infrastructure must be assessed within three years of initial treatment and, where found inadequate, remedial action must be taken.
3.4.3 Operational Restrictions
Operational Goal
During or following wet weather conditions, timber harvesting operations are modified or where necessary
suspended to minimise risks to soil and water quality values.
Mandatory Actions
3.4.3.1 Snigging and forwarding must be suspended when significant rutting is likely to be caused by machine traffic unless actions are taken to reduce that risk.
3.4.3.2 Snigging and forwarding must be suspended when water begins to flow along tracks, threatening stream water quality or soil values, unless appropriate remedial actions have been taken to protect those values.
3.4.3.3 Timber harvesting operations on landings must be suspended when continuation would result in significant deterioration of the landing surface causing increased levels of compaction or mixing of bark through soil on the landing surface.
3.5 Forest Regeneration and Management
This section covers the regeneration of private native forest and the subsequent management of such
stands, where required. Unless required for another approved purpose, private native forests in Victoria
are to be successfully regenerated to approximate the original forest composition.
3.5.1 Regeneration
Regeneration of private native forests must be in accordance with Guidelines for the removal, destruction
or lopping of native vegetation (2017) an incorporated document in the VPPs and all planning schemes.
Operational Goals
Harvested native forest is managed to ensure that the forest is regenerated and that the biodiversity of
the native forest is perpetuated.
The natural floristic composition and representative gene pools are maintained when regenerating native
forests by using appropriate seed sources and mixes of dominant species.
Mandatory Actions
3.5.1.1 Action must be taken to secure the regeneration of harvested coupes, except where:
i. the land is to be used for an approved purpose for which native vegetation is not compatible (for example, approved services, pre-existing apiary sites and infrastructure, and structures); or
ii. timber has been harvested by thinning a stand; or
iii. the stocking of seedlings or regrowth is assessed as sufficient through natural regeneration processes.
3.5.1.2 Silvicultural methods for regeneration must suit the ecological requirements of the forest type and local conditions.
3.5.1.3 Where fire is used in regeneration, all practicable measures must be taken to protect all areas excluded from harvesting (including buffers and filter strips).
3.5.1.4 Private native forest must be regenerated following timber harvesting, with species native to the area, wherever possible using the same provenances, or if not available, from an ecologically similar locality. An ecologically similar locality for a species is from a similar elevation, aspect, soil type and/or climate, preferably as close as possible to the harvested area.
3.5.1.5 Except where past management practices may have altered species composition, regeneration must aim to approximate the composition and spatial distribution of canopy species common to the coupe prior to harvesting, where they can be determined.
3.5.1.6 Where mechanical disturbance is used, it must be undertaken with due consideration of erosion risk potential and the proximity of waterways (refer to section 3.2.1).
3.5.2 Stocking Assessment and Remedial Treatment
56 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
Operational Goal
Stocking and early seedling growth is monitored and remedial action is taken where necessary to
successfully regenerate harvested areas of native forests.
Mandatory Actions
3.5.2.1 Stocking on harvested coupes must be assessed within three years of treatment, to determine whether regeneration has been successfully achieved and to ensure that re-treatment occurs where necessary.
3.5.2.2 Where stocking, health or early growth is inadequate, remedial work must be conducted as soon as practicable to obtain adequate regeneration. Further assessment must be undertaken following remedial treatment.
3.5.2.3 The results of assessment must be recorded for future reference.
3.5.3 Tending
Tending includes stand improvement (such as overwood removal or reduction), thinning, fertilising and
other silvicultural practices to promote stand health and timber production. Appropriate action may be taken
to tend native forest stands where consistent with environmental safeguards and offsite impacts are
minimised.
Operational Goal
The productive capacity and other values of the forest are maintained or enhanced by appropriate tending
of stands.
Mandatory Actions
Tending must be planned and conducted in a manner that minimises adverse impacts on areas that are
excluded from harvesting.
4 Code Application – Plantations
Plantations are managed stands of trees of either native or exotic species, planted or sown primarily for
timber production purposes. This chapter applies to timber harvesting operations in all plantations, except
those managed by the Department (which are subject to chapter two).
Plantation development is regulated by the Victoria Planning Provisions (VPP) and a permit is generally not
required. Refer to your local planning scheme for details. The Code is an incorporated document in the VPP.
4.1 Plantation Planning and Design
4.1.1 Plantation Planning and Design
Operational Goals
Plantations on private land are designed, managed and operated in accordance with this Code.
Local government is appropriately informed of new plantation development on private land by the
lodgement of either a Plantation Development Notice or a planning permit, in accordance with this Code.
Mandatory Actions
4.1.1.1 Plantation design must take account of environmental values and be consistent with relevant fire protection requirements.
4.1.1.2 For new plantations where a planning permit is not required, a Plantation Development Notice must be lodged with the local government not less than 28 days prior to the commencement of site preparation. The 28 day minimum lodgement time may be waived with the agreement of the local government.
4.1.1.3 A Plantation Development Notice must include:
i. the landowners name and address;
ii. the total area to be planted;
iii. species to be planted;
iv. year of planting;
v. a map of the plantation, showing:
- the location of the plantation;
- any access roads or tracks;
- power lines;
- any retained native vegetation within the plantation boundaries.
58 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
4.2 Environmental Values in Plantations
Environmental values such as biodiversity, carbon sequestration, salinity control and water quality in
plantations must be considered at all stages, from planning through to harvesting and re-establishment.
Adverse impacts from plantations on environmental values, particularly water quality and river health, can
be minimised by appropriate planning and management.
4.2.1 Water Quality, River Health and Soil Protection
Waterways include all permanent and temporary streams, pools, wetlands and drainage lines*. Well
managed plantation establishment, tending, roading and harvesting near waterways may avoid
unacceptable off-site impacts.
Operational Goals
Water quality and river health values are maintained or improved in plantations by protecting waterways
from disturbance.
Soil erosion and water pollution are minimised by avoiding timber harvesting operations in inappropriate
areas or slopes and undertaking necessary preventive measures.
Mandatory Actions
Waterways
4.2.1.1 The entry of soil and other pollutants into waterways must be avoided as far as is practicable.
4.2.1.2 Timber harvesting operations (including establishment, tending, roading, harvesting and re-establishment) must be planned and conducted in such a manner as to minimise mass movement or sedimentation of waterways.
4.2.1.3 Machinery activity within 20 metres of any waterway must be kept to the minimum necessary, to avoid soil disturbance.
4.2.1.4 Machinery activity must not occur within five metres of the saturated zone of a permanent or temporary stream (except for the minimum necessary to construct stream crossings), or wetland.
4.2.1.5 Crossing of waterways with ground-based machinery must be avoided, except when constructing or using a designated crossing. Where temporary crossings or log culverts are used, they must be removed immediately after harvesting or any subsequent replanting work for which they are required, using a technique that minimises soil disturbance.
4.2.1.6 Tree extraction must not cause disturbance to the bed or bank of permanent or temporary streams. Damage to associated riparian vegetation must be minimised.
4.2.1.7 Retained native vegetation along a waterway must be protected from damage caused by ground based timber production. Trees accidentally felled into retained vegetation or across a waterway may only be removed with minimal disturbance to vegetation or soil.
* Note that artificial drainage lines (ditches) are not considered waterways for the purpose of this Code.
4.2.1.8 Additional measures to protect water quality and aquatic habitat, including increasing the zone of minimal machinery activity, must be adopted where there is a high local risk due to:
i. the erodibility of soils;
ii. rainfall erosivity;
iii. steep slopes;
iv. particular riparian habitat values;
v. the intensity and magnitude of the timber harvesting operation; and
vi. any particular requirements of a water supply off take point.
Steep Slopes
4.2.1.9 Timber harvesting operations (including establishment, tending, roading, harvesting and re-establishment) must be planned and conducted in such a manner as to not compromise soil stability or lead to mass movement or sedimentation of waterways.
4.2.1.10 Timber harvesting operations must not occur on slopes where they cannot be conducted safely, or if it threatens the stability of the soil or has high potential for adverse off-site effects. The potential for mass soil movement must be assessed and necessary preventative actions applied.
4.2.1.11 Soil and water values must be protected by the limitation of site preparation and timber production on steep slopes or on lesser slopes of unstable soil where erosion hazard is high.
4.2.1.12 On slopes greater than 30 degrees with low or medium soil erosion hazard, and slopes less than 30 degrees with a high or very high soil erosion hazard, additional measures must be taken to avoid movement of soil into streams, such as the adoption of cable harvesting or the provision of appropriate buffers and filter strips.
4.2.2 Conservation of Biodiversity
Operational Goal
Timber harvesting operations planning and implementation in plantations address the conservation of
biodiversity, including rainforest, in accordance with relevant laws.
Mandatory Actions
4.2.2.1 Retained native vegetation must be protected from damage caused by timber harvesting operations.
4.2.2.2 Any burning undertaken must be planned and managed to minimise damage to retained native vegetation both within and outside the operational area.
60 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
4.3 Establishment and Management of Plantations
Establishment activities for plantation development include site preparation, chemical usage and processes
for maintaining forest health.
4.3.1 Site Preparation
Site preparation activities should be appropriate for successful tree establishment and growth, whilst
minimising potential adverse environmental impacts.
Operational Goal
Site preparation is appropriate to the characteristics of the particular site, and take into account the
maintenance of soil and water values as well as site productivity.
Mandatory Actions
4.3.1.1 If waste timber and debris are to be burned, then burning must minimise damage to retained native vegetation within or outside the operational area.
4.3.1.2 Burning must not be conducted under power lines except with approval from the electricity supply and distribution authority.
4.3.1.3 Where windrows or heaps are created, soil within them must be kept to a minimum.
4.3.2 Chemical Usage
Fertilisers may be applied at establishment and during the life of the plantation to stimulate growth and correct
nutrient deficiencies. Chemicals may also be used to limit competition from grasses and weeds to maximise
tree growth or to manage tree diseases or nutrient deficiencies affecting tree health.
Operational Goal
Fertiliser and chemicals are only used where appropriate to the site conditions and circumstances and with
care for the maintenance and protection of water quality, biodiversity, soil values and neighbouring land uses.
Mandatory Actions
4.3.2.1 Chemical use must be appropriate to the circumstance and conducted with due consideration given to the maintenance of water quality, soil and biodiversity. Potential off-site, non-target impacts must be minimised.
4.3.2.2 When using herbicides or pesticides in a declared Special Water Supply Catchment, the relevant Water Authority must be notified prior to application.
4.3.3 Plantation Health
Plantation health may be promoted through management practices such as thinning, salvage harvesting,
weed, pest and disease control, to ensure the ongoing viability of the stand and avoid impacts on nearby
landowners.
Operational Goal
Plantation health is monitored and maintained by employing appropriate preventative, protective and remedial
measures.
Mandatory Actions
4.3.3.1 If the introduction of an exotic agent is suspected, the Victorian Government’s Biosecurity section must be informed.
4.3.3.2 Where there is a known risk of introducing pests and pathogens, the risk must be minimised through appropriate treatment of equipment when moving from known infected areas.
4.3.3.3 Trees in the vicinity of power lines that are suffering from damage or disease must be removed where they are at risk of falling and making contact with power lines.
4.4 Plantation Roading
This section covers the planning, design, construction, maintenance and use of plantation roads and stream
crossings.
Operational Goal
The management of all roads that are part of timber production take account of environmental and cultural
values, the safety of road users and the intended use of the road.
4.4.1 Road Planning
Mandatory Actions
4.4.1.1 Road planning for new roads must:
i. identify and record possible environmental risks and construction difficulties, so that adequate design standards can be used, and so that construction activities can be timed to minimise risks associated with wet weather;
ii. locate roads to minimise risks to environmental values, particularly soil, water quality and river health, during both construction and ongoing road use, while ensuring road user safety;
iii. minimise the number of stream crossings.
4.4.2 Road Design
Road design includes the consideration of traffic type and volume, surface materials, road shape as well as
road infrastructure including culverts, drains, batters, bridges and fords.
Good road design is vital for maintaining water quality. It is important to control the speed (and hence erosivity)
of water, and to provide the greatest possible infiltration to trap sediments before discharge into waterways.
Mandatory Actions
4.4.2.1 Plantation roads must be designed to a standard capable of carrying anticipated traffic with reasonable safety, and meeting Code requirements, particularly water quality.
4.4.2.2 All fill disposal areas and embankments must be planned and designed to minimise soil erosion, mass soil movement, and potential water quality deterioration.
4.4.2.3 Stream crossings must be designed according to the nature, size and period of flow (both pre and anticipated post-harvest) and characteristics of the bed and banks of the stream.
4.4.2.4 Appropriate drainage must be provided. Spacing of drainage outlets along a road must take into account soil erodibility, the rainfall erosivity, and the proximity of the road to streams. Energy
62 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
dissipating structures or silt traps must be used where necessary to reduce water velocity and trap sediments.
4.4.2.5 Drainage onto exposed erodible soil or over fill slopes must be avoided where possible. Structures and earthworks required to avoid such discharges must be identified during planning and construction as required.
4.4.2.6 Stream crossings must be appropriately designed to minimise barriers to the passage of fish and other aquatic fauna.
4.4.3 Road Construction
Mandatory Actions
4.4.3.1 Road construction must be conducted in a manner consistent with plans and designs.
4.4.3.2 All fill disposal areas must be stabilised and rehabilitated when no longer required.
4.4.3.3 Adequate temporary stabilisation must be employed to deal with site earthwork drainage and erosion control if road construction is halted or suspended for any reason.
4.4.3.4 Quarry materials known to be infected with any pest plant or pathogen must not be used.
4.4.3.5 Road construction must ensure that:
i. disturbance to stream beds and banks is kept to a minimum;
ii. soil and rock fill is not pushed into streams, nor placed into a position where there is a risk
that it will erode into a stream; and
iii. cement, raw concrete, soil fill and other road making materials are not spilt into watercourses
during any construction.
4.4.4 Road Maintenance
Mandatory Actions
4.4.4.1 Roads used for timber haulage must be maintained to minimise erosion and protect water quality and other environmental values.
4.4.4.2 Road drainage systems must be maintained to minimise erosion and the discharge of turbid water into waterways.
4.4.4.3 Blading off of roads is only permitted where measures are in place to prevent potential adverse impacts on water quality and where effective side drainage can be maintained.
4.4.5 Suspension of Haulage
Mandatory Actions
4.4.5.1 Heavy vehicle traffic must not use roads in plantations when persistent wet weather or road stability compromise road drainage and water quality.
4.4.5.2 Heavy vehicle traffic must not use roads in plantations when persistent dry weather causes the surface materials to unravel to a degree that poses a threat to water quality, in the absence of suitable preventative or remedial actions to manage the risk to water quality.
4.4.6 Road Closures
Mandatory Actions
4.4.6.1 Roads must be closed (either temporarily or permanently) and effectively rehabilitated where they are no longer required or where their continued use will threaten environmental values.
4.4.6.2 Roads that are permanently closed must be adequately drained.
4.5 Timber Harvesting
Timber harvesting is the felling of trees, and includes thinning of plantations. Mandatory Actions relevant
to timber production that are necessary for the protection of environmental values are described in section
4.2.
4.5.1 Timber Harvesting Plan
Operational Goal
A Timber Harvesting Plan is prepared in accordance with the requirements of this Code and submitted to
the relevant local government prior to the commencement of harvesting operations.
Mandatory Action
4.5.1.1 A Timber Harvesting Plan must be submitted to local government not less than 28 days before the commencement of any harvesting operations. The 28 day minimum lodgement time may be waived with the agreement of local government.
4.5.1.2 When preparing a Timber Harvesting Plan the following issues must be addressed:
i. protection of relevant environmental and cultural heritage values;
ii. methods to minimise impacts on water quality and river health from timber harvesting and
associated roads; and
iii. any necessary arrangements with the distribution authority for the electrical operational
control of power lines during harvesting.
4.5.1.3 The Timber Harvesting Plan must include:
i. landowners name and address;
ii. the months during which operations are to occur;
iii. estimated timber volumes to be harvested;
iv. proposed haulage routes;
v. a map showing:
- the plantation or coupe location;
64 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
- significant features within the coupe boundary including waterways and any areas
reserved or specifically managed for protection of biodiversity or cultural heritage
values;
- the area(s) to be harvested;
- new or upgraded roads;
- power lines;
- plantation infrastructure
vi. conditions applying to the timber harvesting operation, including any permit conditions
where required; and
vii. fire protection measures.
4.5.1.4 A copy of the Timber Harvesting Plan and any supporting prescriptions must be provided to the harvesting team leader. The Plan’s implementation, including specific prescriptions to be applied to the plantation, must be discussed with him/her. These documents must be available on site while timber harvesting operations are in progress. All amendments and variations to operational requirements (such as the removal of trees from buffers for safety purposes) must be documented in the Timber Harvesting Plan and dated by the harvesting team leader.
4.5.1.5 A Timber Harvesting Plan is current for 24 months following lodgement with local government.
4.5.1.6 A Timber harvesting Plan applies to a single coupe, a number of coupes or to an entire plantation's timber harvesting operations.
4.5.1.7 Local government may accept the lodgement of a Timber Harvesting Plan for multiple locations and operations rather than individual Timber Harvesting Plans if it is satisfied that the composite Timber Harvesting Plan adequately covers the information required for all coupes included in the Plan.
4.5.1.8 For larger operations covering several coupes over a period of years, a Scheduling Plan may be prepared and submitted (with the agreement of local government), which identifies:
i. coupe general locations;
ii. planned operational periods;
iii. haulage routes; and
iv. expected volumes.
4.5.1.9 A Scheduling Plan replaces the need to include the information from 4.5.1.8 in a Timber Harvesting Plan. Submitting a Scheduling Plan does not remove the requirement for the remaining items in 4.5.1.3 to be addressed in a Timber Harvesting Plan and submitted at the appropriate time.
4.5.1.10 A Scheduling Plan is current for up to five years following lodgement with local government, however any significant variations must be communicated to local government prior to their implementation.
4.5.2 Timber Harvesting
Operational Goal
Timber harvesting is conducted in a manner appropriate to the site, to manage the impact on soil, water and
other values, including biodiversity and cultural heritage.
Mandatory Action
4.5.2.1 All timber harvesting, including thinning, must be consistent with the Timber Harvesting Plan.
4.5.2.2 The location of boundaries must be easily distinguishable in the field.
4.5.3 Plantation Infrastructure
The operation of a harvesting coupe generally requires the development and use of specific infrastructure,
including log landings and dumps, and snigging and forwarding tracks. The planning and use of
plantation infrastructure must be undertaken in a manner that minimises impacts on environmental values.
Mandatory Actions
4.5.3.1 Plantation infrastructure (including tracks) must be designed, located, constructed and maintained to minimise potential adverse impacts on soil and water quality.
4.5.3.2 The placement of log landings and dumps must avoid areas that have been excluded from harvesting specifically for the purpose of protecting or managing values such as biodiversity conservation, waterways or cultural heritage.
4.5.3.3 The area of log landings and log dumps must be minimised without compromising safety.
4.5.3.4 All infrastructure must be stabilised and rehabilitated to minimise erosion risk upon completion of timber production, where not required for future timber production. All tracks must be effectively rehabilitated to prevent soil erosion.
4.5.3.5 Extraction and forwarding tracks must be located to minimise potential adverse impact on soil and water quality and maintain effective drainage to prevent soil erosion. They should be placed at the greatest practicable distance from waterways, without compromising safety.
4.5.3.6 Tracks must have effective drainage to prevent soil erosion. Cross-drains, where used, must be spaced and angled to prevent surface run-off and subsequent discharge of turbid water into streams or drainage lines.
4.5.3.7 Snigging and forwarding tracks must not be bladed off where this would result in an adverse impact on water quality or the loss of topsoil from the site.
4.5.4 Operational Restrictions
Operational Goal
During or following wet weather conditions, timber harvesting operations are modified or where necessary
suspended to minimise risks to soil and water quality values.
Mandatory Actions
4.5.4.1 Timber harvesting operations must be restricted or stopped where there is a risk to soil and water quality values during or following wet weather conditions.
4.5.4.2 Extraction, forwarding and haulage must be suspended when water begins to flow along tracks, except where appropriate preventive actions have been taken to address risks to off-site water quality.
66 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
Appendix A
Legislation, Regulations and Policies applying to timber harvesting operations
on State forest and private land in Victoria.
Appendix A provides a list of legislation, regulations and policies applying to timber harvesting
operations that are in addition to the Code. Appendix A is not an exhaustive list.
Commonwealth legislation Public Private
Aboriginal and Torres Strait Islander Heritage Protection Act 1984 Y Y
Agricultural and Veterinary Chemicals Act 1994 Y Y
Australian Heritage Council Act 2003 Y Y
Biosecurity Act 2015 Y Y
Environment Protection and Biodiversity Conservation Act 1999 Y Y
Export Control Act 1982 Y Y
National Environment Protection Measures (Implementation) Act 1998 Y Y
Native Title Act 1993 Y Y
Regional Forests Agreement Act 2002 Y Y
State legislation Public Private
Aboriginal Heritage Act 2006 Y Y
Accident Compensation Act 1985 Y Y
Agricultural and Veterinary Chemicals (Control of Use) Act 1992 Y Y
Building Act 1993 Y Y
Catchment and Land Protection Act 1994 Y Y
Climate Change Act 2017 Y Y
Conservation, Forests and Lands Act 1987 Y Y
Country Fire Authority Act 1958 Y Y
Crown Land (Reserves) Act 1978 Y N
Dangerous Goods Act 1985 Y Y
Electricity Safety Act 1998 Y Y
Emergency Management Act 2013 Y Y
Environment Protection Amendment Act 2018 Y Y
Environment Protection Act 2017 Y Y
Environmental Protection Act 1970 Y Y
Fences Act 1968 N Y
Firearms Act 1996 Y Y
Fisheries Act 1995 Y Y
Flora and Fauna Guarantee Act 1988 Y Y
Forests Act 1958 Y Y
Forests (Wood Pulp Agreement Act 1996) Y N
Heritage Act 2017 Y Y
Heritage Rivers Act 1992 Y Y
Land Act 1958 Y Y
Land Conservation (Vehicle Control) Act 1972 Y
Local Government Act 1989 N Y
Marine and Coastal Act 2018 Y Y
National Parks Act 1975 Y N
Occupational Health and Safety Act 2004 Y Y
Parks Victoria Act 2018 Y
Planning and Environment Act 1987 Y Y
Planning and Environment (Planning Schemes) Act 1996 N Y
Plant Biosecurity Act 2010 Y Y
Prevention of Cruelty to Animals Act 1986 Y Y
Reference Areas Act 1978 Y N
Road Management Act 2004 Y Y
Safety on Public Land Act 2004 Y N
State Owned Enterprises Act 1992 Y N
Summary Offences Act 1966 Y N
Sustainable Forests (Timber) Act 2004 Y N
Subordinate Legislation Act 1994 (Vic) Y Y
Traditional Owner Settlement Act 2010 Y N
Victorian Plantations Corporation Act 1993 Y Y
Water Act 1989 Y Y
Wildlife Act 1975 Y Y
Workplace Injury Rehabilitation and Compensation Act 2013 Y Y
Regulations* Public Private
Aboriginal Heritage Regulations 2018 Y Y
Agricultural and Veterinary Chemicals (Control of Use) Regulations
2017
Y Y
Conservation, Forests and Lands (Infringement Notice) Regulations
2017
Y Y
Country Fire Authority Regulations 2014 N Y
Dangerous Goods (Explosives) Regulations 2011 Y Y
Dangerous Goods (HCGD) Regulations 2016 Y Y
Dangerous Goods (Storage and Handling) Regulations 2012 Y Y
Electricity Safety (Electric Line Clearance) Regulations 2015 Y Y
Electricity Safety (Installations) Regulations 2009 Y Y
68 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)
Fences Regulations 2014 N Y
Flora and Fauna Guarantee Regulations 2011 Y N
Forests (Fire Protection) Regulations 2014 Y N
Forests (Licenses and Permits) Regulations 2009 Y N
Forests (Recreation) Regulations 2010 Y N
Heritage Regulations 2017 Y Y
Land Conservation (Vehicle Control) Regulations 2013 Y N
Occupational Health and Safety Regulations 2017 Y Y
Planning and Environment Regulations 2015 Y Y
Subordinate Legislation (Legislative Instruments) Regulations 2011 Y Y
Subordinate Legislation (Prevention of Cruelty to Animals Regulations
2008) Extension Regulations 2018
Y Y
Road Management (General) Regulations 2016 Y N
Traditional Owner Settlement Regulations 2017 Y N
Victorian Plantations Corporation (Register of Plantation Licences)
Regulations 2018
Y Y
Wildlife Regulations 2013 Y Y
Workplace Injury Rehabilitation and Compensation Regulations 2014 Y Y
Policy Public Private
Australia’s Biodiversity Conservation Strategy 2010-2030 Y Y
Code of Practice for Bushfire Management on Public Land 2012 Y N
Biodiversity 2037 – Protecting Victoria’s Environment (2017) Y Y
Invasive Plants and Animals Framework (2017) Y Y
National Forest Policy Statement (1992) Y Y
National Forest Industries Plan (2018) Y Y
National Indigenous Forest Strategy (2005) Y Y
Our Forests, Our Future (2002) Y Y
State Environment Protection Policy (Air Quality Management) Y Y
State Environment Protection Policy (Control of Noise from Commerce, Industry and Trade)
Y Y
State Environment Protection Policy (Prevention and Management of Contamination of Land)
Y Y
State Environment Protection Policy (Waters of Victoria) Y Y
Sustainability Charter for Victoria’s State forests (2006) Y N
Victoria's Climate Change Adaptation Plan (2017-2020) Y Y
Water for Victoria (2016) Y Y
*Most statutory rules including many of these sunset after 10 years.
70 Consultation Draft: Code of Practice for Timber Production 2014 (as amended 2019)