Upload
ahmed-elsherif
View
147
Download
2
Embed Size (px)
DESCRIPTION
Earned Value Analysis Concept & Application
Citation preview
Earned Value Analysis Concept and Application
Presented byAhmed Rami Elsherif
27/12/2012
Concept
Earned Value Analysis (EVA). Is a Project Management control technique which integrates Scope, Schedule and Cost data for objectively measuring project performance and progress.
Performance is measured by determining the budgeted cost of work performed (i.e., earned value) and comparing it to the actual cost of work performed (i.e., actual cost) and the planned cost of work performed (i.e. planned cost).
Definitions
ConceptAbbreviation
Description
Budget at Completion BAC Baseline cost of 100% of the project.
Actual Cost AC Total costs actually incurred so far.
Earned Value EVAmount of budget earned so far based on physical work accomplished, without reference to actual costs.
Planned Value PVThe budget for the physical work scheduled to be completed by the end of the time period.
Metrics
ConceptAbbreviation
Description
Cost Variance CVMeasure of cost overrun.CV = EV – AC
Schedule Variance SVMeasure schedule slippage. SV = EV – PV
Cost Performance Index CPICost efficiency ratio.CPI = EV/AC
Scheduled Performance Index
SPISchedule efficiency ratio.SPI = EV/PV
Estimate at Completion EACExpected total cost based on the current cost and schedule efficiency ratios.EAC = AC+((BAC-EV)/(CPI*SPI))
For example
The project is to build a 4 wall room. The cost per wall is 100 SAR and it will take 1 day to construct 1 wall. At the end of the 3 day we have finished 2.5 walls and our actual cost is 280 SAR then our values are :
Budget at Completion (BAC) = 400 SAR
Actual Cost (AC ) = 280 SAR
Earned Value (EV) = 250 SAR
Planned Value (PV) = 300 SAR
And based on the above data we can calculate the following:
Calculated Metrics
Cost Variance is CV = EV – AC = 250 – 280 = -30
we are over budget by 30 SAR
Scheduled Variance is SV = EV – PV = 250 – 300 = -50
we behind scheduled by 50 SAR
Cost Performance Index is CPI = EV / AC = 250 / 280 = .89
For each 1 SAR we spend we gain .89 halalas
Schedule Performance Index is SPI = EV / PV = 250 / 300 = .83
We are behind schedule by 17 %.
Estimate at Completion is EAC = AC+((BAC-EV)/(CPI*SPI)) = 483
If we continue with the same efficiency rates, we might end up with a total cost of 483 SAR.
Proposal
Recent research studies have shown that the tools and techniques of Earned Value Analysis have positive impact on improving project controls on Scope, Cost and Schedule and are good predictors of project success.
Popularity of EVA has grown significantly in recent years for which we would like to recommend using it for ATCO projects (i.e. construction, big projects in EWE, EWF).
For that we have developed a simple module in the EIS where project managers will enter the EV parameters which the system will combine with data booked in accounts and calculates the EV metrics.
Data from RAS ALKHER project is entered in the system for testing.
1. Login to EIS by assigned operational staff.
2. Process the EV report of his particular division.
3. Enter the EV values of the Month and any comments regarding the variances.
4. Use the data and reports in the monthly project status reporting.
Steps in EIS
Project EV data entered by Operations on a
monthly basis
Projects status dashboard report
Graphical Presentations
Proposed Plan
1. Agree with you if this is a suitable solution. We can discuss this by taking RAS ALKHER project data which is already entered in the system as an example.
2. If Yes share it with operations for feedback on possible enhancements or improvements.
3. Identify users in each divisions and do training.
4. Start using the new process.