Public Works
FACILITIES, PARKS AND INFRASTRUCTURE CAPITAL IMPROVEMENT PRESENTATION TO THE EVANSTON CITY COUNCIL
SEPTEMBER 30, 2013
INTRODUCTIONSection 1 Facilities: Homayoon Pirooz,
Assistant Director of Public Works Infrastructure and Engineering
Section 2 Parks: Stefanie Levine,
Senior Project Manager Facilities and Parks
Section 3 Streets, Sidewalks & Alleys:
Suzette Robinson, Director of Public Works
Public Works Summary: Suzette Robinson
2
SECTION 1FACILITIES OVERVIEW
2009 to 2013 Cost Summary Slides and Tables
• Civic Center• Other City Facilities• Community Facilities• Lakefront Facilities
Proposed Projects for 2014
Future Focus
3
LORRAINE H. MORTON CIVIC CENTER
4
$1,772,200
$99,000
$417,000
$139,000
$135,000
$66,000 $44,500
$221,000 $16,300
$49,200 $329,000 2009-13 Capital Investments
Roof replacement - $1,772,200 Front entry reconstruction - $99,000Washrooms renovations - $417,000 Fire pump replacement - $139,000Asbestos abatement - $135,000 Tuckpointing - $66,000Hallway carpet tiles - $44,500 Parking lot lighting - $221,000ADA doors - $16,300 Misc. HVAC - $49,200Miscellaneous - $329,000
Total 5 year investment: $3.29 million
OTHER CITY FACILITIES
5
$1,214,300
$710,000 $3,277,000
2009-13 Capital Investments
Service Center - $1,214,300 Fire Stations - $710,000
Police/Fire Headquarters - $3,277,000
Total 5 year investment: $5.20 million
COMMUNITY CENTERS
6
$82,000 $173,000
$15,000
$252,000
$246,000 $1,267,500
2009-13 Capital Investments
Chandler-Newberger Center - $82,000 Crown Center - $173,000
Ecology Center - $15,000 Fleetwood-Jourdain Center - $252,000
Levy Senior Center - $246,000 Noyes Cultural Arts Center - $1,267,500
Total 5 year investment: $2.04 million
LAKEFRONT FACILITIES
7
$1,324,700
$435,000
$1,542,000
$98,000 $32,000 2009-13 Capital Investments
Clark Street Beach House / Entry Drive - $1,324,700
Dempster Street Locker Building and Boat Racks - $435,000
Lakefront Bike Path - $1,542,000
Lagoon Renovation (design only) - $98,000
Harley Clark Mansion - $32,000
Total 5 year investment: $3.43 million
FACILITIES EXPENDITURES
8
24%
37%
15%
25%2009-13 Capital Investments By Percentages
Civic Center - 24% Other City Facilities - 37% Community Centers - 15%
Lakefront Facilities - 25%
Total 5 year investment: $13.96 million
PROPOSED 2014FACILITIES PROJECTS
Project Name GO Bonds Carryover Other Sources Total
Animal Shelter Roof / HVAC $120,000 $120,000
Arrington Lakefront Lagoon Renovations $275,000 $200,000 $900,000 $1,375,000
Chandler-Newberger Study / Interior Improvements $250,000 $250,000
Church Street Boat Ramp Repairs $350,000 $200,000 $550,000
Civic Center Boiler Building Roof and Masonry $120,000 $120,000
Civic Center Security $300,000 $300,000
Clark Street Beach Bird Habitat Restoration $173,000 $173,000
Crown Partnership Study $73,000 $73,000
Dempster Street Beach Boat Racks $75,000 $75,000
Ecology Center Addition $100,000 $100,000
Facilities Capital Contingency $250,000 $250,000
Fire Station 2 First Floor Remodeling $360,000 $360,000
Fleetwood-Jourdain Study / Interior Improvements $250,000 $250,000
Levy Center Structural Study $100,000 $100,000
Salt Dome Reconstruction $380,000 $380,000
Service Center Electrical Study $35,000 $35,000
Total $2,200,000 $1,038,000 $1,273,000 $4,511,000
9
FACILITIES EXPENDITURES
10
19%
35%15%
30%
2009-14 Capital Investments By Percentages
Civic Center - 19% Other City Facilities - 35% Community Centers - 15%
Lakefront Facilities - 30%
Total 6 year investment: $18.47 million
FACILITIES FUTURE FOCUS1. Investments in Existing Community Centers
• Increase investment rate (15% current)?• Chandler• Fleetwood• Levy
2. Harley Clarke Mansion
• Recreation facility?• Park expansion?
3. Robert Crown
• P3 update• What next?
4. Skate Park
• Council direction needed• Locations for consideration
5. Recycling Center
• Recreation facility?• Park expansion?
6. Shared Recreation Facilities
• District 65• ETHS• Northwestern University
11
SECTION 2PARKS OVERVIEW
12
2009 to 2013 Cost Summary
Proposed Projects for 2014
Future Focus
PARKINVESTMENTS
13
Total 5 year investment: $890,900
$269,300
$273,200
$139,800
$133,600
$75,000 2009-13 Capital Investments
Brummel Richmond Tot Lot - $269,300 Firemens Park - $273,200 James Park - $139,800
Ladd Arboretum - $133,600 Twiggs Park - $75,000
PROPOSED 2014PARK PROJECTS
14
Project Name GO Bonds Carryover Other Sources Total
Baker Park $75,000 $25,000 $100,000
Fountain Square Design Study $300,000 $300,000
Grey Park $56,500 $56,500
Ladd Arboretum $22,000 $88,000 $110,000
Needs Assessment and Evaluation $150,000 $150,000
Penny Park $130,000 $20,000 $150,000
Total $225,000 $208,500 $433,000 $866,500
PARKS FUTURE FOCUS1. Needs Assessment and Evaluation
• Establish current conditions and uses• Determine park access / proximity to users• Compare Evanston to national standards• Define future needs• Establish long term strategy for future improvements
2. Partnership Opportunities
• Schools• Open streets / parking lots
3. Fund Raising
• Community groups• Private organizations• Grants
15
SECTION 3 INFRASTRUCTURE
16
Primary
1 23
45
6
789
2010 TO 2014PRIMARY STREET RESURFACING
17
39.64%
3.32%
12.47%8.97%
4.62%
7.86%
5.22%
7.41%
4.94% 5.55%2010-2014 Streets Resurfaced by Ward/Square Yards
Primary Streets-173,176.58 sq yrds Ward 1-14,507.44 sq yrds Ward 2-54,483.11 sq yrds Ward 3-39,206.66 Ward 4-20,177.77
Ward 5-34,315.44 Ward 6-22,799.83 Ward 7-32,354.44 Ward 8-21,572.44 Ward 9-24,257.67
2
Pri-mary
13
4
5
6
7 8 9
SURFACE CONDITIONPRIMARY ROUTES
18
13.35%
19.19%
34.02%
33.45% Very Poor less than 40
Poor 40-50
Poor 50-60
Fair 60-65
SURFACE CONDITION BY WARD BELOW 40
19
1
2
46
7
89
SURFACE CONDITION BY WARD 40 TO 49
20
1
23
4
56
7
8
9
SURFACE CONDITION BY WARD 50 TO 59
21
9 12
3
4
567
8
SURFACE CONDITION BY WARD 60 TO 65
22
2
3
4
56
7
8
9 1
CITY OF EVANSTON'SMETHODOLOGY FOR RESURFACING
• Utility Priority
• Development Priority
• Grant/TIF Priority
• Ward Equity
• Surface Condition
• Citizen Input/Field Review
23
RESURFACING COMPARISON
24
Area Percentage of City Average Percentage Resurfaced
Primary 42% 39.64%
Ward 1 3% 3.32%
Ward 2 9% 12.47%
Ward 3 5% 8.97%
Ward 4 5% 4.62%
Ward 5 4% 7.86%
Ward 6 10% 5.22%
Ward 7 9% 7.41%
Ward 8 6% 4.94%
Ward 9 7% 5.55%
STREETS SUMMARY
Total needed to bring roads up to Fair category by 2018
$36,684,999
Current Funding Levels and Methodology
• $1.4 million MFT, 1.8 million CIP• $3.2 million total annually is not sufficient to achieve an
overall Fair condition
25
PRIMARY ROUTE SUMMARY
26
SURFACE CONDITION Total SQ YD CostLess than 40 35722.42 $1,821,84440 - 50 51374.89 $2,620,11950 - 59 91053.18 $4,643,71260 - 65 89531.91 $4,566,127Total $13,651,802
SURFACE CONDITION Total SQ YD CostLess than 40 31141.00 $1,276,781 40 - 50 96344.40 $3,950,120 50 - 59 225700.80 $9,253,733 60 - 65 208599.10 $8,552,563 Total $23,033,197
LOCAL STREETS SUMMARY
SIDEWALK PROGRAMTotal miles of sidewalk – 268 miles
Current Sidewalk Methodology
• Funding: 50% Resident/ 50% City• Result: 50,000 SQ FT sidewalk replaced annually
Option One
• Funding: 60% Resident/ 40% City• Result: 60,000 SQ FT sidewalk replaced annually
Option Two
• Funding: 80% Resident/ 20% City• Result: 80,000 SQ FT sidewalk replaced annually
27
Before
After
ALLEY PROGRAM
28
Total length of alleys in the City – 70 miles
Length of paved alley – 41.7 miles
Previous Alley Methodology
• Funding: 100% Resident• Result: Program participation dwindled
Current Alley Methodology
• Funding: 50% Resident/ 50% City• Result: Initially increased and now program numbers are declining
Option One
• Funding: 40% Resident/ 60% City• Result: More applications, depleting funds
Option Two
• Funding: 20% Resident/ 80% City• Result: More applications, depleting funds
29
QUESTIONS