Upload
thedalles
View
5.875
Download
1
Tags:
Embed Size (px)
Citation preview
Water Rate Analysis
Will NorrisAdministrative Intern
City of The Dalles
Note to reader: Extra text has been added to the following slides that didn’t exist in the original PowerPoint, as it had a verbal presentation.
For further information please refer to the 7/25/11 Council Agenda Packet at: http://www/newsite/sites/default/files/imported/agendas/city_council/PDFs/Agenda072511.pdf
Agenda1. Water Utility Background
– Water Consumption– Previous Forecasts and Actuals– Expenditures and Revenues
2. Capital Requirements– Operations– Capital Improvements
3. Revenue Predictions4. Future Options
City of the Dalles - Water Rate Analysis
Consumption History
City of the Dalles - Water Rate Analysis
Background Capital Requirements Revenue Predictions Options
FY01/0
2
FY02/0
3
FY03/0
4
FY04/0
5
FY05/0
6
FY06/0
7
FY07/0
8
FY08/0
9
FY09/1
0
FY10/1
1 -
200,000
400,000
600,000
800,000
1,000,000
1,200,000
Metered water data from Utility Billing shows that system-wide water use has changed little in the past ten years
Possible reasons could include conservation, reaction to higher water prices and more water efficient appliances
Previous revenue predictions assumed increasing water use and more development.
Lower than expected water sales has meant that revenue expectations have not been met
Background Capital Requirements Revenue Predictions
Previous Revenue Predictions
0
1,000,000
2,000,000
3,000,000
4,000,000
5,000,000
Revenue Predicted vs. Actual2006 staff report Actual
($)
Mill
ions
City of the Dalles - Water Rate Analysis
Difference
$1.3 Million
Options
FY 97/98
FY 98/99
FY 99/00
FY 00/01
FY 01/02
FY 02/03
FY 03/04
FY 04/05
FY 05/06
FY 06/07
FY 07/08
FY 08/09
FY 09/10
$-
$500,000
$1,000,000
$1,500,000
$2,000,000
$2,500,000
$3,000,000
$3,500,000
$4,000,000
Total Revenue Operating Costs and Debt Payments Fund Balance
Water Utility History
City of the Dalles - Water Rate Analysis
Background Capital Requirements Revenue Predictions
Flat Rates/Lowered Reserves
Rate Increases/Capital Investments
Options
Water Utility Personnel and Materials(2011 Dollars)
City of the Dalles - Water Rate Analysis
Background Capital Requirements Revenue Predictions Options
FY 01/02
FY 02/03
FY 03/04
FY 04/05
FY 05/06
FY 06/07
FY 07/08
FY 08/09
FY 09/10
$-
$500,000
$1,000,000
$1,500,000
$2,000,000
$2,500,000
$3,000,000
Adjusting for inflation, the operating costs within the Water Utility have ,on average, increased 1.6% per year.
This is as healthcare, energy and metals prices have experienced large increases.
FY 2011/12 Debt Service
City of the Dalles - Water Rate Analysis
Revenue Predictions
2007 Water Revenue Bond $561,405(Wicks Clear Well, Dam permitting, Lone Pine well)
FFC 2008 $59,971(Public Works Shop Relocation)
FFC 2009 $32,421(West 1st Local Improvement District)
ARRA Loan $200,892(Vista Reservoir)
Total $854,689
OptionsBackground Capital Requirements
While operating costs have remained stable, implementing the Water Master Plan as well as meeting unexpected regulatory costs has substantially increased the debt of the utility.
Required Revenue to meet Expenses
Meeting current debt service and continuing forward historic price trends will require significant increases in Revenue in order to maintain fund balances.
Background Capital Requirements Revenue Predictions
City of the Dalles - Water Rate Analysis
Options
$-
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
Previous Actual Future Projected
Capital Projects
City of the Dalles - Water Rate Analysis
Background Capital Requirements Revenue Predictions Options
Thompson / 19 St. $650,000DEQ Temp Mitigation $1,200,000Paint Sorosis Reservoir
$670,000
Clean Garrison Reservoir
$15,000
Dog River Line Replacement
$6,800,000
Lone Pine Well Enhancement
$1,000,000
Paint Columbia View Reservoir
$300,000
3rd St. Streetscape $600,000Finished Water Pipeline
$10,000,000
TOTAL $22,000,000
Port Pipeline $950,000
There are still many projects that need to be completed in the next decade. Only one of which is primarily capacity enhancement.
The rest are meeting federal regulations or securing the quality and quantity of water the city already uses
Background Capital Requirements Revenue Predictions
Revenue PredictionsCity of the Dalles - Water Rate Analysis
Options
Previous revenue predictions created hypothetical scenarios and then calculated what billing would result.
This analysis instead used a regression equation to model the relationship between rate increases and additional revenue.Note: Background graph is not necessarily actual model statistics
City of the Dalles - Water Rate Analysis
Background Capital Requirements Revenue Predictions
FY 01/02
FY 02/03
FY 03/04
FY 04/05
FY 05/06
FY 06/07
FY 07/08
FY 08/09
FY 09/10
FY 10/11
FY 11/12
$1,250,000
$1,750,000
$2,250,000
$2,750,000
$3,250,000
$3,750,000
$4,250,000
+ 0% rate+ $3k revenue
+ 10% rate+ $311k
Options
Years with flat rate increases saw flat revenue growth. After instituting successive 10% rate increases, each year saw about a $311,000 increase in revenue.
Background Capital Requirements Revenue Predictions Options
0% 1% 2% 3% 4% 5% 6% 7% 8% 9% 10%
-$200,000
-$100,000
$0
$100,000
$200,000
$300,000
$400,000
$500,000X Variable 1 Line Fit Plot
$0
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
$7,000,000
$8,000,000
Actual Predicted Revenue
0% 1% 2% 3% 4% 5% 6% 7% 8% 9% 10%
-$200,000
-$100,000
$0
$100,000
$200,000
$300,000
$400,000
$500,000X Variable 1 Line Fit Plot
$-
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
$7,000,000
$8,000,000
Actual Predicted Revenue
City of the Dalles - Water Rate Analysis
Using this relationship to model a regression equation, any increment of rate increases can be used to estimate revenue growth.
Background Capital Requirements Revenue Predictions Options
City of the Dalles - Water Rate Analysis
Options1. On-time
– This is a safe scenario– Each capital investment completed as planned
2. Delayed– Each project is delayed several years to allow the supporting
rate base to grow
3. Critically Delayed– Increases risk of infrastructure failure and emergency
maintenance
A. Minimum Rate IncreasesB. Stable Rate Increases
City of the Dalles - Water Rate Analysis
Background Capital Requirements Revenue Predictions Options
Option #1 On Time
City of the Dalles - Water Rate Analysis
Background Capital Requirements Revenue Predictions Options
• Least risk and highest upfront cost option
FY 11/12 10%FY 12/13 16%FY 13/14 16%FY 14/15 14%FY 15/16 10%FY 16/17 10%FY 17/18 10%FY 18/19 8%FY 19/20 8%FY 20/21 6%
Eight of the ten projects are bonded in FY 11/12. The last two projects, port pipeline extension and replacing the finished water pipeline are bonded in FY 16/17
Option #2 A Delayed
City of the Dalles - Water Rate Analysis
Background Capital Requirements Revenue Predictions Options
• Each project delayed several years• Three bond issues requiredFY 11/12 10%FY 12/13 10%FY 13/14 6%FY 14/15 6%FY 15/16 8%FY 16/17 12%FY 17/18 14%FY 18/19 12%FY 19/20 12%FY 20/21 14%
Thompson/19th street project is paid with cash in FY 11/12. The first bonding begins in FY 14/15.
This plan requires three rounds of bonding.
Option #2 B Delayed
City of the Dalles - Water Rate Analysis
Background Capital Requirements Revenue Predictions Options
• Rates are spread more evenly• Fund Balances grow before projects
FY 11/12 10%FY 12/13 10%FY 13/14 10%FY 14/15 10%FY 15/16 8%FY 16/17 8%FY 17/18 8%FY 18/19 10%FY 19/20 10%FY 20/21 10%
Exact same Capital Project timeline at Option #2 A.
Version B prioritizes stable rate increases, rather than just-in-time rate increases.
Option #3 A Critically Delayed
City of the Dalles - Water Rate Analysis
Background Capital Requirements Revenue Predictions Options
• Projects pushed to their furthest extreme• Dog River Permitting will require renewal
FY 11/12 10%FY 12/13 10%FY 13/14 6%FY 14/15 8%FY 15/16 4%FY 16/17 6%FY 17/18 10%FY 18/19 10%FY 19/20 15%FY 20/21 16%
Thompson/19th st. is still paid cash this year. The largest project, Dog River Pipeline and the Finished Water Pipeline are delayed until FY 19/20.
Option #3 B Critically Delayed
City of the Dalles - Water Rate Analysis
Background Capital Requirements Revenue Predictions Options
• More evenly spacing rate increases leads to a large growth in fund balances
FY 11/12 10%FY 12/13 8%FY 13/14 8%FY 14/15 8%FY 15/16 8%FY 16/17 8%FY 17/18 8%FY 18/19 8%FY 19/20 10%FY 20/21 12%
Version B prioritizes more stable rates. However, with the two larges projects, Dog River pipeline and Finished water pipeline replacements both delayed, major rate increases at the end of the decade are unavoidable.
City of the Dalles - Water Rate Analysis
Discussion