56
Page | 1 Presented by: John Glinski Tappan Zee Constructors, LLC

2015 CRW - Project Spotlight: New NY Bridge Project

Embed Size (px)

Citation preview

PowerPoint Presentation

Presented by: John GlinskiTappan Zee Constructors, LLC

Page | #

1

Presented by: John GlinskiTappan Zee Constructors, LLC

Page | #

2

THE NEW NY BRIDGE

3

Tappan Zee Bridge, 25 miles north of New York CityNew York City

Site Location

Page | #

4

Existing bridge carries 138K vehicles per day vs. design capacity of 100KFunctionally obsolete, major structural and operational deficiencies, high accident rateForecasting $1B in maintenance over next 10 years

Existing Tappan Zee Bridge

Page | #

510/1/2015Delivering a New NY Bridge for the 21st CenturyIEEE Tappan Zee Subsection Joint Meeting with Westchester Chapters of ASME & SME - June 18, 2014

Built between March 1952 and December 15, 1955 (44 months)81 million (780m est. 2014 dollars)Existing Tappan Zee Bridge

Page | #

610/1/2015Delivering a New NY Bridge for the 21st CenturyIEEE Tappan Zee Subsection Joint Meeting with Westchester Chapters of ASME & SME - June 18, 2014

7

THE NEW NY BRIDGE

Two independent bridges

Total length, 3.1 miles each

43 Piers, 2 abutments

Main span, 0.4 mile long cable stay

Approach bridge, 2.7 mile long, 350-ft steel girders

Design-Build, $3.9 billion

Page | #

New NY Bridge2 spans, 8 general traffic lanes12 lanes, wide shoulders, emergency access lanes, shared use path Shared Use PathNorthern Span96Westchester to Rockland

Southern Span87Rockland to Westchester

ShoulderShoulder

Emergency Access Potential Bus Lane

THE NEW NY BRIDGE

Page | #

9

BELVEDERES AND SHARED USE PATH

South NyackTarrytown234561

Page | #

The New New York Bridge will include belvederes and shared use paths for pedestrians and cyclists creating a new dimension to connectivity in the Hudson River Valley. Once the bridge is complete you will be able to walk, bike and enjoy the stunning views in the bridge.10

Pile Installation

11

Piles6 foot4 foot

Page | #

12

Vibratory HammerImpact Hammer

Production Pile Installation

Over 1000 piles50 miles of steel pilesDeepest pile over 400 feetMinimal Field Welding Ultrasound Inspected

Page | #

13

Heavy Ram Weight Required Due to Pile Wall ThicknessIHC S-800 Hydraulic Hammer

Page | #

14

Underwater Noise Mitigation

Bubble CurtainSturgeon Monitoring

Page | #

15

Underwater Noise Mitigation

Page | #

16

Main Span Foundations

Page | #

17

Material barge with 4-diameter steel pipe pilesImpact hammer with noise attenuationRinger cranePile driving templateWelding tentTYPICAL PILE DRIVING SETUP

Page | #

Delivering a New NY Bridge for the 21st Century10/1/2015IEEE Tappan Zee Subsection Joint Meeting with Westchester Chapters of ASME & SME - June 18, 201418

MAIN SPAN FOUNDATIONS

Piles are driven into bedrock and arranged into a rectangular grid

Page | #

Why is the main span built where it is?

The geology of the riverbed under the main spans offers both a deep water channel for navigation and relatively shallow depth to bedrock for terminating the main span piles.

19

MAIN SPAN PILE CAPS

12,000 CY of concrete is poured into pile cap and formed with rebar and piles

Page | #

Each of the main span towers (west tower and east tower) will have a massive foundation comprised of piles and a cast-in-place pile cap.

20

Main span pile cap Lowering

21

APPROACH CONSTRUCTION

22

FOUNDATION DESIGNPRECAST PILE CAPS

Concrete Pile Caps used on the approach are precast in VirginiaTravel by barge to project site

Page | #

The larger 6 foot diameter piles are required for the piers closest to the navigation channel because they are much more efficient at resisting the large lateral ship impact forces than the 4 foot diameter piles used elsewhere2310/1/2015Delivering a New NY Bridge for the 21st CenturyIEEE Tappan Zee Subsection Joint Meeting with Westchester Chapters of ASME & SME - June 18, 2014

PRE-CAST PILE CAP INSTALLATION

Page | #

Cranes carefully lower these basketball court sized concrete tubs into place24

CIP PIER COLUMN CONSTRUCTION

Page | #

2510/1/2015Delivering a New NY Bridge for the 21st CenturyIEEE Tappan Zee Subsection Joint Meeting with Westchester Chapters of ASME & SME - June 18, 2014

Storage and Office BuildingsCompleted Sub-AssemblyAssembly AreaGirder SectionsDelivery TruckTrestlesDelivery BargeMi-JacksCOEYMANS PRE-ASSEMBLY YARD

Page | #

Delivering a New NY Bridge for the 21st Century10/1/2015IEEE Tappan Zee Subsection Joint Meeting with Westchester Chapters of ASME & SME - June 18, 201426

APPROACH SPAN STEEL FABRICATION

Page | #

2710/1/2015Delivering a New NY Bridge for the 21st CenturyIEEE Tappan Zee Subsection Joint Meeting with Westchester Chapters of ASME & SME - June 18, 2014

CranesMore than 40 cranes on siteAdditional cranes at off site locationsSpecialty cranesSpecialty lifting systems and gantries

Page | #

4 TOWER CRANES

Page | #

Rigging

Page | #

Lifting Frames

Page | #

Pier cap rebar

Concrete pier caps used on the approach are precast in VirginiaTravel by barge to project site

Page | #

32

Precast Pier cap

Page | #

Precast Pier cap

Page | #

Up to 600 tonsPrecision placement

Precast pile cap lifting system

Page | #

Precast pile cap lifting system

Page | #

Girder lifting system

1200 ton lifting capacity Hydraulic adjustments 410 long girder assembly 3 girders assembled

Page | #

Crosby inspection system

Page | #

What is RFID?RFID = Radio Frequency IdentificationAn ID tag not affected by dirt or water that holds up in most rigging environmentsIn QUIC-CHECKs adaptation of this technology, the tag must be touched by the scanner. This eliminates the potential of scanning an adjacent productSeveral variations of the technology:Active tags: Contain a battery; always transmitting a signal (a large tag, not suitable for most rigging applications)Passive tags: Tag contains no batter; activated by the RFID scanner (this is what QUIC-CHECK uses)Transmission Frequency: Low Frequency, High Frequency, Ultra High Frequency (QUIC-CHECK uses High Frequency)Examples of RFID technology in use:Toll collection systems like EZ-Pass and PikePassContactless payment terminals like ApplePay

Page | #

Crosby QUIC-CHECK Version 3.0

Local Network ServerClient PCsReportsHandheld w/Integrated RFID ScannerData is stored either on network server (as shown) or on client PCHandheld unit used to conduct field inspectionsThis is synced to a client PC via USB cable, then data stored to serverReports selected on PC, then generated from network server database, where they can be stored or emailed

RFID Tags

Page | #

Crosby QUIC-CHECK Version 3.0

Page | #

Crosby QUIC-CHECK Version 3.0

Application Screen Images

Page | #

Tappan Zee & Crosby QUIC-CHECKTZC began using Crosby QUIC-CHECK in 2013How TZC is using it:Currently tracking 8,500 pieces of rigging inspections and location informationTZC requires all rigging be RFID-equippedUsed for lift planning, inventory and part replacementEliminates the need for handwritten inspection records; significantly reduces inspection timeTZC Developed a Scope of Work document all rigging suppliers must comply with:By adhering to this requirement, TZC suppliers enter the rigging gear directly to Crosby QUIC-CHECK, providing TZC with:Supplier identification (each supplier assigned a unique identifier)Delivery location (initial location)Order numberProduct details (sling type, capacity, etc.)In Service DateInstantly added to TZC QUIC-CHECK database

Crosby DistributorsCrosby QUIC-CHECK Data Sharing Server

Page | #

QUIC-CHECK The Next GenerationCrosby QC User

Scaleable DatabaseAnytime ReportingUser AnalyticsComing 1st Qtr, 2016

Enhancements:All data stored in the cloudUses iPhone/iPads/Android phones/Android tablets as the mobile deviceData changed via one device will instantly appear on all other devices; No manual syncing requiredMuch faster field operationDatabase will dynamically scale to required sizeMore robust data sharingPhotos can be stored with product inspection recordDeeper training integrationState of the art programming code and hardwareWorldwide functionalitySupport for pre-programmed products from Crosby (4th Qtr, 2016)

Page | #

Page | #

Page | #

Safety

Page | #

47

Logistics

Page | #

29 BoatsCrew boatsTug boatsother work boats

Page | #

weather

Page | #

50

weather

Page | #

51

MAN OVERBOARD TRAINING

Page | #

I LIFT NY SUPER CRANE

I Lift NY Super Crane

. . . the I Lift NY Super Crane! One of the worlds largest floating cranes. Having this on the project dramatically speeds up construction and reduces cost and dredging needed. This behemoth posts some great statistics:

The current photo in stowed position.54

PLACEMENT OF FIRST GIRDER ASSEMBLY

Page | #

QUESTIONS?