SOFTWARE PROJECT MANAGEMENT

TOPIC 8

1

Page 2: 8.project management chapter 8

Software project managementConcerned with activities involved in ensuring that

software is delivered on time and on schedule and in accordance with the requirements of the organisations developing and procuring the software.

Project management is needed because software development is always subject to budget and schedule constraints that are set by the organisation developing the software.

2

Page 3: 8.project management chapter 8

Management activities1. Proposal writing.2. Project planning and scheduling.3. Project costing.4. Project monitoring and reviews.5. Personnel selection and evaluation.6. Report writing and presentations.

3

Page 4: 8.project management chapter 8

Management commonalitiesThese activities are not peculiar to software management.Many techniques of engineering project

management are equally applicable to software project management.

Technically complex engineering systems tend to suffer from the same problems as software systems.

4

Page 5: 8.project management chapter 8

Project staffingMay not be possible to appoint the ideal people to work

on a project:i. Project budget may not allow for the use of highly-

paid staff;ii. Staff with the appropriate experience may not be

available;An organisation may wish to develop employee skills on a

software project.Managers have to work within these constraints especially

when there are shortages of trained staff.

5

Page 6: 8.project management chapter 8

Project planningProbably the most time-consuming project management

activity.Continuous activity from initial concept through to

system delivery. Plans must be regularly revised as new information becomes available.

Various different types of plan may be developed to support the main software project plan that is concerned with schedule and budget.

6

Page 7: 8.project management chapter 8

Types of project plans

7

Plan Description

Quality plan Describes the quality procedures and standards that will beused in a project. See Chapter 27.

Validation plan Describes the approach, resources and schedule used forsystem validation. See Chapter 22.

Configurationmanagement plan

Describes the configuration management procedures andstructures to be used. See Chapter 29.

Maintenance plan Predicts the maintenance requirements of the system,maintenance costs and effort required. See Chapter 21.

Staff developmentplan.

Describes how the skills and experience of the project teammembers will be developed. See Chapter 25.

Page 8: 8.project management chapter 8

Project planning process

8

Page 9: 8.project management chapter 8

The project planThe project plan sets out:

I. The resources available to the project;II. The work breakdown;III. A schedule for the work.

9

Page 10: 8.project management chapter 8

Project plan structure1. Introduction.2. Project organisation.3. Risk analysis.4. Hardware and software resource requirements.5. Work breakdown.6. Project schedule.7. Monitoring and reporting mechanisms.

10

Page 11: 8.project management chapter 8

Activity organizationActivities in a project should be organised to produce

tangible outputs for management to judge progress.Milestones are the end-point of a process activity.Deliverables are project results delivered to customers.The waterfall process allows for the straightforward

definition of progress milestones.

11

Page 12: 8.project management chapter 8

Milestones in the RE process

12

Evalua tionrepor t

Prototypede velopment

Userrequirements

Requir ementsanalysis

Feasibilityrepor t

Feasibilitystud y

Architectur aldesign

Designstud y

Systemrequirements

Requir ementsspecification

ACTIVITIES

MILESTONES

Page 13: 8.project management chapter 8

Project schedulingSplit project into tasks and estimate time and

resources required to complete each task.Organize tasks concurrently to make optimal use of

workforce.Minimize task dependencies to avoid delays

caused by one task waiting for another to complete.Dependent on project managers intuition and experience.

13

Page 14: 8.project management chapter 8

The project scheduling process

14

Estimate resourcesfor activities

Identify activitydependencies

Identifyactivities

Allocate peopleto activities

Softwarerequirements

Activity chartsand bar char ts

Create projectchar ts

Page 15: 8.project management chapter 8

Scheduling problemsEstimating the difficulty of problems and hence the cost of

developing a solution is hard.Productivity is not proportional to the number of people

working on a task.Adding people to a late project makes it later because of

communication overheads.The unexpected always happens. Always allow contingency

in planning.

15

Page 16: 8.project management chapter 8

Bar charts and activity networksGraphical notations used to illustrate the project schedule.Show project breakdown into tasks. Tasks should not be

too small. They should take about a week or two.Activity charts show task dependencies and the critical

path.Bar charts show schedule against calendar time.

16

Page 17: 8.project management chapter 8

Task durations and dependencies

17

Activity Duration (days) Dependencies

T1 8

T2 15

T3 15 T1 (M1)

T4 10

T5 10 T2, T4 (M2)

T6 5 T1, T2 (M3)

T7 20 T1 (M1)

T8 25 T4 (M5)

T9 15 T3, T6 (M4)

T10 15 T5, T7 (M7)

T11 7 T9 (M6)

T12 10 T11 (M8)

Page 18: 8.project management chapter 8

Activity network

18

star t

T2

M3T6

Finish

T10

M7T5

T7

M2T4

M5

T8

4/7 /03

8 da y s

14/7 /03 15 da y s

4/8/03

15 da ys

25/8/03

7 da ys

5/9/03

10 day s

19/9/03

15 da ys

11/8/03

2 5 da ys

10 da y s

20 da y s

5 da y s25/7 /03

15 da y s

25/7 /03

1 8/7 /03

10 da ys

T1

M1 T3T9

M6

T11

M8

T12

M4

Page 19: 8.project management chapter 8

Activity timeline

19

4/7 11/7 18/7 2 5/7 1/8 8/8 15/8 22/8 29/8 5/9 12/9 19/9

T4

T1T2

M1

T7T3

M5

T8

M3

M2

T6

T5

M4

T9

M7

T10

M6

T11M8

T12

Star t

Finish

Page 20: 8.project management chapter 8

Staff allocation

20

4/7 11/7 18/7 25/7 1/8 8/8 15/8 22/8 29/8 5/9 12/9 19/9

T4

T8 T11

T12

T1

T3

T9

T2

T6 T10

T7

T5

Fred

Jane

Anne

Mary

Jim

Page 21: 8.project management chapter 8

Risk managementRisk management is concerned with identifying risks

and drawing up plans to minimise their effect on a project.

A risk is a probability that some adverse circumstance will occur ◦ Project risks affect schedule or resources;◦ Product risks affect the quality or performance of the

software being developed;◦ Business risks affect the organisation developing or

procuring the software.

21

Page 22: 8.project management chapter 8

Software risks

22

Risk Affects Description

Staff turnover Project Experienced staff will leave the project before it is finished.

Management change Project There will be a change of organisational management with different priorities.

Hardware unavailability Project Hardware that is essential for the project will not be delivered on schedule.

Requirements change Project and product

There will be a larger number of changes to the requirements than anticipated.

Specification delays Project and product

Specifications of essential interfaces are not available on schedule

Size underestimate Project and product

The size of the system has been underestimated.

CASE tool under-performance

Product CASE tools which support the project do not perform as anticipated

Technology change Business The underlying technology on which the system is built is superseded by new technology.

Product competition Business A competitive product is marketed before the system is completed.

Page 23: 8.project management chapter 8

The risk management process1. Risk identification◦ Identify project, product and business risks;

1. Risk analysis◦ Assess the likelihood and consequences of these risks;

1. Risk planning◦ Draw up plans to avoid or minimise the effects of the

risk;1. Risk monitoring◦ Monitor the risks throughout the project;

23

Page 24: 8.project management chapter 8

The risk management process

24

Risk avoidanceand contingency

plans

Risk planning

Prioritised risklist

Risk analysis

List of potentialrisks

Riskidentification

Riskassessment

Riskmonitoring

Page 25: 8.project management chapter 8

Risk identificationi. Technology risks; risks that derive from the software

or hardware technologies that are used to develop the system.

ii. People risks; risks that are associated with the people in the development team.

iii. Organisational risks; risks that derive from organizational environment where the software is being developed.

iv. Requirements risks; risks that derive from changes to the customer requirements and the process of managing the requirements change.

v. Estimation risks; risks that derive from the management estimates of the resources required to build the system.

25

Page 26: 8.project management chapter 8

Risks and risk types

26

Risk type Possible risks

Technology The database used in the system cannot process as many transactions per secondas expected.Software components that should be reused contain defects that limit theirfunctionality.

People It is impossible to recruit staff with the skills required.Key staff are ill and unavailable at critical times.Required training for staff is not available.

Organisational The organisation is restructured so that different management are responsible forthe project.Organisational financial problems force reductions in the project budget.

Tools The code generated by CASE tools is inefficient.CASE tools cannot be integrated.

Requirements Changes to requirements that require major design rework are proposed.Customers fail to understand the impact of requirements changes.

Estimation The time required to develop the software is underestimated.The rate of defect repair is underestimated.The size of the software is underestimated.

Page 27: 8.project management chapter 8

Risk analysisAssess probability and seriousness of each risk.Probability may be very low, low, moderate, high

or very high.Risk effects might be catastrophic, serious,

tolerable or insignificant.

27

Page 28: 8.project management chapter 8

Risk analysis

28

Risk Probability Effects

Organisational financial problems force reductions inthe project budget.

Low Catastrophic

It is impossible to recruit staff with the skills requiredfor the project.

High Catastrophic

Key staff are ill at critical times in the project. Moderate Serious

Software components that should be reused containdefects which limit their functionality.

Moderate Serious

Changes to requirements that require major designrework are proposed.

Moderate Serious

The organisation is restructured so that differentmanagement are responsible for the project.

High Serious

Page 29: 8.project management chapter 8

Risk analysis

29

Risk Probability Effects

The database used in the system cannot process asmany transactions per second as expected.

Moderate Serious

The time required to develop the software isunderestimated.

High Serious

CASE tools cannot be integrated. High Tolerable

Customers fail to understand the im pact ofrequirements changes.

Moderate Tolerable

Required training for staff is not available. Moderate Tolerable

The rate of defect repair is underestim ated. Moderate Tolerable

The size of the software is underestimated. High Tolerable

The code generated by CASE tools is ineffi cient. Moderate Insignificant

Page 30: 8.project management chapter 8

Risk planningConsider each risk and develop a strategy to manage that

risk.1. Avoidance strategies◦ The probability that the risk will arise is reduced;

1. Minimisation strategies◦ The impact of the risk on the project or product will be

reduced;1. Contingency plans◦ If the risk arises, contingency plans are plans to deal

with that risk;

30

Page 31: 8.project management chapter 8

Risk management strategies

31

Risk Strategy

Organisationalfinancial problems

Prepare a briefing document for senior managementshowing how the project is making a very importantcontribution to the goals of the business.

Recruitmentproblems

Alert customer of potential difficulties and thepossibility of delays, investigate buying-incomponents.

Staff illness Reorganise team so that there is more overlap of workand people therefore understand each other’s jobs.

Defectivecomponents

Replace potentially defective components with bought-in components of known reliabilit y.

Page 32: 8.project management chapter 8

Risk management strategies

32

Risk Strategy

Requirementschanges

Derive traceabili ty information to assess requirementschange impact, maximise information hiding in thedesign.

Organisationalrestructuring

Prepare a briefing document for senior managementshowing how the project is making a very importantcontribution to the goals of the business.

Databaseperformance

Investigate the possibilit y of buying a higher-performance database.

Underestimateddevelopment time

Investigate buying in components, investigate use of aprogram generator

Page 33: 8.project management chapter 8

Risk monitoringAssess each identified risks regularly to decide whether

or not it is becoming less or more probable.Also assess whether the effects of the risk have changed.Each key risk should be discussed at management

progress meetings.

33

Page 34: 8.project management chapter 8

Risk indicators

34

Risk type Potential indicators

Technology Late delivery of hardware or support software, many reported technology problems

People Poor staff morale, poor relationships amongst team member, job availability

Organisational Organisational gossip, lack of action by senior management

Tools Reluctance by team members to use tools, complaints about CASE tools, demands for higher-powered workstations

Requirements Many requirements change requests, customer complaints

Estimation Failure to meet agreed schedule, failure to clear reported defects

Page 35: 8.project management chapter 8

Key points

Good project management is essential for project success.

The intangible nature of software causes problems for management.

Managers have diverse roles but their most significant activities are planning, estimating and scheduling.

Planning and estimating are iterative processes which continue throughout the course of a project.

35

Page 36: 8.project management chapter 8

Key points

A project milestone is a predictable state where a formal report of progress is presented to management.

Project scheduling involves preparing various graphical representations showing project activities, their durations and staffing.

Risk management is concerned with identifying risks which may affect the project and planning to ensure that these risks do not develop into major threats.

36

Page 37: 8.project management chapter 8

37

Software cost estimation

Page 38: 8.project management chapter 8

38

Software cost componentsHardware and software costs.Travel and training costs.Effort costs (the dominant factor in most

projects)◦ The salaries of engineers involved in the project;◦ Social and insurance costs.

Effort costs must take overheads into account◦ Costs of building, heating, lighting.◦ Costs of networking and communications.◦ Costs of shared facilities (e.g library, staff restaurant,

etc.).

Page 39: 8.project management chapter 8

39

Costing and pricingEstimates are made to discover the cost, to the

developer, of producing a software system.There is not a simple relationship between the

development cost and the price charged to the customer.Broader organisational, economic, political and business

considerations influence the price charged.

Page 40: 8.project management chapter 8

40

Software pricing factors

Page 41: 8.project management chapter 8

41

A measure of the rate at which individual engineers involved in software development produce software and associated documentation.

Not quality-oriented although quality assurance is a factor in productivity assessment.

Essentially, we want to measure useful functionality produced per time unit.

Software productivity

Page 42: 8.project management chapter 8

42

Size related measures based on some output from the software process. This may be lines of delivered source code, object code instructions, etc.

Function-related measures based on an estimate of the functionality of the delivered software. Function-

points are the best known of this type of measure.

Productivity measures

Page 43: 8.project management chapter 8

43

Estimating the size of the measure (e.g. how many function points).

Estimating the total number of programmer months that have elapsed.

Estimating contractor productivity (e.g. documentation team) and incorporating this estimate in overall estimate.

Measurement problems

Page 44: 8.project management chapter 8

44

Lines of code (LOC) is a software metric used to measure the size of a software program by counting the number of lines in the text of the program's source code.

LOC is typically used to predict the amount of effort that will be required to develop a program, as well as to estimate programming productivity or effort once the software is produced.

The measure was first proposed when programs were typed on cards with one line per card;

How does this correspond to statements as in Java which can span several lines or where there can be several statements on one line.

Lines of code

Page 45: 8.project management chapter 8

advantages:1. Scope for Automation of Counting: Since line of code

is a physical entity; manual counting effort can be easily eliminated by automating the counting process.

Small utilities may be developed for counting the LOC in a program. However, a code counting utility developed for a specific language cannot be used for other languages due to the syntactical and structural differences among languages.

2. An Intuitive Metric: line of code serves as an intuitive metric for measuring the size of software due to the fact that it can be seen and the effect of it can be visualizedThis way, LOC comes in handy to express the size of software among programmers with low levels of experience.

45

Page 46: 8.project management chapter 8

Disadvantages:1. Lack of Accountability: Lines of code measure suffers

from some fundamental problems. Some think it isn't useful to measure the productivity of a project using only results from the coding phase, which usually accounts for only 30% to 35% of the overall effort.

2. Lack of Cohesion with Functionality: Though experiments have repeatedly confirmed that effort is highly correlated with LOC, functionality is less well correlated with LOC. That is, skilled developers may be able to develop the same functionality with far less code, so one program with less LOC may exhibit more functionality than another similar program. In particular, LOC is a poor productivity measure of individuals, because a developer who develops only a few lines may still be more productive than a developer creating more lines of code.

46

Page 47: 8.project management chapter 8

Cont’d

3. Adverse Impact on Estimation: estimates based on lines of code can adversely go wrong, in all possibility.

4. Developer’s Experience: Implementation of a specific logic differs based on the level of experience of the developer.

Hence, number of lines of code differs from person to person. An experienced developer may implement certain functionality in fewer lines of code than another developer of relatively less experience does, though they use the same language.

47

Page 48: 8.project management chapter 8

48

The lower level the language, the more productive the programmer◦ The same functionality takes more code to implement in

a lower-level language than in a high-level language.The more verbose the programmer, the higher the

productivity◦ Measures of productivity based on lines of code suggest

that programmers who write verbose code are more productive than programmers who write compact code.

Productivity comparisons

Page 49: 8.project management chapter 8

49

System development times

Page 50: 8.project management chapter 8

Function pointsFunction point measures the functionality from the user

point of view, that is, on the basis of what the user request and receives in return. Therefore, it deals with the functionality being delivered, and not with the lines of code, source modules, files etc.

Measuring size in this way has the advantage that size measure is independent of the technology used to deliver the function.

50

Page 51: 8.project management chapter 8

Importance of function point (features)

This is independent of the languages tools, or methodology used for implementation.

They can be estimated from requirement specification or design specification.

They are directly linked to the statement of request.

51

Page 52: 8.project management chapter 8

52

Function pointsBased on a combination of program characteristics◦ external inputs and outputs;◦ user interactions;◦ external interfaces;◦ files used by the system.

A weight is associated with each of these and the function point count is computed by multiplying each raw count by the weight and summing all values.

Page 53: 8.project management chapter 8

53

Function pointsThe function point count is modified by complexity of the

project.FPs can be used to estimate LOC depending on the

average number of LOC per FP for a given language.◦ LOC = AVC * number of function points; ◦ AVC is a language-dependent factor varying from 200-

300 for assemble language to 2-40 for a 4GL;FPs are very subjective. They depend on the estimator◦ Automatic function-point counting is impossible.

Page 54: 8.project management chapter 8

54

Object pointsObject points (alternatively named application points)

are an alternative function-related measure to function points when 4Gls or similar languages are used for development.

Object points are NOT the same as object classes. The number of object points in a program is a weighted

estimate of:◦ The number of separate screens that are displayed;◦ The number of reports that are produced by the system;◦ The number of program modules that must be

developed to supplement the database code;

Page 55: 8.project management chapter 8

55

Object point estimationObject points are easier to estimate from a specification

than function points as they are simply concerned with screens, reports and programming language modules.

They can therefore be estimated at a fairly early point in the development process.

At this stage, it is very difficult to estimate the number of lines of code in a system.

Page 56: 8.project management chapter 8

56

Real-time embedded systems, 40-160 LOC/P-month.

Systems programs , 150-400 LOC/P-month.Commercial applications, 200-900

LOC/P-month.In object points, productivity has been measured

between 4 and 50 object points/month depending on tool support and developer capability.

Productivity estimates

Page 57: 8.project management chapter 8

57

Factors affecting productivity

Page 58: 8.project management chapter 8

58

All metrics based on volume/unit time are flawed because they do not take quality into account.

Productivity may generally be increased at the cost of quality.

It is not clear how productivity/quality metrics are related. If requirements are constantly changing then an approach

based on counting lines of code is not meaningful as the program itself is not static

Quality and productivity

Page 59: 8.project management chapter 8

59

Estimation techniquesThere is no simple way to make an accurate estimate of the

effort required to develop a software system◦ Initial estimates are based on inadequate information in a

user requirements definition;◦ The software may run on unfamiliar computers or use

new technology;◦ The people in the project may be unknown.

Project cost estimates may be self-fulfilling◦ The estimate defines the budget and the product is

adjusted to meet the budget.

Page 60: 8.project management chapter 8

60

Changing technologiesChanging technologies may mean that previous estimating

experience does not carry over to new systems.◦ Distributed object systems rather than mainframe

systems;◦ Use of web services;◦ Use of ERP or database-centred systems;◦ Use of off-the-shelf software;◦ Development for and with reuse;◦ Development using scripting languages;◦ The use of CASE tools and program generators.

Page 61: 8.project management chapter 8

61

Estimation techniques1. Expert judgement2. Estimation by analogy3. Algorithmic cost modelling4. Pricing to win5. Parkinson's law

Page 62: 8.project management chapter 8

62

Estimation techniques

Page 63: 8.project management chapter 8

Algorithmic cost modelling

A formulaic approach based on historical cost information and which is generally based on the size of the software.

Page 64: 8.project management chapter 8

Expert judgementOne or more experts in both software

development and the application domain use their experience to predict software costs. Process iterates until some consensus is reached.

Advantages: Relatively cheap estimation method. Can be accurate if experts have direct experience of similar systems

Disadvantages: Very inaccurate if there are no experts!

Page 65: 8.project management chapter 8

Estimation by analogyThe cost of a project is computed by comparing the

project to a similar project in the same application domain

Advantages: Accurate if project data availableDisadvantages:Impossible if no comparable

project has been tackled. Needs systematically maintained cost database

Page 66: 8.project management chapter 8

Parkinson's LawThe project costs whatever resources are

availableAdvantages: No overspendDisadvantages: System is usually unfinished

Page 67: 8.project management chapter 8

Pricing to winThe project costs whatever the customer has to spend on

itAdvantages: You get the contractDisadvantages: The probability that the

customer gets the system he or she wants is small. Costs do not accurately reflect the work required

Page 68: 8.project management chapter 8

68

Top-down and bottom-up estimationAny of these approaches may be used top-down or

bottom-up.Top-down◦ Start at the system level and assess the overall system

functionality and how this is delivered through sub-systems.

Bottom-up◦ Start at the component level and estimate the effort

required for each component. Add these efforts to reach a final estimate.

Page 69: 8.project management chapter 8

69

Top-down estimationUsable without knowledge of the system architecture and

the components that might be part of the system.Takes into account costs such as integration,

configuration management and documentation.Can underestimate the cost of solving difficult low-level

technical problems.

Page 70: 8.project management chapter 8

70

Bottom-up estimationUsable when the architecture of the system is

known and components identified.This can be an accurate method if the system has

been designed in detail.It may underestimate the costs of system level

activities such as integration and documentation.

Page 71: 8.project management chapter 8

71

Algorithmic cost modelling Cost is estimated as a mathematical function of

product, project and process attributes whose values are estimated by project managers:◦ Effort = A × Size B × M

◦ A is an organisation-dependent constant, B reflects the disproportionate effort for large projects and M is a multiplier reflecting product, process and people attributes.

The most commonly used product attribute for cost estimation is code size.

Most models are similar but they use different values for A, B and M.

Page 72: 8.project management chapter 8

72

Estimate uncertainty

x

2 x

4x

0.5x

0.25x

Feasibility Requirements Design Code Delivery

Page 73: 8.project management chapter 8

73

The COCOMO modelCOCOMO model stands for Constructive Cost Model.An empirical model based on project experience.Well-documented, ‘independent’ model which is not tied

to a specific software vendor.Long history from initial version published in 1981

(COCOMO-81) through various instantiations to COCOMO 2.

COCOMO 2 takes into account different approaches to software development, reuse, etc.

Page 74: 8.project management chapter 8

74

COCOMO 81

Page 75: 8.project management chapter 8

75

COCOMO 2 COCOMO 81 was developed with the assumption that a waterfall

process would be used and that all software would be developed from scratch.

Since its formulation, there have been many changes in software engineering practice and COCOMO 2 is designed to accommodate different approaches to software development.

Page 76: 8.project management chapter 8

76

COCOMO 2 models COCOMO 2 incorporates a range of sub-models that produce

increasingly detailed software estimates. The sub-models in COCOMO 2 are:◦ Application composition model. Used when software is

composed from existing parts.◦ Early design model. Used when requirements are available but

design has not yet started.◦ Reuse model. Used to compute the effort of integrating reusable

components.◦ Post-architecture model. Used once the system architecture has

been designed and more information about the system is available.

Page 77: 8.project management chapter 8

77

Use of COCOMO 2 models

Number ofapplication points

Number of functionpoints

Based on Used for

Used for

Used for

Used for

Based on

Based on

Based on

Number of lines ofcode reused or

generated

Number of lines ofsource code

Applicationcomposition model

Early design model

Reuse model

Post-architecturemodel

Prototype sy stemsdeveloped using

scripting, DBprog ramming etc.

Initial effortestimation based onsystem requirementsand design options

Effort to integ ratereusable components

or automaticallygenerated code

Development effor tbased on system

design specification

Page 78: 8.project management chapter 8

Types of COCOMO Models This model gives 3 levels of estimations namely basic, intermediate

and detail.

1.Basic COCOMO model It gives an order of magnitude of cost. This model uses estimated size of software project and the type of software being developed.

The estimation varies for various types of projects and these various kinds are:-

• Organic-mode project:- These project include relatively small teams working in a familiar environment, developing a well understood application, the feature of such project are-

78

Page 79: 8.project management chapter 8

Cont’ed

1) The communication overheads are low.

2) The team members know what they can achieve.3) This project is much common in nature.

• Semi-detached model: A project consists of mixed project team of experienced and fresh engineers. The team has limited experience of related system development and some of them are unfamiliar with output and also some aspects of system being developed.

• Embedded model:- There will be very strong coupled hardware, software regulations and operational procedures. Validation costs are very high. For e.g. System program and development of OCR for English.

79

Page 80: 8.project management chapter 8

2. Intermediate COCOMO modelThe intermediate COCOMO model estimates the software

development effort by using 15 cost drivers’ variables besides the size variable used in basic COCOMO.

Intermediate COCOMO computes software development effort as function of program size and a set of "cost drivers" that include subjective assessment of product, hardware, personnel and project attributes. This extension considers a set of four "cost drivers", each with a number of subsidiary attributes:

• Product attributeso Required software reliabilityo Size of application databaseo Complexity of the product

80

Page 81: 8.project management chapter 8

Cont’ed

Hardware attributeso Run-time performance constraintso Memory constraintso Volatility of the virtual machine environmento Required turnabout timePersonnel attributeso Analyst capabilityo Software engineering capabilityo Applications experienceo Virtual machine experienceo Programming language experienceProject attributes o Use of software tools o Application of software engineering methods o Required development schedule 81

Page 82: 8.project management chapter 8

3.Detailed COCOMO modelDetailed COCOMO - incorporates all characteristics of the

intermediate version with an assessment of the cost driver's impact on each step (analysis, design, etc.) of the software engineering process.

The detailed COCOMO model can estimate the staffing cost and duration of each of the development phases, subsystem, and modules. It allows you to experiment with different development strategies, to find the plan that best suits your needs and resources.

82

Page 83: 8.project management chapter 8

development phases of the detailed COCOMO model

1. plan/requirements: this is the first phase of the development cycle. The requirement is analyzed, the product plan is set up and a full product specification is generated. This phase consumes from 6% to 8% of the effort and 10% to 40% of the development time.

2. product design: The second phase of the COCOMO development cycle is concerned with the determination of the product architecture and the specification of the subsystems. This requires 16% to 18% of the normal effort and 19% to 38% of the development time.

83

Page 84: 8.project management chapter 8

Cont’dCont’d

3. programming: This is the third phase and is divided into sub phases : detailed phase and code/unit phase. This requires 48% to 68% of the effort and 24% to 64% of the development time.

4. integration/test : This phase of COCOMO occurs before delivery. This mainly consists of putting the tested parts together and then testing the final product. This requires 16% to 34% of normal effort and 18% to 34% of the development time.

84

Page 85: 8.project management chapter 8

85

Application composition modelSupports prototyping projects and projects where

there is extensive reuse.Based on standard estimates of developer

productivity in application (object) points/month.Takes CASE tool use into account.Formula is◦ PM = ( NAP × (1 - %reuse/100 ) ) / PROD

◦ PM is the effort in person-months, NAP is the number of application points and PROD is the productivity.

Page 86: 8.project management chapter 8

86

Object point productivity

Page 87: 8.project management chapter 8

87

Early design modelEstimates can be made after the requirements

have been agreed.Based on a standard formula for algorithmic

models◦ PM = A × SizeB × M where

◦ M = PERS × RCPX × RUSE × PDIF × PREX × FCIL × SCED;◦ A = 2.94 in initial calibration, Size in KLOC, B varies

from 1.1 to 1.24 depending on novelty of the project, development flexibility, risk management approaches and the process maturity.

Page 88: 8.project management chapter 8

88

MultipliersMultipliers reflect the capability of the developers, the non-

functional requirements, the familiarity with the development platform, etc.◦ RCPX - product reliability and complexity;◦ RUSE - the reuse required;◦ PDIF - platform difficulty;◦ PREX - personnel experience;◦ PERS - personnel capability;◦ SCED - required schedule;◦ FCIL - the team support facilities.

Page 89: 8.project management chapter 8

89

The reuse modelTakes into account black-box code that is reused without

change and code that has to be adapted to integrate it with new code.

There are two versions:◦ Black-box reuse where code is not modified. An effort

estimate (PM) is computed.◦ White-box reuse where code is modified. A size

estimate equivalent to the number of lines of new source code is computed. This then adjusts the size estimate for new code.

Page 90: 8.project management chapter 8

90

Reuse model estimates 1For generated code:◦ PM = (ASLOC * AT/100)/ATPROD◦ ASLOC is the number of lines of generated code◦ AT is the percentage of code automatically generated.◦ ATPROD is the productivity of engineers in integrating

this code.

Page 91: 8.project management chapter 8

91

Reuse model estimates 2When code has to be understood and integrated:◦ ESLOC = ASLOC * (1-AT/100) * AAM.◦ ASLOC and AT as before.◦ AAM is the adaptation adjustment multiplier computed

from the costs of changing the reused code, the costs of understanding how to integrate the code and the costs of reuse decision making.

Page 92: 8.project management chapter 8

92

Project duration and staffingAs well as effort estimation, managers must

estimate the calendar time required to complete a project and when staff will be required.

Calendar time can be estimated using a COCOMO 2 formula◦ TDEV = 3 × (PM)(0.33+0.2*(B-1.01))

◦ PM is the effort computation and B is the exponent computed as discussed above (B is 1 for the early prototyping model). This computation predicts the nominal schedule for the project.

The time required is independent of the number of people working on the project.

Page 93: 8.project management chapter 8

93

Key points

There is not a simple relationship between the price charged for a system and its development costs.

Factors affecting productivity include: domain experience, process quality, the project size, technology support and the working environment.

Software may be priced to gain a contract and the

functionality adjusted to the price.

Page 94: 8.project management chapter 8

94

Key points

Different techniques of cost estimation should be used when estimating costs.

The COCOMO model takes project, product, personnel and hardware attributes into account when predicting effort required.

Algorithmic cost models support quantitative option analysis as they allow the costs of different options to be compared.

The time to complete a project is not proportional to the number of people working on the project.