1. 2015HervBaron HERVE BARON Introduction to Oil & Gas
facilities Design Welcome!
2. 2015HervBaron HERVE BARON Introduction to Oil & Gas
facilities Design This presentation comes with sound! Please
download the PowerPoint file to get it.
3. 2015HervBaron HERVE BARON Training objectives & scope To
get familiar with how Oil & Gas facilities Projects are
developed To get familiar with how Oil & Gas facilities design
is conducted To get familiar with the work of each Engineering
discipline
4. 2015HervBaron HERVE BARON Project development phases
Engineering: Organisation, Documents Plant design overview The
engineering disciplines o PROCESS o PLANT LAYOUT o EQUIPMENT o
SAFETY & ENVIRONMENT o CIVIL o PIPING o PIPELINE o
INSTRUMENTATION o ELECTRICAL Training Agenda
5. 2015HervBaron HERVE BARON Project development phases
Engineering: Organisation, Documents Plant design overview The
engineering disciplines o PROCESS o PLANT LAYOUT o EQUIPMENT o
SAFETY & ENVIRONMENT o CIVIL o PIPING o PIPELINE o
INSTRUMENTATION o ELECTRICAL Training Agenda
6. 2015HervBaron HERVE BARON Project development phases
Pre-Project/Conceptual Objective: Define the business opportunity,
select technology, estimate cost Content: technical assessment,
develop process design, milestone schedule, cost estimate
Deliverables: Functional requirements, Process design, +/-30% cost
estimate, milestone schedule By: Company Step 1
7. 2015HervBaron HERVE BARON Project development phases
Pre-Project/Conceptual Objective: Define the business opportunity,
select technology, estimate cost Content: technical assessment,
develop process design, milestone schedule, cost estimate
Deliverables: Functional requirements, Process design, +/-30% cost
estimate, milestone schedule By: Company gateStep 1
8. 2015HervBaron HERVE BARON Project development phases
Pre-Project/Conceptual Objective: Define the business opportunity,
select technology, estimate cost Content: technical assessment,
develop process design, milestone schedule, cost estimate
Deliverables: Functional requirements, Process design, +/-30% cost
estimate, milestone schedule By: Company Front End Engineering
Design (FEED) Objective: refine cost estimate, prepare EPC phase
Content: Develop Plant design (P&IDs, layout etc.)
Deliverables: +/-10% cost estimate, Technical exhibits of EPC
Contract, Project schedule By: Contractor gateStep 1 Step 2
9. 2015HervBaron HERVE BARON Project development phases
Pre-Project/Conceptual Objective: Define the business opportunity,
select technology, estimate cost Content: technical assessment,
develop process design, milestone schedule, cost estimate
Deliverables: Functional requirements, Process design, +/-30% cost
estimate, milestone schedule By: Company Front End Engineering
Design (FEED) Objective: refine cost estimate, prepare EPC phase
Content: Develop Plant design (P&IDs, layout etc.)
Deliverables: +/-10% cost estimate, Technical exhibits of EPC
Contract, Project schedule By: Contractor gate gateStep 1 Step
2
10. 2015HervBaron HERVE BARON Project development phases
Pre-Project/Conceptual Objective: Define the business opportunity,
select technology, estimate cost Content: technical assessment,
develop process design, milestone schedule, cost estimate
Deliverables: Functional requirements, Process design, +/-30% cost
estimate, milestone schedule By: Company Front End Engineering
Design (FEED) Objective: refine cost estimate, prepare EPC phase
Content: Develop Plant design (P&IDs, layout etc.)
Deliverables: +/-10% cost estimate, Technical exhibits of EPC
Contract, Project schedule By: Contractor gate gate Project
Execution (EPC) Objective: Delivery of the Plant ready for Start-Up
Content: Detail Engineering, Procurement, Construction
Deliverables: Mechnically completed Plant, ready for Start- Up By:
Contractor Step 1 Step 2 Step 3
11. 2015HervBaron HERVE BARON Project development phases
Pre-Project/Conceptual Objective: Define the business opportunity,
select technology, estimate cost Content: technical assessment,
develop process design, milestone schedule, cost estimate
Deliverables: Functional requirements, Process design, +/-30% cost
estimate, milestone schedule By: Company Front End Engineering
Design (FEED) Objective: refine cost estimate, prepare EPC phase
Content: Develop Plant design (P&IDs, layout etc.)
Deliverables: +/-10% cost estimate, Technical exhibits of EPC
Contract, Project schedule By: Contractor gate gate Project
Execution (EPC) Objective: Delivery of the Plant ready for Start-Up
Content: Detail Engineering, Procurement, Construction
Deliverables: Mechnically completed Plant, ready for Start- Up By:
Contractor Step 1 Step 2 Step 3
13. 2015HervBaron HERVE BARON Project development phases
Engineering: Organisation, Documents Plant design overview The
engineering disciplines Training Agenda
14. 2015HervBaron HERVE BARON
15. 2015HervBaron HERVE BARON
16. 2015HervBaron HERVE BARON Engineering Process Safety
Equipment / Mechanical Plant Layout Piping Civil Instrumentation
and Control Electrical Engineering organisation
17. 2015HervBaron HERVE BARON Project development phases: the
role of Engineering Engineering: Organisation, Documents Plant
design overview The engineering disciplines Training Agenda
18. 2015HervBaron HERVE BARON Engineering document register
Document number Document title Document revision A 1 48104 Service
building instrument. rooms cables routing B A 2 48102 Trouble
shooting diagrams D A 3 48134 F&G system architecture drawing E
A 4 50100 Instrument index B A 7 50003 Spec for instrument
installation works and service C A 8 50960 Instrument Data sheets
for temperature switches B A 9 50110 Requisition for pressure
relief valves B M 1 62059 General plot plan B M 2 62020 Piping
details standard C M 2 62070 Piping general arrangement Area 1 D M
4 60100 Special items list D M 5 62250 Piping isometrics booklet C
M 6 60000 Pipes and fittings thickness calculation A M 6 62351
Calculation note CN1 - piping stress analysis A M 7 60001 General
piping specification C M 8 60103 Data sheets for station piping
material B M 9 60200 Requisition for pipes F
19. 2015HervBaron HERVE BARON Engineering document codification
Discipline code A Instrumentation & Control C Civil engineering
E Electrical G Project general documents J Mechanical K Safety M
Piping & Layout P Processes S Steel Structures V Vessels Heat
exchangers W Materials Welding Document type 1 Installation
drawings 2 Detail drawings 3 Diagrams 4 Lists Bill of Quantities 5
Isometrics 6 Calculation notes 7 Specifications 8 Data sheets 9
Requisitions Serial number Document number Document title Document
revision A 1 48104 Service building instrument. rooms cables
routing B A 2 48102 Trouble shooting diagrams D A 3 48134 F&G
system architecture drawing E A 4 50100 Instrument index B A 7
50003 Spec for instrument installation works and service C A 8
50960 Instrument Data sheets for temperature switches B A 9 50110
Requisition for pressure relief valves B M 1 62059 General plot
plan B M 2 62020 Piping details standard C M 2 62070 Piping general
arrangement Area 1 D M 4 60100 Special items list D M 5 62250
Piping isometrics booklet C M 6 60000 Pipes and fittings thickness
calculation A M 6 62351 Calculation note CN1 - piping stress
analysis A M 7 60001 General piping specification C M 8 60103 Data
sheets for station piping material B M 9 60200 Requisition for
pipes F Revision index
20. 2015HervBaron HERVE BARON The common engineering
deliverables
21. 2015HervBaron HERVE BARON Project development phases: the
role of Engineering Engineering: Organisation, Documents Plant
design overview The engineering disciplines Training Agenda
22. 2015HervBaron HERVE BARON Plant Design Business case
23. 2015HervBaron HERVE BARON Plant Design PFD, HMB Process
Simulations Business case
24. 2015HervBaron HERVE BARON Process Design, PFD, HMB
25. 2015HervBaron HERVE BARON Plant Design PFD, HMB Process
Equipment sizing / specification Process Simulations Business
case
26. 2015HervBaron HERVE BARON Process Equipment sizing &
Data Sheet
27. 2015HervBaron HERVE BARON Process Equipment sizing &
Data Sheet
28. 2015HervBaron HERVE BARON Plant Design PFD, HMB Process
Equipment sizing / specification Process Simulations Business case
Equipment design by vendors
29. 2015HervBaron HERVE BARON Plant Design PFD, HMB Process
Equipment sizing / specification Process Simulations Business case
Equipment design by vendors Fluids composition & conditions
Material selection and specifications
30. 2015HervBaron HERVE BARON Plant Design PFD, HMB Process
Equipment sizing / specification Process Simulations Business case
Equipment design by vendors Fluids composition & conditions
Material selection and specifications Plant Layout
31. 2015HervBaron HERVE BARON Plant Design
32. 2015HervBaron HERVE BARON Plant Design PFD, HMB Process
Equipment sizing / specification Process Simulations Business case
Equipment design by vendors Fluids composition & conditions
Material selection and specifications Plant Layout Utility
consumption Utility Units Design
33. 2015HervBaron HERVE BARON Plant Design PFD, HMB Process
Equipment sizing / specification Process Simulations Business case
Equipment design by vendors Fluids composition & conditions
Material selection and specifications Plant Layout Utility
consumption Utility Units Design Electrical power generation &
distribution
37. 2015HervBaron HERVE BARON Plant Design PFD, HMB Process
Equipment sizing / specification Process Simulations Business case
Equipment design by vendors Fluids composition & conditions
Material selection and specifications Plant Layout Utility
consumption Utility Units Design Civil design Electrical power
generation & distribution
38. 2015HervBaron HERVE BARON Civil Foundation Drawings
39. 2015HervBaron HERVE BARON Plant Design PFD, HMB Process
Equipment sizing / specification Process Simulations Business case
Equipment design by vendors Fluids composition & conditions
Material selection and specifications Plant Layout Utility
consumption Utility Units Design Civil design Electrical power
generation & distribution
40. 2015HervBaron HERVE BARON Plant Design PFD, HMB Process
Equipment sizing / specification Process Simulations Business case
Equipment design by vendors Fluids composition & conditions
Material selection and specifications Plant Layout Utility
consumption Utility Units Design Civil design P&IDs Electrical
power generation & distribution
41. 2015HervBaron HERVE BARON P&ID Compare the information
shown on the PFD and the P&ID
42. 2015HervBaron HERVE BARON Plant Design PFD, HMB Process
Equipment sizing / specification Process Simulations Business case
Equipment design by vendors Fluids composition & conditions
Material selection and specifications Plant Layout Utility
consumption Utility Units Design Civil design P&IDs Piping
Routing Electrical power generation & distribution
44. 2015HervBaron HERVE BARON Plant Design PFD, HMB Process
Equipment sizing / specification Process Simulations Business case
Equipment design by vendors Fluids composition & conditions
Material selection and specifications Plant Layout Utility
consumption Utility Units Design Civil design P&IDs Piping
Routing Instrumentation & Control design
49. 2015HervBaron HERVE BARON Plant Design PFD, HMB Process
Equipment sizing / specification Process Simulations Business case
Equipment design by vendors Fluids composition & conditions
Material selection and specifications Plant Layout Utility
consumption Utility Units Design Civil design P&IDs Piping
Routing Structural steel design Instrumentation & Control
design
50. 2015HervBaron HERVE BARON Project development phases
Engineering: Organisation, Documents Plant design overview The
engineering disciplines o PROCESS o PLANT LAYOUT o EQUIPMENT o
SAFETY & ENVIRONMENT o CIVIL o PIPING o PIPELINE o
INSTRUMENTATION o ELECTRICAL Training Agenda