Upload
gayan-mapitiya
View
1.363
Download
3
Embed Size (px)
Citation preview
COM 4310 1
Capital Investment Decisions
(Project Appraisal)
Capital investment decisions are those decisions that
involve current outlays (costs) in return for a stream of
benefits in future years.
The distinguishing feature between short-term
decisions and capital investment (long-term) decisions
is time.4/29/2011
COM 4310 2
Appraisal methods
• NPV
• IRR
• Payback / Discounted payback
• ARR
4/29/2011
COM 4310 3
Appraisal methods
The concept of Net Present Value (NPV)
• By using discounted cash flow techniques we can calculate Net Present Value.
• Present value is the today’s value (year 0) of any future cash flow after discounting it by an appropriate discount rate.
• The process of converting cash to be received in the future into a value at the present time by the use of an interest rate is called as discounting.
4/29/2011
COM 4310 4
Present value = FV
(1 + K)^
• Compounding is the opposite of discounting, since it is the future value of present cash flows.
Future Value = PV (1 + K)^
4/29/2011
COM 4310 5
• Calculation of Net Present Value,– Example:
The Master company is evaluating a project with an expected life of three (3) years and investment outlay of Rs. 10 million. The estimated net cash inflows are as follows.
– Year 1 3 million– Year 2 6 million– Year 3 4 million
The opportunity cost of capital is 10%. You are required to calculate the net present value of the project.
4/29/2011
COM 4310 6
The Internal Rate of Return (IRR)
This is the discount rate that will cause the net
present value of an investment to be zero.
That is, IRR is the Effective Interest Rate (EIR) of the
project.
IRR is also known as Discounted Rate of Return.
IRR is the “maximum cost of capital” that can be
allowed to finance a project. If your cost of capital is
greater than IRR , then you are incurring losses.
4/29/2011
COM 4310 7
The IRR can be found by trial and error by using a number
of discount factors until the NPV equals zero.
However, we can use Interpolation method to calculate IRR.
This method gives an approximation of the IRR.
IRR = LR + LR NPV x (HR – LR)
LR NPV – HR NPV
4/29/2011
COM 4310 8
• Calculate the IRR of the previous example…
• IRR has a technical shortcoming. That is, when cash flows of the project are unconventional multiple IRRs are possible for a project. But, only one IRR is economically significant in determining whether or not the investment is possible.
• Therefore, when unconventional cash flows involve, NPV method is more appropriate to decide whether project is accepted or not.
4/29/2011
COM 4310 9
Timing of cash flows To simplify the presentation, our calculations have been based on the assumption that any cash flows in future years will occur in one lump sum at the year end.
Both NPV and IRR methods take into account the time value of money.
Techniques that ignore the time value of money
Payback Method
Accounting rate of return (ARR)
4/29/2011
COM 4310 10
Payback Method
• The payback method is defined as the length of
time that is required for a stream of cash inflows
from an investment to recover the original cash
outlay of the investment.
• Payback period is a simple method but could result
in selecting a wrong project since it does not
consider time value of money.
4/29/2011
COM 4310 11
• However, to minimize the problems with payback
period, it can be adjusted to show the time value
of money and discounted payback method is
used.
• Calculate the payback period and
discounted payback period for previous
example.
4/29/2011
COM 4310 12
Accounting rate of return (ARR)
The Accounting rate of return (ARR) , also known as the
return on investment and return on capital employed .
This method differs from other methods in that profits
rather than cash flows are used.
ARR = average annual profits x 100
average investments
However, ARR method ignores the time value of money.
4/29/2011
COM 4310 13
Example ….
A project has an initial outlay of Rs. 20 million. It is assumed that project will have an scrap value of Rs.5 million. Average annual profit expected from the project is Rs. 3 million.
ARR = average annual profits x 100
average investments
3 X 100
(20+5)/2
24%
4/29/2011
COM 4310 14
Decision criteria• Accept the project if NPV is positive.
• Accept the project if Discount rate < IRR
• Accept the project if payback is comparatively
shorter.
• Accept the project if ARR > expected rate of
return
4/29/2011
COM 4310 15
Mutually exclusive projects
Mutually exclusive projects exist where the acceptance
of one project excludes the acceptance of another
project .
It is recommended to use NPV method to rank
mutually exclusive projects.
4/29/2011
COM 4310 16
Qualitative factors
Not all investment projects can be described
completely in terms of monetary costs and benefits.
Therefore, even if some costs and benefits cannot be
quantified they should be considered in investment
decisions.
4/29/2011
COM 4310 17
Capital rationing
Situations may occur where there are
insufficient funds available to a firm to
undertake all those projects that yield a
positive net present value. This situation is
described as capital rationing.
4/29/2011
COM 4310 18
The term “soft capital rationing” is often used to
refer to situations where, for various reasons the
firm internally imposes a budget ceiling on the
amount of capital expenditure.
Where the amount of capital investment is
restricted because of external constraints such as
the inability to obtain funds from the financial
markets, the term “hard capital rationing” is used.
4/29/2011
COM 4310 19
Whenever capital rationing exists,
management should allocate the limited
available capital in a way that maximizes
the NPVs of the firm.
For ranking projects “profitability index”
is used.
4/29/2011
COM 4310 20
Profitability index = PV of cash inflows
investment
4/29/2011
COM 4310 21
Example………Sade company operates under the constraint of capital
rationing has identified four (4) independent investments from which to choose. The company has Rs. 10 million available for capital investment during the current period. Which projects should the company choose?
Projects Investment requiredRs. Mn
Present value of InflowsRs. Mn
Net Present value
Profitability Index (PI)
Ranking as per PI
P 5 5.6 0.6 1.12 3Q 3 3.5 0.5 1.17 2R 6 6.2 0.2 1.03 4S 2 2.4 0.4 1.20 1
4/29/2011
COM 4310 22
Weighted average cost of capital (WACC)
Most companies are likely to be financed by a
combination of debt and equity capital. The overall
cost of capital is also called as weighted average
cost of capital.
WACC = (% of Debt capital x cost of debt) + (% of Equity capital x cost of
equity)
4/29/2011
COM 4310 23
Example…..
Assume that after tax cost of debt capital is 8% and the required rate of return on equity capital is 12% and the company intends to maintain a capital structure of 40% debt and 60% equity. The overall cost of capital for the company is calculated as ,
(8% x 40%) + (12% x 60%) = 10.4%
Can we use the WACC as the discount rate to calculate a project’s NPV ?
Yes , provided that the project is of equivalent risk to the firm’s existing assets and firm intends to maintain its target capital structure.
4/29/2011