56
Management & Entrepreneurship (Course Code:10AL51) Department of IEM JSS Academy of Technical Education, Bengaluru-560060

Unit viii preparation of project report

Embed Size (px)

Citation preview

Page 1: Unit viii preparation of project report

Management & Entrepreneurship

(Course Code:10AL51)

Department of IEM

JSS Academy of Technical Education, Bengaluru-560060

Page 2: Unit viii preparation of project report

Project Management

CHAPTER 5: Preparation of Project

Page 3: Unit viii preparation of project report

• Introduction – Meaning, Identification, Selection.

• Project Report – Need, Significance, Contents and Formulation.

• Guidelines by planning commission for Report.

• Errors of Project Reports; Project Appraisal.

• Identification of Business Opportunities.

• Feasibility Study – Market, Technical, Financial and Social.

Course outline

Page 4: Unit viii preparation of project report

Introduction

Page 5: Unit viii preparation of project report

Introduction – Meaning of a project

‘Specifically Evolved Work Plan’ devised to achieve specific objective within

a specified period of time.

It is a scheme, design, a proposal of something intended to achieve.

Each project differs in size, nature, objective & complexity.

Page 6: Unit viii preparation of project report

A project is a sequence of unique, complex and connected activities

having one goal or purpose and that must be completed by a specific

time, within budget, and according to specifications.

“Projects are the Building Blocks of an Investment Plan”

Introduction – Meaning of a project

Page 7: Unit viii preparation of project report

Attributes / Characteristics

Page 8: Unit viii preparation of project report

Attributes/Characteristics

• Complex Activities Not simple / Repetitive acts

• Connected Activities Some order/sequence in which the activities are executed

• One Goal Projects must have a single goal as compared to a program

• Specified Time Projects have a specified completion date

• Within Budget Projects also have resource limits (people, money, machines)

Page 9: Unit viii preparation of project report

Attributes/Characteristics

• According to Specification

• The customer or recipient of the deliverables from the project expects a

certain level of functionality and quality from the project.

Page 10: Unit viii preparation of project report

Project Program

Project includes all activities to complete a given job.

A program is defined as an ongoing process or ongoing operation indefinitely.

It has narrow scope and has shorter duration

It has broader scope and has longer duration

Project is a part of Program Main activity

Projects is individual activity.A program is a group of projects managed in a coordinated way to obtain benefits.

Project vs Program

Page 11: Unit viii preparation of project report

Project Parameters

Some common constraints that influence a project are:

1. Scope

2. Quality

3. Cost

4. Time

5. Resources

Project Parameters

The scope and quality of a project are influenced by a variety of constraints

like time, cost and availability of resources.

Page 12: Unit viii preparation of project report

Project Classification

Page 13: Unit viii preparation of project report

Quantifiable & Non-Quantifiable Projects

Sectoral Projects

Techno-Economic projects

Classification of Projects

Page 14: Unit viii preparation of project report

Quantifiable & Non-Quantifiable Projects

Classification of Projects

Projects for which a right quantitative assessment of benefits can be made are

termed as quantifiable projects

Ex: power generation, mineral, development, industrial development etc.,

Projects for which quantitative assessment cannot be made are termed as

non-quantifiable projects

Ex: health, education, Defence etc.,

Page 15: Unit viii preparation of project report

Sectoral Projects

Classification of Projects

Automobile sector

Agricultural sectoral

Power sector

Health sector

Education sector

Transport sector

Manufacturing sector

Food processing sector

Mining sector

Irrigation sector

Page 16: Unit viii preparation of project report

Techno Economic Projects

Classification of Projects

Factor intensity-oriented Classification

• Large Capital Investment, Labor intensive

Causation classification

• Demand/Raw material based

Magnitude-oriented classification

• Size based, Large, Medium, Small

Page 17: Unit viii preparation of project report

Project Identification

Page 18: Unit viii preparation of project report

Project selection process consist of Two main Steps:

Project Identification Project Selection

Project Identification - Idea generation

Selection process starts with the generation of a product idea.

In order to select the most promising project, the entrepreneur needs to

generate a few ideas about the possible projects he/she can undertake.

Project identification is concerned with collection of economic data and

analyzing it.

Project Identification / Selection

Page 19: Unit viii preparation of project report

Project Ideas - Ways or Sources: various internal and external sources

Knowledge of potential customer needs.

Watching emerging trends in demands for certain products.

Scope for producing substitute / alternative product.

Going though certain professional magazines.

Success stories of known entrepreneur or friend or relatives.

Making visit to trade fairs and exhibitions displaying new products and services.

Meeting with government Agencies.

Idea given by the knowledgeable person.

A new product introduced by the competitor.

Opportunity Scanning & Identification

Page 20: Unit viii preparation of project report

Project Selection

Page 21: Unit viii preparation of project report

Project selection starts from where project identification ends.

A tool generally used for this purpose is: SWOT/C analysis.

The intending entrepreneur analysis his /her strength and weakness,

opportunities /competitive advantages and threats / challenges offered by each

of the project ideas.

Finally project selected to converted into enterprise.

The process involved in selecting a project out of some projects - zeroing in

process.

Project Selection

Page 22: Unit viii preparation of project report

Project Selection Parameters

Technology

Equipment

Investment size

Location

Marketing

Page 23: Unit viii preparation of project report

Project Report

Page 24: Unit viii preparation of project report

Project Report

A project report or a business plan is a written statement of what an

entrepreneur proposes to take up.

Well evolved course of action devised to achieve the specified objectives

within a specified period of time.

Operating document / Roadmap / Guidelines.

Page 25: Unit viii preparation of project report

Contents of Project Report

• General information

• Promoter

• Location

• Land and building

• Plant and machinery

• Production process

• Utilities

• Transport and communication

• Raw material

• Man power

• Products

• Market

• Requirement of working capital

• Requirement of funds

• Cost of production and profitability of first ten years.

• Break-even analysis.

• Schedule of implementation.

Page 26: Unit viii preparation of project report

Formulation of Project Report

Page 27: Unit viii preparation of project report

Formulation of Project Report

General Information

• Biodata of promoter, Industry profile, constitution, organization and product details.

Project Description

• Site/location, infrastructure, raw materials, skilled labours, Utilities, pollution control, communication and transportation, Production process, machineries and equipment, capacity of plant, technology and R&D.

Market Potential • Demand and supply, Marketing strategy, after sales service

Page 28: Unit viii preparation of project report

• Capital Cost and source of Finance

• Assessment of Working Capital

Economic and social Variables

• Employment generation, Exports, local resource utilization, development area.

Formulation of Project Report

Project Implementation • PERT and CPM

Page 29: Unit viii preparation of project report

PLANNING COMMISSION GUIDELINES

Page 30: Unit viii preparation of project report

Planning Commission Guidelines

In order to process investment proposals and arrive at investment decisions, the planning Commission has issued guidelines for preparing/formulating industrial projects.

1. General Information

Feasibility report should include an analysis of the industry to which the project belongs / past

performance / description of industry / role of Public sector / Allocation of investment funds.

Page 31: Unit viii preparation of project report

Planning Commission Guidelines

2. Preliminary analysis of alternatives

• This should contain present data on the gap between demand and supply for the outputs

which are to be produced.

• Data on the capacity that would be available from projects that are in production or under

implementation at the time the report is prepared.

• A complete list of all existing plants in the industry, giving their capacity and their level of

production actually attained.

• A list of all projects for which letters of intent licenses have been issued and a list of proposed

projects.

Page 32: Unit viii preparation of project report

Planning Commission Guidelines

3. Project Description

• The feasibility report should mention the technology/process chosen for the project.

• Information relevant to determining the optimality of the location chosen.

• To assist in the environmental effects of a project, every feasibility report must present the

information on specific points, i.e. population, water, land, air, flora, & fauna, effects arising

out of projects pollution, other environmental disruption etc.

Page 33: Unit viii preparation of project report

Planning Commission Guidelines

4. Marketing Plan

                    It should contain the following items;

• Data on the marketing plan

• Demand & prospective supply in each of the areas to be served.

• Methods & the data used for main estimates of domestic supply.

• Selection of the market areas.

• Estimates of the degree of price sensitivity.

• It should contain an analysis of past trends in prices.

Page 34: Unit viii preparation of project report

Planning Commission Guidelines

5. Capital Requirements & Costs

The estimates should be reasonably complete & properly estimated.

Information on all items of costs should be carefully collected & presented.

6. Operating Requirements & Costs

• Operating costs - incurred after the commencement of commercial production.

• Information about all items of operating costs should be collected.

• Operating costs relate to the costs of raw materials & intermediaries, fuel, utilities, labour,

repair & maintenance, selling expenses & other expenses.

Page 35: Unit viii preparation of project report

Planning Commission Guidelines

7. Financial Analysis

• This strategy is to present some measures to assess the financial viability of the project.

• Foreign Exchange Requirements should be cleared by the Department of Economic Affairs.

• The feasibility report should take into account income tax rebates for priority industries,

incentives for backward areas, accelerated depreciation etc.

• The sensitivity analysis should also be presented – i.e. the sensitivity of the rate of return of

change in the level & pattern of product prices.

Page 36: Unit viii preparation of project report

Planning Commission Guidelines

8. Economic Analysis

• Social profitability analysis needs some adjustment in the data relating the costs & returns to

the enterprise.

• One important type of adjustment involves a correction in input & costs, to reflect the true

value of foreign exchange, labour & capital.

• The enterprise should try to assess the impact of its operations on foreign trade.

• Indirect costs & benefits should be included in the report. If they cannot be quantified, they

should be analysed & their importance emphasized.

Page 37: Unit viii preparation of project report

Network Analysis

Page 38: Unit viii preparation of project report

Network Analysis

Network analysis is the general name given to certain specific techniques which

can be used for the planning, management and control of projects.

• The network analysis methods are used in project management where the

elements are key activities of the project in the mutual time relation.

• The network analysis methods focus on calculating or critical path

optimizing between the elements.

Page 39: Unit viii preparation of project report

Network Analysis

Among basic network analysis methods include:

• CPM (Critical Path Method)

• CCM (Critical Chain Method)

• PERT Method (Program Evaluation and Review Technique)

• GERT Method (Graphical Evaluation and Review Technique)

• MPM Method (Metra Potential Method)

Page 40: Unit viii preparation of project report

Network Analysis

• The network analysis methods are related to the concept of network diagram,

which is a view of the project as a diagram which expresses various links

between the project activities.

• The network diagrams and network analysis methods are based on the Graph

Theory.

Page 41: Unit viii preparation of project report

Network Analysis

CPMLogical mathematical model of the project based upon the optimal duration required for each activity and optimal use of available limited resources.It is a deterministic model.

PERT• Scheduling technique, It shows any job or project as a set of

processes/activities which must take place in a certain sequence.• It is a probabilistic model and introduces uncertainties in project network.

GERT• Networks representing research and development project the process is

repeated till the desired out come is achieved.• GERT network only simulation can be used.

Page 42: Unit viii preparation of project report

Network Analysis

Use of PERT

• The activities of the project are identified along with their interrelationships and graphically

represented.

• Time required for completing each activity/process is estimated.

• Minimum time required for completing the entire project is estimated.

• The critical activities are identified for the efficient allocation of resources in order to complete

the project at the earliest.

• Closer watch on critical and other activities so as to complete the project on time.

Page 43: Unit viii preparation of project report

Network Analysis - CPM

The following table gives the activities and the time required to complete each activity of the project.

Example

Page 44: Unit viii preparation of project report

Network Analysis - CPM

The following table gives the activities and the time required to complete each activity of the project.

Example

Page 45: Unit viii preparation of project report

Network Analysis - CPM

The following table gives the activities and the time required to complete each activity of the project.

Example

• Since the path 1-2-5-6 consumes longest time (18 days). • it is known as critical path and the activities 1-2, 2-5 and 5-6 are known as

critical activities.• Hence the project completion time is 18 days.

Page 46: Unit viii preparation of project report

Network Analysis

Differences between PERT and CPM

PERT CPM

Event oriented approach Activity oriented approach

Allows uncertainty Does not allow uncertainty

Probabilistic model Deterministic model

Time based Cost based

Page 47: Unit viii preparation of project report

COMMON MISTAKES BY ENTREPRENEURS IN PROJECT FORMULATION

Page 48: Unit viii preparation of project report

COMMON MISTAKES BY ENTREPRENEURS IN PROJECT FORMULATION

• Selection of project area

• Market study and analysis

• Selection of technology

• Optimistic estimates

• Ownership form

• Selection of location

Page 49: Unit viii preparation of project report

PROJECT FEASIBILITY STUDY

Page 50: Unit viii preparation of project report

PROJECT FEASIBILITY STUDY

Project feasibility analysis is carried out to ensure viability of project.

The project feasibility study is

• Market feasibility

• Technical feasibility

• Financial feasibility

• Economic feasibility

• Ecological feasibility

Page 51: Unit viii preparation of project report

PROJECT FEASIBILITY STUDY

Market Feasibility • Demand for the proposed product/service.• Market share of the project under consideration.

Market analysis requires variety of information and appropriate forecasting methods.

Consumption trends in the past and the present / Past and present supply

position / Production possibilities and constraints / Imports and exports /

Structure of competition / Cost structure / Consumer behaviour, intentions,

motivations, attitudes, preferences and requirements / Distribution channels /

Administrative, technical and legal constraints.

Page 52: Unit viii preparation of project report

PROJECT FEASIBILITY STUDY

Technical Feasibility

Determine whether prerequisites for successful commissioning of the project have been considered.

Technical analysis addresses the following;

• Has the availability of raw material, power, and other inputs been established?

• Is the selected scale of operation optimal?

• Is the production process chosen suitable?

• Are the equipment and machines chosen appropriate?

• Have the auxiliary equipment and supplementary engineering works been provided?

• Has provision been made for treatment of effluents?

• Is the proposed layout of the site, buildings and plant sound?

• Have work schedules been drawn up realistically?

• Is the technology proposed to be employed appropriate from the social point of view?

Page 53: Unit viii preparation of project report

PROJECT FEASIBILITY STUDY

Financial Feasibility To ascertain whether the propose project is financially viable.

The aspects to be looked into;

• Investment outlay and cost of project

• Means/modes of financing

• Project profitability

• Break-even point

• Cash flows of the project

• Investment worthiness judged in terms of various criteria of merit

• Project financial position

• Level of risk

Page 54: Unit viii preparation of project report

PROJECT FEASIBILITY STUDY

Economic/Social Cost-benefit Analysis Judging a project from the larger social point of view.

The aspects to be looked into;

• What are the direct economic benefits and costs of the project measured in terms of shadow

(efficiency) prices and not in terms of market prices?

• What would be the impact of the project on the distribution of income in the society?

• What would be the impact of the project on the level of savings and investment in the society?

• What would be the contribution of the project towards the fulfilment of certain like self-

sufficiency, employment and social order?

Page 55: Unit viii preparation of project report

PROJECT FEASIBILITY STUDY

Ecological Analysis Environmental concerns should be addressed properly.

The aspects to be looked into;

• What is the likely damage caused by the project to the environment?

• What is the cost of restoration measures required to ensure that the damage to

the environment is contained within acceptable?

Page 56: Unit viii preparation of project report

End of Module