Activity types & Relationships By Er.Nikil Raj… Creating logic in your project CRITICAL PATH SCHEDULE EARLY START ORACLE LATE START PLANNING EARLY START ORACLE Primavera SLACK FORWARD PASS EPS PASS 0 5 / 2 6 / 2 0 2 2 1 Copyright © all rights reserved to www.tutomaash.com | any queries can be mailed to [email protected]

Activity Types and Relationships in Primavera p6

Embed Size (px)

Citation preview

Page 1: Activity Types and Relationships in Primavera p6

05/01/2023

1

Activity types & RelationshipsBy Er.Nikil Raj…Creating logic in your project

CRITICAL PATH SCHEDULE EARLY

START ORACLE LATE START

PLANNING EARLY START ORACLE

Primavera SLACK FORWARD PASS

EPS PASS

Copyright © all rights reserved to www.tutomaash.com | any queries can be mailed to [email protected]

Page 2: Activity Types and Relationships in Primavera p6

05/01/2023

2

Activity types

START MILESTONEFINISH MILESTONE

TASK DEPENDENT RESOURCE

DEPENDENT

LEVEL OF EFFORTWBS SUMMARY

Page 3: Activity Types and Relationships in Primavera p6

05/01/2023

3

START MILESTONE

FINISH MILESTONE

Start milestone activities displays start date

Finish milestone activities displays finish date0DURATION

ACTIVITIES

Page 4: Activity Types and Relationships in Primavera p6

05/01/2023

4

TASK DEPENDENT RESOURCE

DEPENDENTTASK DEPENDENT

ACTIVITYRESOURCE DEPENDENT

ACTIVITY

RESOURCE CALENDAR

PROJECT CALENDAR

Page 5: Activity Types and Relationships in Primavera p6

05/01/2023

5

LEVEL OF EFFORT

FOUNDATION

SUPER STRUCTURE

FINISH WORK

PROJECT MANAGEMENT (LOE)

SSFF

30d30d

30d

90dDuration is calculated from its

relationships• Level of effort activities cannot have constraints assigned to them.

• Level of effort activities are not included when leveling resources.

NOTE

Page 6: Activity Types and Relationships in Primavera p6

05/01/2023

6

WBS SUMMARY

4TH Floor Roof Slab – 10 day• Marking - 1day• Wall reinforcement - 3day• wall shuttering - 2 day• Roof slab shuttering - 1 day• Slab reinforcement - 2 day• Slab concreting - 1 day• Total slab duration (WBS summary) –

10 day

WBS Summary Activities will follow its

WBS Summary duration

Page 7: Activity Types and Relationships in Primavera p6

05/01/2023

7

RelationshipsACTIVIT

Y AACTIVIT

Y B

ACTIVITY A

ACTIVITY B

ACTIVITY A

ACTIVITY B

ACTIVITY B

ACTIVITY A

ACTIVITY B

ACTIVITY A

ACTIVITY B

ACTIVITY A

FSSF

SSFF

FS-1D

FS+1D

LEAD

LAG

1D

1D

FINISH TO START

START TO FINISH

START TO START

FINISH TO FINISH

Page 8: Activity Types and Relationships in Primavera p6

05/01/2023

8