Overview
5
Introduction
6
Atlas Honda Limited is a joint venture between the AtlasGroup and Honda Motor Co., Japan. Both these motorcyclemanufacturing concerns were established by the AtlasGroup. Atlas Honda Limited manufactures and marketsHonda motorcycles in collaboration with Honda MotorCompany.
Plant Departments
7
Atlas Honda follows Process Layout.
They have different sections of different operations some of which are:
Casting Plant
Paint Shop
HR Department
Finance & Accounts
IT Department
Logistics
Vendor Procurement
Maintenance
Store
QC Department
Manufacturing Plant
Assembly Plant
Engine Plant
8
Management
9
It is a skill of personal will and humility towards theprofession through which a person can lead any instituteor organization with well organized manner.
Management system
10
In Honda Atlas the Management Style is Benevolentautocracy, Which means the employs are expected to beloyal and co-operative in production. The behavior of topmanagement with the employs is decent and kind butdecision making is centralized.
OrganizatiOn…??
11
An Organization is firm which born when a group ofpersons work on a common goal. Honda is a PrivateLimited Company. Two or more person can form this typeof company and Govt. does not interference the workingof the system.
Atlas Honda Plants Location
12
Atlas Honda have two main plants in Pakistan.
One is in Karachi and the other one on Sheikhupura Road
They manufacture Only CD70 in Karachi, while in Sheikhupura Plant they manufacture all of their models i.e. CD70, CD100, CD125, and CD125 Deluxe.
Plant Locations RESONS
13
Further more the reason of there more production inShiekhupura Road. They could also have made there plantin other place then this, but another reason is that theyhave the most demand in Punjab all over Pakistan.
Most of there Vendors & Sub Contractors are also fromLahore and Shiekhupura so there availability also counts alot.
Plant lOcatiOns rEsOns…
14
The reason of manufacturing only One model in Karachi isthe plant location as well the demand in Karachi.
As we all know that street crimes and car snatching arevery common in Karachi. So they prefer to have thecheapest of the motorcycles.
Effect of Location
15
Human resources
Infra Structure
Industrial Culture
Material Resources
Energy
16
AKMAL Hafeez
BSME-01113011
17
Process layout
18
In process layout the machines are grouped on the bases of
function in atlas Honda process layout has used
PrOcEss layOut ….
19
PROCESS NO. OPTION OPERATION DESCRIPTION
1 Cutting & Molding Die cutting of metal sheets & shaping of cut parts
2 Die Casting Casting of aluminum parts
3 Welding & Grinding Joining of sheet Metal Parts & Grinding of welds & seams.
4 Machining Finishing of Site Cast & supplied parts
5 Cleaning & Preparation Spraying with Rust inhibiting Compound.
6 Phosphating Surface cleaning & preparation of Mild steel parts
7 Dipping Surface coating in a paint dip tank
8 Anodizing Surface preparation of Cast and Machined Aluminum parts
9 Degreasing Surface cleaning of circular Aluminum parts
10 Drying after Phosphating Oven Drying
11 Drying after Dipping Oven Drying to cure Dip Tank coating
12 Air Drying Drying by Compressed Air
13 Spray Painting Surface Finishing by Air/ Paint spray
14 Buffing Mechanical cleaning of circular Aluminum parts
15 Drying after painting Oven Drying to cure Spray paint coating
16 Engine Assembly Assembly of Engine from parts
17 Final Assembly of Complete Motorcycle
Total productive maintenance Application
20
They have:
Proper Material Movement
Space for the Operator
Space for repair & Maintenance
Space for temporary storage
Space for Loading Unloading
Maximization of the use of workspace
All the utilities are provided in the proper manner.
Proper Safety Rules
STORES
21
Stores dept. at AHL performs following functions.
Manages the receiving, stacking & issuance of parts &materials to the shop.
Ensures the provision & dispatches of required parts to SKP& KHI plant, spares part division & vendors.
Handles the rejections & damages from all shops
Handles the scraps & wastes generated in the factory
Division of stores
22
Stores dept. at AHL has been divided into a no of smallstores according to the type of material being stored andfunctions/services provided by the store. The division isshown as follows…
At AHL, following handling techniques are used:
a) For handling from shop to shop especially designedtrolleys, and pallets are used.
b) Imported motorcycle components are received in steel &wooden cases &pallets.
c) Local vendor parts are received from receiving section instandard carton boxes.
Material Handling
23
For in plant material handling, they have Fork Lifters,Trucks, Pick-ups etc.
They have Belt conveyor on their assembly line whichmoves automatically and can be paused if required.
MatErial Handling…
24
They also use suspensionconveyors on the assembly lineto bring the chassis from thepaint ED Paint shop onto theassembly line.
In their Engine Div. they useIdler roller conveyors to forwardthe work piece from onemachine to another.
25
PRODUCTION PLANNING
26
PPC deals with managing the details of what & how manyproducts to produce and when, and obtaining the rawmaterials, parts, and resources to produce those items.PPC does this by managing information. For this purposePPC has to keep strong interactions in terms ofcoordination, communication & cooperation with 4 majorsections of Production and service departments like….
QA, Logistics
Maintenance
DCC/ Stores
PPC Karachi as well.
Waqas gul
BSME-01113066
27
Planning
28
Production planning is done to ensure the budgetedproduction targets of AHL. The planning is majorly done atAHL, the company sets its production targets. On the basisof these targets following type of planning is done.
Aggregate planning
Master production schedule
Aggregate planning
29
On the basis of forecasting, a schedule from SAP, accordingto the production capacities & company’s strategies, isgenerated which includes the planning of whole year. Itincludes the production breakup of motorcycles for wholeyear into model wise, plant wise & month wise breakups.
Master production schedule
30
In Honda Master Production Schedule represent Quantitiesof individual products Considering demand for cast currentinventory and back log.
On the basis of aggregate planning, such a monthlyschedule is made which includes day wise (2- shift wise),model & color wise breakups.
VENDORs
200+ vendors are actively engaged with the company.
Apart from the local vendors there is one main foreignsupplier for imported components/ parts i.e. Honda Motorcompany JAPAN which accounts for 30% of its purchases.
Trading reputation of the company is excellent
since the company is known for its fair
dealing and timely payments record to all creditors
VENDOR PROCUREMENT
The main responsibility if this dept. is ensuring part availability in rightquantity & in right time.
This department is for local vendors in Pakistan.
Purchase orders:-The purpose is to inform developed vendors (in the
start of the new year)that during this new year, AHL will buy the parts insuch quantities and at such rate. This basically helps vendor to do hisaggregate & capacity planning.Trading reputation of the company is excellent
since the company is known for its fair
dealing and timely payments record to all creditors
Batch Production
33
Atlas Honda manufactures motorcycles in Batches.
In 2012 they manufactured 6,44,000 Bikes and had a targetof 7,50,000 bikes last year.
They manufacture bikes on the order of PPC (Productionand Planning Control).
PPC receives orders from their dealers.
BatcH PrOductiOn…
34
PPC is the most important department throughout theplant, so as it has to make decisions according to thedemand that on which day how many bikes will bemanufactured of each model further more of which color,and in what time. And they make it sure that there desiredproduction rate is fulfilled completely.
Atlas Honda manufactures 1815 bikes per day on anaverage.
BatcH PrOductiOn…
35
There total Lead time on the assembly line is 28sec for Onebike.
They have only one assembly line, on which they makemodifications according to the model to be assembled.
Similarly, they do not have different departments(welding,painting, etc.) of every model, they rather just change thejigs accordingly and start to manufacture the next model.
There casting plant is Ranked on 1st position in Asia. Theyhave a very good environment over there and very goodfacilities for the workers too.
Production capacity in Pakistan
36
Rashid munir
BSME-01113015
37
Variety Control
38
Planning is nothing without control. PPC(Productionplanning and control) control ensures & arranges thenecessary resources for implementation of productionplan. For this purpose PPC has an eye on the in-house,vendor, import items &ensures that all the material for thenext day production are available. if there is any shortage,then they collaborate with vendor procurement to ensureavailability of part in time. The other function of PPC is thatif there are deficiencies in the resources available forproduction due to any reason, they work to save thecompany from production loss.
Process of Variety Control
39
Honda Atlas Variety Control process is based on Following….
Simplification:-
Honda Atlas Reducing The Number of type of product.
Standardization:-
Honda Atlas make the Qualitative values of SignificantProduct.
Specialization:-
Honda Atlas Effort on a limited variety of product.
QUALITY ASSURANCE
40
QA dept. administers Quality management & qualitycontrol functions. QA dept. identifies quality relatedproblems in vendor & in-house parts & takes preventiveaction for their re-occurrence.
WARRANTY & FINAL INSPECTION
41
Warranty Claim Data Collection
Final inspection
Stages of final inspection
a) Test bench
b) Visual check
c) Functional check
42
Visual check:
At the second stage visual check is performed.In this test, inspectors check the bike visually according tothe criteria & inspection points provided to them.
Functional check:
It includes the Co & HC emission test & head light testing.Final inspection dept. generates the straight pass of themotorcycles which shows the no of O.K parts as compared tototal no of production.
Final inspection
43
This section of QA is located in final section of 500K plant.This section is formed for the final analysis of the completemotorcycle that comes out of the frame assy.
HR Department
44
In Honda Altus HR is fundamentally an expression of this organization to belief on employee element on the organization success.
The current
Chief Executive Officer: Saquib H. Shirazi
HR is Mr. Razi ur Rehman
General Manager Engineering and Projects:
Muhammad Noman Khan
Human Resources and Succession Plan
45
Honda Atlas Human Resources Policy is to hire young,fresh, energetic and active associates to meet the existingand future workforce requirements and providing itsassociates maximum opportunities for internal mobilitythrough personal training and development to enablethem to take higher positions.
HR Philosophy
46
In Honda Altas HR philosophies are following:
Respect for Individuals
People of organization create it’s success: Apply Integrity Professionalism Feeling for others Primary job is to provide quality service.
They have 3245 employees currently working in their plant in 3 shifts.
Atlas Culture
47
Sincerity & Loyalty
Time is money
Be self assured
Don’t expect others
Members to be helpful
Live economically
Do charity
3R – Respect, recognition, reward
Be overall happy, healthy & wealthy
Education, experience, expertise & application
Recruitment & Separation Policy
48
Minimum Qualification
Written Test
Primary Interview
Final Interview
Pre-Employment Medical Test
Offer Letter
Joining Report
Induction Plan
Probationary Period
Confirmation Letter
Training Programs
49
They also arrange several training programs and In house seminars with different institutions like:
IBA Karachi
LUMS Lahore
CMD Lahore
PIM Karachi , Lahore
PIQC Lahore , Karachi
PITAC Lahore
NUST Islamabad
CNDC
50
51