Plug Placement Technique
9-5/8” C/Shoe
• Drill pipe/ tubing is lowered to
desired depth (bottom of
planned plug) in the cased /
open hole
• Drill pipe/ tubing is run in
• Mud is circulated thoroughly to
make it homogeneous9-5/8”
C/Shoe
Plug Placement Technique
• Drill pipe/ tubing is run in
• Mud is circulated
• Mud pump stopped
• Pre-flush/ Spacer is pumped
ahead cement slurry to avoid
contamination with mud.
9-5/8” C/Shoe
Plug Placement Technique
• Drill pipe/ tubing is run in
• Mud is circulated
• Pre-flush/ Spacer is pumped
• Calculated volume of cement
slurry is pumped (hole volume
for desired cement rise)
9-5/8” C/Shoe
Pre-flush
Plug Placement Technique
• Drill pipe/ tubing is run in
• Mud is circulated
• Pre-flush/ spacer is pumped
• Cement slurry is pumped
• After-flush is pumped behind
cement slurry to avoid
contamination with mud
9-5/8” C/Shoe
After-flush
Cmt Slurry
Pre-flush
Plug Placement Technique
• Drill pipe/ tubing is run in
• Mud is circulated
• Pre-flush/ spacer is pumped
• Cement slurry is pumped
• After-flush is pumped
• Displacement is done with mud
to balance the cement plug.
9-5/8” C/Shoe
Plug Placement Technique
9-5/8” C/Shoe
• Drill pipe/ tubing is run in
• Mud is circulated
• Pre-flush/ spacer is pumped
• Cement slurry is pumped
• After-flush is pumped
• Displacement with mud.
(Metal volume to be considered).
(Slightly under displacement
preferred to avoid backflow)
Plug Placement Technique
• Drill pipe/ tubing is run in
• Mud is circulated
• Pre-flush/ spacer is pumped
• Cement slurry is pumped
• After-flush is pumped
• Displacement is completed
Balanced Plug
Method
Balanced Plug
Method
Inside Drillpipe & Annulus
columns balanced
9-5/8” C/Shoe
Pre-flush
After-flush
Cmt Slurry
Plug Placement Technique
• Pipe is pulled out slowly off the
cement column.
• In case exact plug top is desired,
string is pulled out up to the
desired cement top only (with
the pipe still inside the cement
column)
9-5/8” C/Shoe
Plug Placement Technique
9-5/8” C/Shoe
• Pipe is pulled out (above cmt top)
• BOP is Closed
Plug Placement Technique
9-5/8” C/Shoe
• Pipe is pulled out (above cmt top)
• BOP is Closed
• Reverse Circulation is
established
Plug Placement Technique
9-5/8” C/Shoe
• Pipe is pulled out (above cmt top)
• BOP is Closed
• Reverse Circulation established
• Excess cement is reversed out.
Plug Placement Technique
9-5/8” C/Shoe
• Pipe is pulled out (above cmt top)
• BOP is Closed
• Reverse Circulation established
• Excess cement reversed out.
• Circulation is stopped
• BOP is opened
• Further pull out for safety
Plug Placement Technique