DELHI-AGRA ROAD PROJECT by L & T Pvt. Ltd.
Citation preview
Page 1
DELHI-AGRA ROAD PROJECTby L & T Pvt. Ltd.
Intership Présentation by:
Sachin KumarRoll no.:111000129
Page 2
PROJECT:
Page 3
Project Details:
PROJECT TITLE DELHI-AGRA ROAD PROJECT
CUSTOMERM/S RELIANCE
INFRASTRUCTURE LTD.
CONSULTANTSAI/ FEEDBACK
CONTRACTORLARSEN & TOUBRO LTD
CONTRACT AGREEMENT
DATE
21/08/2012
CONTRACT VALUE
Rs.2040 cr
CONTRACT DURATION
27 MONTHS
PROJECT START DATE
01/10/2012
Page 4
Kosi Plant:
1. QA/QC department
2. Highway department
3. Structure department
4. Planning department
5. Safety department (deals with the safety of
staff i.e. proper shoes, helmet, jacket, etc)
6. Store (provides tools, diesel and material)
7. Account department (that maintain the
account)Also there are 1 HOT MIX PLANT, 2 BATCHING PLANT AND 1 WET MIX PLANT
Page 5
HOT MIX PLANT
Page 6
BATCHING PLANT 1
Page 7
BATCHING PLANT 2
Page 8
WET MIX PLANT
Page 9
Also all field work is done on chainage noted on curb
Page 10
QUALITY ASSURANCE AND QUALITY CONTROL DEPARTMENT
QA/QC deals with the all test of minerals which
are using in construction at the site i.e. soil,
aggregate, cement, sand etc and check their
quality also because quality is major pillar of
strength and serviceability after which site
means highway construction comes in which
different layers of the crust spreaded over each
other so that distribution of load should be
uniform , this part comes under Highway
department
1 2 3
4 5 6 6
9
87
Page 13
1. Moisture content and Density of soil
2. Free swell index
3. Grain size analysis
4. Compressive strength of concrete
cubes
5. Marshall test of DBM ( Dense
bituminous concrete )
Test Going On:
Page 14
MOISTURE CONTENT AND DENSITY OF SOIL:
This test is conducted on the soil to calculate its
moisture content and dry density, so that, the
control on settlement of layer can be done
Rammer
Mould
Sample
Page 15
This test is done for getting the failure of soil in
condition arises in which water get stagnated for long
period of time and settlement occurs in the layer.
Kerosene
water
Sample
Sample
FREE SWELL INDEX:
Page 16
GRAIN SIZE ANALYSIS:
This test is done to found the percentage of gravel, sand , silt and clay in soil sample. Gravel (75mm - 4.75mm), sand (4.75mm – 0.075mm ) and silt & clay (0.075mm passing)
PROCEDURE:
1. Take soil sample and wash it to remove dust
2. Sieve it with 0.075mm sieve
3. Dry the sand and weight it W gm
4. Do sieve analysis
Page 17
I.S. SIEVE WT. RETAINED
(gm)W1
% RETAINEDW1/W*100
CUMMULATIVE %AGE RETAINED
(A)
CUMMULATIVE %AGE PASSING(100-A)%
100mm
75mm
50mm
19mm
10mm
4.75mm
2.36mm
0.425mm
0.075mm
pan
Page 18
COMPRESSIVE STRENGTH OF CONCRETE CUBES:
This test is conducted to check the compressive strength of concrete cube after 3rd day, 7th day and 28th day of casting
PROCEDURE:
1. Cast the cube of 150mm*150mm*150mm
dimension mould by using fresh concrete which
is mixed according to design.
2. Remove the cubes from mould after 24 hours
and put it in water tank for curing
3. Take out the cubes after 3rd day , 7th day and
28th day of casting
4. Put the cube immediately in the machine and
applied the load , record the loadat failure ,L
Page 19
Compression machine
Cubes to be tested
Curing Tank
Page 20
MARSHALL TEST OF DBM ( DENSE BITUMINOUS CONCRETE )
This test is done to calculate the compressive strength
of DBM by marshall stability apparatus
Sample
Page 21
HIGHWAY DEPARTMENT
Highway department deals with all the
construction related to the road that can be
embankment and crust construction. Before
cutting or excavating the land , the most
important part is to know the reduced level of
land where we have to start working.
Page 22
Reduced level:
Step 1: Height of instrument (H.I.)= back sight(B.S.)+ temporary bench mark (T.B.M.)
Step 2: Reduced level (R.L.) = H.I. – I.S.
Page 23
EMBANKMENT:
After acquaintance of land , process of clearing and grubbing is done i.e. cutting of tree and root removal from land. Then, the process of embankment filling by soil works in which we calculate reduced level of land at 8 points and then, average it, A. Let crust thickness be C , then , embankment thickness, E comes to be
E=A-C
After calculating E, the numbers of soil layer, N in embankment is calculated by taking each layer of 200 mm thickness such that each layer can be compacted tightly as
N=E/200
Page 24
CRUST:
1 2
43
Page 27
Page 28
After settling the layer by roller (fig.17), there is test conducted under the supervision of costumer for calculating:
1.Wet density2.Moisture content3.Degree of compaction
Page 29
STRUCTURE DEPARTMENT
This department deals with the construction
of all the structures related to road i.e.
1.Flyover
2.Railway over bridges
3.Pedestal under pass
4.Vehicular under pass
12
3
5
8
6
7
Page 32
9
10
Page 33
PLANNING DEPARTMENT
Planning department plays a major role in controlling all the
activities which are related to the project. This can be usage
of material, machines, manpower each and every thing related
to project always pass through this department. The five
major things which I had learned in it :
1.Drawings
2.Daily Progress Report
3.Bar bending Schedule
4.Strip Chart
Page 34
1. Drawings: All the drawings of pavements,
culverts, pedestal under pass, vehicular under pass and
flyover.
Page 35
2. Daily progress report: This report consist an excel chart which tells about all the daily work to be completed and how much work completed. This chart forwards to heads so that they can easily examine the project progress easily.
3. Bar bending schedule: This consists of the information about bars shape , size and dimensions that are used in construction.
4. Strip chart: This chart is representation of road on an excel file which tell us about the section progress of road
CONCLUSION
As day by day number traffic volume is
increasing ,so , this road is widening which is very
necessary because it decrease the rush and
accidental chances on road. Also from all the staff
of L&T ltd. I learned that doing work with proper
dedication, responsibility and honesty makes the
person successful.