Site Extend for Building
17m x 9.3m (158 Sq m)
Project
Facility Building For Workers
Site
Dematagoda Running Shed Premises
Client’s Requirements
Changing Room - 60_Mechanical Staff
Shunters Room - 3 Persons
Shunting Engine
Drivers Room - 4 Persons
Shop 36 - 3 Persons
Gaungers Room - 3 Persons
Engineers Room
Institute
Library
Specifications
01. Foundations As per engineers instructions
02. Anti-termite treatment (with a 10 year warranty)
03. Walls
Brick in cement sand mortar, 9” or 4 ½” thick where applicable.
04. Slab and part of the Staircase
Reinforced concrete 5” thick with Grade 25 concrete.
05. Steel stair case
06. Roof
• Zn/AL Roofing sheets.
• 3"x2" 'GI' box bar at 3'-0" c/c
• 2"x2" 'C' purlings
• Supplying & fixing of 8"x8" colour bonded moulded Zn/Al
gutters with necessary accessories.
• Supplying & fixing of 4" x 4" Zn/Al square Rain water down
pipes with necessary accessories as per detail drawing.07. Aluminum doors and windows – at First floor
All windows and door-win; powder coated aluminum
08. All Timber doors – at Ground floor
Doors - 3”x4” timber framed paneled doorsWindows –Timber framed Glazed windows.
09. Internal Finish & Plaster
Painted over two coats of emulsion paint (Standard colours) on
smoothed putty over rough cement sand plaster
10. External Finish &Plaster
Two coats of paint over filler coat on rough plaster
11. Finishes
All internal floor areas - tiles valued Rs.150/- per Sqft
All bath rooms
Floor - non slip tiles. Value Rs.150/- per Sqft.
Walls - up to 3’ H in average - Tile value Rs.150/- per Sqft.
12. Electrical
Socket outlets
5 amp - 20
15 amp - 05
Lamp points- 35 (Point Only) + 3 for garden
Fans - 08 (Including Fan) Indian/Chinese make)
(Connection charges to CEB by client)
13. Plumbing
WC’S - 02 nos,(Fittings; Chinese make)
Wash Basin (with tap)Chinese make
• Vanity - 01 no in GF
• Vanity - 01 no in FF
Septic tank
Soakage pit
14.External work
Solar panel - approx. Rs125,000/- direct payment to supplier by client
Estimated Cost Summery
Toal Ground floor area = 1002.25 Sq.ft
Total Cost for Ground floor = 1002.25 Sq.ft x LKR.3400
= approx. LKR. 3,407,650
Total Upper floor area = 921.50 Sq.ft
Total Cost for Ground floor = appox. LKR. 1,000,000
Total Cost = LKR. 3,407,650 + LKR. 1,000,000
= LKR. 4,407,650
Added Provisional Sum [10%] = appox. LKR. 5,000,000
Total Cost of the project = appox. LKR. 5,000,000/=