21.3.2015 Tero Järvinen, BIM Manager Granlund Oy EBEC 2015, Helsinki

EBEC2015 Helsinki. Concept of Big Room, Granlund Oy

Embed Size (px)

Citation preview

21.3.2015

Tero Järvinen, BIM ManagerGranlund Oy

EBEC 2015, Helsinki

Granlund OyConsultancy

• MEP Design• Facilities Management• Energy and Sustainability

Software• Manager– Facilities Management• Designer – MEP Design• RIUSKA – Energy Analysis• BSPro – IFC middleware

Numbers• ~532 person, 45 MEUR (2014)

• R&D 3,6 MEUR

MEP Design, Tero Järvinen

Departments

HVAC ElectricalBuilding

Automation

Facility Management

Energy andSustainability

SoftwareDevelopment

Innovation and

Development

Innovaatiotoiminta, Tero Järvinen

EBEC 2015

Task:a Collaborative Workspace for Multiparty Construction Design Team, eq. ”Big Room” concept

21.3.2015

Tero Järvinen, BIM Manager, Granlund

EBEC 2015, Helsinki

EBEC 2015, Helsinki

Task• To develop a concept for a collaborative and innovative

work environment for a Construction Design Team

• Often this kind of workplaces are called ”Big Room”

TATE-tietomallinnus, Tero Järvinen

Origin: DPR Construction inc.

• To get Common Understanding of construction project, different partiesshould be involved in an early phase.

• The decision of building investmentcosts and sustainability are made in an early phase of the project.

• To achieve these requirements, deepcollaboration is needed.

EBEC 2015, Helsinki

Requirements• A collaborative and innovative workplace for a

Construction Design Team

• ICT heavily in use. BIM (Building Information Model) is a mandatory work tool for everyone.

• Social aspect: How to raise team spirit? How to handledifferent personalities?

EBEC 2015, Helsinki

Requirements• Design team includes people from different companies. All

members do not work in a Big Room every day

Discipline Number of people

Week schelude, how many days persons are in Big Room

Architect 4 2 persons 5 day a week2 persons 3 day a week

Structural Engineer 3 2 persons 5 day a week1 person 2 day a week

HVAC Engineer 4 2 persons 5 day a week2 person 2 day a week

Electrical Engineer 3 2 persons 5 day a week1 person 1 day a week

Building Owner 2 2 persons 1 day a week

End User of building 2 2 persons 1 day a week

Random companies 3 3 persons 5 day a week

EBEC 2015, Helsinki

Something to remember• Team Members are randomly working also in other projects

• A project in a Big Room can last 1-2 years

• Big Room is a temporary building / space. When the project is over, the use of the Big Room is also over

• The Big Room can be located in a new or existing building

DRP Construction inc.: Mission Bay Hospital, San Francisco Skanska USA.: San Carlos Medical Clinic, San Carlos

EBEC 2015, Helsinki

ResultsFree Presentation methods, teams decide how to make the presentation

• A concept of a Big Room

• A layout of a Big Room, what kind of room(s)/function(s) are needed?

• How ICT is used? What kind of technical equipments areneeded?

• How people communicate with each other?

• How to work effectively together? How to encourage teamspirit?

• How to translate ”Big Room” into Finnish language?

Innovaatiotoiminta, Tero Järvinen

BIM; Building Information Model

Combied Model

Sustainability Marketing materialHollywood BIM

Models with simulation

Technical visualization

Service Area Charts

Drawings

BIM software(marketing picture)

Real view of BIM Software Combied model with info Equipment schedules

Simulations

Diagrams

Facility Management

Meilahden potilastorni, 1.kerros

EBEC 2015, Helsinki

Helsinki Music Centre, at Imperial side