Swayam Superstructures Pvt.Ltd.
Index
• • 1. Company Profile• 2. Organisation Chart• 3. Safety policy• 4. Quality policy• 5. Technical Staff Strength• 6. Plant & Equipment details• 7. Past experience in related projects (Project Executed in and around Mumbai is
must)• 8. Current Projects in Hand and their status (On-going projects)• 11. Manpower Histogram – Month on Month basis• 12. Detailed Project Schedule for execution – covering complete scope of work• 13. Safety plan and provision.• 14. Reference from current on-going projects.•
EHS Plan for project Execution • Safety Policy of the Contractor • • Safety organization of the Contractor specifying the person accountable for
safety at site. • • Safety organization shall specify the no. of safety manager/ officer and safety
supervisor.• • C.V of the Project Head and the safety team of Contractor to be submitted to the
client for review and approval. • • Plant & Machinery details specifying the make of the machinery/ equipment, age
of machinery with fitness certificate will be provided. • • Details about various processes like safety induction, tool box talk, safety
training, emergency readiness, Safety Committee and incident control shall be covered in the EHS Plan.
EHS Plan • Operational controls like edge protection, hard barricading, safety nets, Personal
Protective Equipment, Fall Arrestor, work platforms, safety signage, Work permit, training and supervision will be provided by SSPL.
• • Safety inspection and audits process and plan to be mentioned in the EHS Plan. • • In case of Incident, reporting structure and first aid arrangement and
modification process shall be included in the plan.
Site Set Up
• Project office • Labour camp setup and maintenance• Traffic and Security management • Safety Induction Room • First Aid Facility • Material storage and Lifting area • Equipment & vehicle parking area
Men and Material access control
• All personnel will have the Project/Site Entry Card.• Safety Induction seal is must on the identity card.• Visitor control will be done through security All vehicles movement will
be recorded. • All entry will be through one gate • Separate pathway for pedestrian
Ensure 100% Safety Induction
• Advance intimation shall be provided to Client’s CM Team including EHS department about new joiners in the standard induction request format.
• New workers /staff / visitors shall undergo safety induction training at site before entering Construction zone.
• Safety Induction stickers shall be issued by the contractor after induction
& recorded.
Ensuring 100% Personal Protective Equipment (PPE)
Men & Materials Logistics • Verification of Project Entry Card & attendance at site • All trailers/ goods carrying material/ equipment will be escorted. • All trailers/ goods vehicle will be under the escort supervision from entry
to exit. • Road safety rules shall be adhered by the Contractor vehicles while at
site
Communication on site
• Radio Frequency sets will be made available to Section In charges • Emergency siren • Public address System/ Megaphone for any announcement / TBT
• Worker restricted for usage of mobile phone during working hrs.
Safety requirements while Excavation or working in Excavated pits
• Inspection of site location • Risk analysis of Excavated area • Checking of underground utilities like
HT/ LT cable, gas pipeline, sewage lines, etc.
• Cave-in protection • Approach to excavated area • Hard barricading of Excavated area • Emergency equipment like motorised
pump for removal of collected water • Adequate safety signage • Follow Work permit process
Fall Protection Provision
• All the opening /cut out, lift duct shall be barricaded with 40 NB pipe
• Peripheral barricading for each floor shall be provided with hand rails.
• Vertical protection shall be provided to floor cut out / any service duct
• Lift duct shall be barricaded horizontally & vertically
• Peripheral barricading with toe guard shall be provided considering safe distance of 1 meter.
• Workmen engaged in height work shall wear Personal Fall Arrest System (Full Body
Safety harness anchored to anchorage point)
Safety screen and safety net Provision
• Horizontal safety net of double layer shall be provided at every 3 floors to prevent fall of material & fall of Person.
• Intermediate safety net shall also be provided
• Conventional Shuttering safety: Conventional Formwork with safety working platform and netting system shall be implemented after seeking approval from Client Engineers/CM Team.
• Horizontal net for lift core area to prevent fall of material / person
Fall Protection-For conventional work
Fall Protection - Catch Nets
Fall Protection – Lift Shaft
Garbage Chute provision for debris removal
Plant and Machineries Erection & Dismantling
• Risk assessment & Method Statement for erection and dismantling of Tower crane to be submitted before erection.
• All the erection activity to be carried out by skilled workers & staff
• All materials to be lifted through lifting area
• Provision of Personal Fall Arrest System
• Scaffolding to be used for erection • Work permit Process to be
implemented • Area needs to be barricaded
Tower Crane (SSPL scope)• Tower Crane inspection & approval from SSPL (Contractor’s) end to be
carried out by Client before mobilization at site.• Method Statement for erection & dismantling to be submitted by SSPL
(Contractor) for seeking approval before carrying out the work. • Operator & rigger proficiency check will be done by Client before
allowing them for work. • Walky Talky mandatory for operator and Rigger/ Signalman. Safety
features mandatory • Self adjusting hook block.• Fail safe break on hoist.• Over Hoist Warning system • Wind speed anemometer • Aviation light • Independent earth pit
Plant and Machineries Inspection and operation
• All the lifting equipment will be subjected to third party certification
• Equipment shall undergo preventive maintenance & report shall be submitted
• Internal Inspection carried out for all equipment periodically Deployment of trained & competent operators only
• Approval of Equipment/ machinery operators shall be taken from Client/Engineer in charge (EHS) Dept. before deployment
Third party Inspection by Expert
• Tower crane • Mobile crane• All the Lifting tools & tackles
(Chain Sling, Wire rope sling, Web belt, D shackles etc.)
• Fitness report of all Equipment/ Vehicles deployed by SSPL (contractor)
• Client approved agency for certification/caliberation.
• TPI reports shall be submitted to Client/Engineer’s (EHS) Dept. before driving the above equipment in use.
Temporary Electrical supply
• SSPL (Contractor) will submit the license and competency certificate of electrical engineer, supervisor & electrician before deploying at work
• Electrical Work shall be carried by only skilled Electricians
• All the Distribution Board will be as per Indian Electricity Act standard.
• ELCB/ RCCB and earth shall be provided for all electrical installation
• Tripping test of ELCB to be carried out & register to be maintained
• Emergency light in staircase/ access/ near lift platform shall be provided
• Fire extinguishers shall be provided and maintained at all levels of building
Material shifting with Temporary loading platform
• Loading platform made available if required for material shifting • Platform shall be installed, after design approval only • Edge Protection & safety harness shall be provided • Safe Working Load and last tested by TPI to be displayed.
Scaffolding
• Scaffolding inspection before usage & tagging system
• Adequate type of scaffolding to be used for different activities (If required)
• Use of fall arrestor and Personal Fall arrest system
• Scaffoldings Erection/ Dismantling shall be carried out by trained Scaffolder
Portable Ladder
• SSPL (Contractor) shall be responsible for ensuring • No portable single ladder shall be over 6 meters in length. • The width between the side rails shall not be less than 45 cm. • When a ladder is used, a person shall be engaged only for the purpose
of holding the ladder at that point of time. • All the ladders must have hand rails. Use only aluminium ladder. Wooden ladder not allowed.
Safety Training & Safety Committee Meeting• Training of workmen through a)
Induction b) Tool Box Talk C) PEP Talk
• Behavior based safety training to all
• Training calendar will be prepared • Training given to Field Engineers &
staff on safety topics• Competency Development
Training of Safety staff • Formation of safety Committee &
monthly meeting • Records of all above shall be
submitted to Employer’s EHS Dept.
Motivational Activities • Best safety workers for the month • Best safety Staff for the month • Annual Safety Day Celebration • Aids awareness • Tetanus drive • National safety week
Fire Prevention
• Fire extinguishers shall be provided at designated places and properly maintained
• Subjected to regular inspection by safety personnel
• Location map will be prepared & displayed
• Fire demo & training for usage during emergency
Emergency Response Plan: (ERP)
• ERP shall be prepared based on site condition & risk • Every one will undergo ERP training • Mock drill to be conducted periodically • Emergency Response Team in place • All the emergency Contact Nos. shall be displayed • Tie-up with nearby Hospital
Safety Posters & Signages
• Safety Posters installed at prominent location at site
• Safety Signage at identified places shall be provided
Housekeeping
• Dedicated supervision for Housekeeping
• Collection dust bin at designated places
• Daily removal of debris/ waste regularly outside the site
• Housekeeping plan shall be prepared
• Housekeeping audit weekly by safety personnel & will be reviewed at weekly site meeting
• Mass Housekeeping drive shall be conducted
Safety Audits & Inspections
• Regular & periodical audits by Corporate EHS dept.• Electrical Inspection • Labor Camp Inspection • House keeping audit • PPE Inspection • Fire Extinguisher inspection • P& M Equipment's inspection • Stores audit
Requirements regarding Workers Accommodation Camp
• Client’ s Scope • • Land for Labour camp duly barricaded
will be allotted by Client. • • Water connection (Main point with
meter) will be provided. • Electricity connection main point with ELCB will be provided. • RO Plant will be provided by Lodha of 500 KL capacity with one outlet point.
• • Security for the overall camp will be
provided at the entrance of the camp.
• SSPL (Contractor’s) Scope• Labor Hutment plan including kitchen, toilet, bath area, STP, soak pit shall
be prepared and get it approved from Client. • Hutment material shall be arranged by SSPL (Contractor). • Hutment erection and commissioning shall be done under SSPL (Contractor) direct supervision. • SSPL (Contractor) will provide Camp boss, Security personnel, electrician and plumber for upkeep and security. • Internal partition shall be erected by SSPL (contractor) within the camp. • Water (Drinking) points- Adequate points shall be planned for your team • Provision of adequate Electrical points in hutment, toilet, bath area and drinking water area and pathway lighting shall be responsibility of SSPL (Contractor).
• SSPL Contractor’s Scope (Continued)• PCC floor shall be provided in all rooms and pathway. • Sufficient brick work
(Bund wall) shall be done to avoid water entering into the room during monsoon. • Proper slope to be provided to the roof of hutment and Tarpaulin shall be provided to prevent leakage during monsoon. • Distribution boards with MCB and ELCB to be provided to safeguard the electrical cable in case of usage of water heater. • Pest control from mosquitoes, rodents and snakes shall be SSPL (Contractor) scope. Frequency shall be discussed with Client. • Safety Induction facility with 20 person capacity with T.V and DVD for screening induction films. • First Aid room facility with trained First Aider and first aid kit shall be provided • Safety signage at conspicuous location shall be provided. • Food waste collection bins shall be provided and daily collection.
Health & Hygiene of labours
• Medical Examination of workmen before getting into job at site.
• Fogging & pest control for Site & labour camp
• Labour camp hygiene condition • MBBS Doctor Visit once a week • First Aid Room with trained First
aider • Ambulance tied up with nearby
hospital
Worker Welfare Facility
• Dust Bin at Labour Camp • Staff Canteen
• Doctor Visit
• Thank you• Swayam Superstructures Pvt.Ltd.