There are generally three methods to the site allotment-

Bidding process

MoU method

Swiss model of defence

Site allotment/license

Page 3: Licensing for SHP

The project for which PFR/DPR isavailable shall be put on acompetitive bidding.The project shall be advertised

widely to seek bids from privateentrepreneurs desirous for settingup SHP.

Bidding process

Page 4: Licensing for SHP

Application in response to theadvertisement should be accompaniedby a non refundable amount fixed bySG.

All bidders shall be subject toprequalification.

Contd…

Page 5: Licensing for SHP

All prequalified bidders will be provided withthe PFR/DPRs.

Bids shall be invited for premium payableupfront.

Upfront will be per MW for each project,subjected to a minimum threshold premium.If the bid received beneath the threshold…

Contd…

Page 6: Licensing for SHP

… will be rejected.

Project will be allotted to the bidders makingthe highest bid.

The successful bidder shall be required todeposit the premium amount within areasonable period of receiving intimationregarding his successful bid.

Contd…

Page 7: Licensing for SHP

If more than one bidder bids theidentical premium per MW for any site, agradation list based on pre-qualificationcriterion shall be the basis for allotment.

In case there is no bid for two times, thesite is allotted to govt. agency.

Contd…

Page 8: Licensing for SHP

The project for which PFR/DPR are notavailable shall be allotted to the pre-qualifiedbidders.

The project shall be advertised in order toseek bids. Application in response to theadvertisement…

Contd…

Page 9: Licensing for SHP

…should be accompanied by a non refundableamount fixed by SG.

All bidders shall be subject to pre-qualification.

The merit list of the bidders shall be preparedaccording to the pre-qualification criterionand project allotted to the bidders.

Contd…

Page 10: Licensing for SHP

Any feasible SHP potential site identified bythe IPPs/User society and proposed to SG forallotment along with self prepared verifiablefeasible PFR/DPR-

Contd…

Page 11: Licensing for SHP

The application fee and bid amount shall be paid.

These projects shall be allotted as first cum basis.

Contd…

Page 12: Licensing for SHP

Any interested developer may give their offerto SG through the state nodal agency.

The SG will give project-wise consent forpreparation of PFR through the state nodalagency to the developer.

MoU method of allotment

Page 13: Licensing for SHP

The developer shall submit PFR to the statenodal agency.

Based on such PFR,SG will decide to giveconsent for detailed survey and investigationand DPR preparation.

Contd…

Page 14: Licensing for SHP

The developer shall submit the DPR to thestate nodal agency and the approval forproject implementation would be given bystate nodal agency, after examining the DPR;if acceptable.

Contd…

Page 15: Licensing for SHP

A formal Memorandum of Understanding/ Agreement will be executed between the developer and SG for implementation of the project.

Contd…

Page 16: Licensing for SHP

This method is generally preferred where there is very less or no competition.

Contd…

Page 17: Licensing for SHP

It is applied where total uncertainty of technology, tariff etc.

In this model an opportunity is given to first bidder to defend his bid.

Swiss model of defense

Page 18: Licensing for SHP

Period of licence/ allotment varies from state to state depending upon the state policy.

For example-in Kerala it is for 20 years; in J&K it is for 40

years

Period of Licence/Allotment

Page 19: Licensing for SHP

The project may be on Build, Own, Operate &Transfer (BOOT) mode.

May be on Build, Operate, Transfer (BOT)mode.

May be on Build, Operate, Lease, Transfer(BOLT) mode.

Ownership mode

Page 20: Licensing for SHP

May be on Lease, Rehabilitate, Operate,Transfer (LROT) mode.

In these modes, after specified period theentire project, including its assets related towater structures and power generation, shallbe transferred to the state government, freeof cost.

Contd…

Page 21: Licensing for SHP

It may be on Build, Own, Operate (BOO) mode.

Contd…

Page 22: Licensing for SHP

Free transfer of shares will be permitted in the companies allotted projects as per the procedure laid down by SG.

Transfer of allotment

Page 23: Licensing for SHP

IPP shall prepare and submit the DPR and all other information and make the necessary applications for obtaining the statutory clearances and approvals of the State & Central government.

Page 24: Licensing for SHP

The IPP shall achieve the financial closure within 12 months from the date of receipt of all statutory approvals and clearances given by the states and central Governments.

Financial closure would imply firm commitments for the financing the entire project.

Financial closure

Page 25: Licensing for SHP

The failure to get those will result inautomatic cancellation of the allotment of thesite, and forfeiture of upfront premiumamounts.

No compensation would be payable to IPP’s insuch instance.

Contd…

Page 26: Licensing for SHP

The IPP may surrender the allotment back to SG if on completion of the DPR, within the stipulated time frame, it has bounds to establish that the project is not techno-economically viable.

Surrender of allotment

Page 27: Licensing for SHP

1. Government of Assam, policy for small hydro power development.2. Hydro electric power policy, Arunachal Pradesh3. Small hydro power policy, Govt. of Madhya Pradesh, New & Renewable

Energy Department.4. Policy guidelines for development of small hydro power projects upto 25

MW capacity in U.P.5. Policy on hydropower development by Private Sector, in the state of

Uttaranchal.6. Teachers manual, Hydropower plants, for engineering diploma program

elective course, by AHEC, IIT Roorkee.7. Electricity act-2003.8. Policy on hydro power development in uttaranchal

References

Page 28: Licensing for SHP

Thank you