37
PRESENTATION ON MAT FOUNDATION DETAILS OF CONSTRUCTION Submitted By:- Group-04, 2 nd Year, 2 nd Semester, Section-C, Department Of Civil Engineering AHSANULLAH UNIVERSITY OF SCIENCE & TECHNOLOGY

Mat or Raft Foundation, AUST O29+30 Sec-C

Embed Size (px)

Citation preview

Page 1: Mat or Raft Foundation, AUST O29+30 Sec-C

PRESENTATION ON MAT FOUNDATIONDETAILS OF CONSTRUCTION

Submitted By:-Group-04, 2nd Year, 2nd Semester, Section-C, Department Of Civil

EngineeringAHSANULLAH UNIVERSITY OF SCIENCE &

TECHNOLOGY

Page 2: Mat or Raft Foundation, AUST O29+30 Sec-C

Contributed By:-Md. Ashif Rayhan Shuvo (12.02.03.041) (Compiler)Nadia Akter Munni (13.01.03.126)Md. Rokanuzzaman (13.01.03.135)Musarrat Mubasshira Atiya (13.01.03.138)Md. Muntasir Salehin (C) (13.01.03.147)Abdullah Al Kafi (13.01.03.159)Mustafidul Hoque (13.01.03.166)Tony Islam (13.01.03.168)Ashiqur Rahman Prottoy (13.01.03.172)

Page 3: Mat or Raft Foundation, AUST O29+30 Sec-C

CONTENTSDefinition of Mat or Raft foundationWhen Mat foundation should be providedTypes of Mat foundationPlan & Sectional viewVisited SitesConstruction Flow ChartConstructing a Mat foundationAdvantages & DisadvantagesConclusion

Page 4: Mat or Raft Foundation, AUST O29+30 Sec-C

Mat FoundationA continuous, thick, concrete slab foundation heavily reinforced with steel supporting an entire structure.It is a type of shallow foundation (depth ≤ width).All the columns are connected to an large RCC slab and the slab is directly contact with the soil.All vertical structural loadings from columns and walls are supported on the common foundation.Generally used in heavy industrial plant, official and commercial buildings and sometimes in residential buildings.

Page 5: Mat or Raft Foundation, AUST O29+30 Sec-C

Sketch Of a Mat Foundation

Page 6: Mat or Raft Foundation, AUST O29+30 Sec-C

When Mat foundation should be providedIf foundation area covers 50-60% of the total plot area.

If the individual columns or footings would be undesirably close together or try to overlap.

It is required where soils have low bearing capacity and have to support heavy structural loads.

Structures on marshy land, soft clay and land that are made up of sanitary land fill or other materials (like debris, unconsolidated soil and solid waste etc.) where differential settlement is suspected.

Page 7: Mat or Raft Foundation, AUST O29+30 Sec-C

Types Of Mat Foundation

Flat Plate Mat Flat Plate Thickened Under

Column

Two-way Beam & Slab

Plate with pedestals

Piled Raft Rigid Frame Mat

Page 8: Mat or Raft Foundation, AUST O29+30 Sec-C

Sectional Design Of A Mat Foundation

Page 9: Mat or Raft Foundation, AUST O29+30 Sec-C

Plan View

Main Beam

Seco

ndar

y Be

am Column

Sectional View

BFS & CC Layer

RCC Slab

Main Beam

Column

Page 10: Mat or Raft Foundation, AUST O29+30 Sec-C

Visited Sites

Credence, Road-7/A, Dhanmondi, Dhaka

Biswas Builders Limited, Road-9/A, Dhanmondi, Dhaka

Page 11: Mat or Raft Foundation, AUST O29+30 Sec-C

Construction Flow Chart

1 • Soil Test

2• Shoring• Water

Proofing

3• Partial

Excavation (Depending upon depth)

4• Strutting• Bracing

5• Full Area

Excavation

6• Soil

Compaction

7• BFS Layer• CC Layer

8• Reinforceme

nt Placing

9• Casting of

RCC• Compaction

10 • Curing

11• Removal of

Shuttering• Further

Curing

12• Retaining

Wall• Shear Wall

Page 12: Mat or Raft Foundation, AUST O29+30 Sec-C

Soil Test

Bearing capacity of soilSoil classificationVoid ratioCompressibility characteristics of the soilPresence & amount of garbage in soilGround water levelMoisture contentDepth of Mat

Page 13: Mat or Raft Foundation, AUST O29+30 Sec-C

Shoring

Creates a continuous wall along the boundary.Supports the load of the surrounding structures during construction.Prevents the surrounding soil from breaking during construction.Prevents the collapsing of the existing structure.Protects the existing structure from vibration.Remains in the ground and serves as a retaining structure.Can be of three types: Concrete pile shore, Steel sheet shore, Log shore.

Page 14: Mat or Raft Foundation, AUST O29+30 Sec-C

Figures of Log Shoring

Page 15: Mat or Raft Foundation, AUST O29+30 Sec-C

Steel Sheet Shore Concrete Pile Shore

Page 16: Mat or Raft Foundation, AUST O29+30 Sec-C

A temporary wall is provided very next to the shoring so that deposited water can’t enter into the construction site.A cement mortar layer is provided over shoring to prevent moisture.

Water Proofing

Page 17: Mat or Raft Foundation, AUST O29+30 Sec-C

Earthwork ExcavationPartial & Full Excavation

is required before further construction.

Soil CompactionAfter full excavation, soil

compaction is needed to obtain a uniform surface for the placement of BFS and other layers.

Page 18: Mat or Raft Foundation, AUST O29+30 Sec-C

Bracing & Strutting

A horizontal support system for the boundary shores during excavation and foundation.

Its requirement depends on the depth of foundation.

Generally made of steel sheet.

Also known as horizontal shores.

Page 19: Mat or Raft Foundation, AUST O29+30 Sec-C

Braces are the orthogonal members in the system.Strut is the inclined member joining two perpendicular braces.King posts are the vertical compression members supporting the brace & strut system.

Page 20: Mat or Raft Foundation, AUST O29+30 Sec-C

Brick Layer Over Compacted Soil

Cement Concrete Layer Over BFS Layer

Page 21: Mat or Raft Foundation, AUST O29+30 Sec-C

Reinforcement Placing

Placement of a batch of horizontal bar;

Placement of another batch of bar to complete the bottom mesh;

Placement of Column bars;

Placement of vertical rod (chair) over bottom mesh to hold the upper mesh;

Upper mesh placement.

Page 22: Mat or Raft Foundation, AUST O29+30 Sec-C

Bottom Mesh Retaining Wall Bar Placement

(Along with bottom mesh placing)

& Column Placement

Page 23: Mat or Raft Foundation, AUST O29+30 Sec-C

Chair Placement Upper Mesh Placement

Chair

Bottom Mesh

Upper Mesh

CC Block

Page 24: Mat or Raft Foundation, AUST O29+30 Sec-C

Sectional View Of Mat Mesh Joint Between Column Footing & Mat Mesh

Upper Mesh

Bottom Mesh

Page 25: Mat or Raft Foundation, AUST O29+30 Sec-C

Joint Between Reinforcement of Column

& Mat Mesh

Tie

Chair

Inclined Bar to hold the

Column straight

Finished Reinforcement Placement

Page 26: Mat or Raft Foundation, AUST O29+30 Sec-C

Other FactorsReinforcement Selection 60~72.5 Graded 12mm~25mm

Rod Cutter

Rod Bending

Chair

Reinforcement Joint(with heavy steel wire)

Tie Bar

Page 27: Mat or Raft Foundation, AUST O29+30 Sec-C

CC Block(to maintain Clear Cover)

Page 28: Mat or Raft Foundation, AUST O29+30 Sec-C

Shuttering

Timber Shuttering Steel Plate Shuttering

Brick Wall used as a Shuttering of Column

Footing(remains as a part of

foundation)

Page 29: Mat or Raft Foundation, AUST O29+30 Sec-C

CastingSide basis castingLayer basis casting

Casting in Mat Mesh Casting in Footing

Page 30: Mat or Raft Foundation, AUST O29+30 Sec-C

Compaction

Casting & Compaction both are done simultaneously.Compaction is generally done by vibrator machine.

Vibrator

Machine

Page 31: Mat or Raft Foundation, AUST O29+30 Sec-C

Leveling

After casting & compaction, leveling is a must to get the same thickness all over the

mat slab.

Leveling with Patta

Page 32: Mat or Raft Foundation, AUST O29+30 Sec-C

Curing

Spraying or Fogging PondingSaturated Wet Coverings (By

Hessian or Gunny Bags)

Page 33: Mat or Raft Foundation, AUST O29+30 Sec-C

Retaining Wall & Shear Wall

Reinforcement Placing Shuttering CastingRetaining wall is provided in basement to prevent lateral load of the surrounding soil.Shear wall is a wall that is designed to resist shear & the lateral force (wind, earthquake).

Page 34: Mat or Raft Foundation, AUST O29+30 Sec-C

AdvantagesThe foundation and floor slab is combined, which saves time and materials.Loads are spread over the whole area of the structure.It can cope with mixed or poor ground condition.It requires little excavation.It reduces differential settlement.

DisadvantagesLarge thickness, expensive.Shore protection is needed.Susceptible to edge erosion.Weak when supporting point loads, specific treatment required.

Advantages & Disadvantages

Page 35: Mat or Raft Foundation, AUST O29+30 Sec-C

Conclusion

This presentation is based on the observations on Mat foundation in various sites & meeting with concerned engineers & workers.

The purpose of this presentation was to gather some practical experience on Mat foundation.

During the making of this presentation, we also practically experienced other major & minor parts of a construction.

Page 36: Mat or Raft Foundation, AUST O29+30 Sec-C
Page 37: Mat or Raft Foundation, AUST O29+30 Sec-C

Thank You All !!