Upload
sagunn-paudyal
View
322
Download
4
Embed Size (px)
Citation preview
Modi Hydropower VisitPresented by:
Bijay Acharya (069/BEL/212)Binod Paudel (069/BEL/215)Deependra Neupane (069/BEL/218)Devendra Bhattarai (069/BEL/219)Madan Bhandari (069/BEL/229)Sagun Paudyal (069/BEL/237)Siddhartha Paudel (069/BEL/240)Suraj G.C. (069/BEL/243)
Why hydropower in Nepal?? Principle of hydropower
generation Key to rescue form the
energy crises of Nepal Hydropower potential in
Nepal Hydropower constructional
background The hydropower project
practices in Nepal
Modikhola Hydropower
One of the high potential river in country Run off River type plant (ROR) 3 km river section , gross head available is 71 m. 2 generator units with each installed capacity 7.4Mw. average annual energy generation of 91 GWh. Estimated initial cost is US $ 27.2 Dollar construction supervision works were carried out fully by
NEA The project construction was started in May 1996
Civil construction detail Catchment Area 510 sq. km Maximum Design Discharge 27.5 /s Turbine Discharge25 /s Rated Net Head 66.96 m Diversion Weir H=7.5 m, L=33 m Intake L=33 m, H=0.7 m, W=20.5 m Box Culvert 250 m (twin barreled) Desanding Basin (twin chambered) L=154.5 m, W=10 m, H=6.5 m Open Canal 61 m Regulating Pondage 37,900 Total Tunnel length 2071 m Surge tank H=40 m, dia=9 m Powerhouse L=28 m, W= 14.5 m, H=23.5 m Tailrace Box Culvert 281 m
Mechanical details Turbines
TypeVertical, Francis
Number 2 Rated Output 7.4 MW Rated Speed 429
rpm
Shaft Orientation
vertical
Penstock Diameter 3.5m Length
32m Material
Steel
Draft tube Type
cylindrical Pressure
compensation
Electrical Details Generators
Type Vertical Shaft, Synchronous type Number 2 Capacity 8260 kVA Power factor 0.9 Voltage 6600 V Frequency 50 Hz
Transformers Type Three phase Number 2 Capacity 8260 kVA Voltage Ratio 6.6/132 kV
Transmission Line 132 kV, L=37 km Towers 109 nos. Installed Plant Capacity 14.8 MW (2 x 7.4 MW) Total Avg Annual Energy 92.5 GWh
Generator Transformer
Generator Transformer
Motor Induction motor
Used in dewatering system, cooling system, diesel generator starter
Servo motor Used in governing the guide vane during
load fluctuation for frequency control
Electrical Auxiliary
Dry transformer Voltage
6.6kV/110V
Battery 110V, 150A and 48V,
100A
Diesel Generator 6 cylinder, .012
inch rpm 445 Power 131hp
Compressor
Control system Controlling the overall flow
Butterflying valve. Controlling the excitation
AVR system. Controlling the power output
Governing mechanism . Circuit breaking
Relay CT & PT SF6 ACB(Air circuit breaker) VCB(vacuum circuit breaker)
PID control system Mechanical breaking system
Governing mechanism Modi khola is a national grid connected
system Automatic electronic governing mechanism
using plc linked with the hydraulic governer. Hydraulic governer is linked to the guide
vane of the generator which finally regulates the overall flow of the water in the turbine to produce the require amount of power
Fig. Governing Mechanism
Synchronization process
Modi khola hydropower is a national grid connected system.
Two types of synchronizing system. Automatic synchronizing system.
Synchronizing rely. Manual synchronizing system.
Fig. Synchronizing Panel
Excitation control system Plays an important role in maintaing the reactive
power flow in the system. Maintain the power factor of the generator in
specfied limits Maintain the generated voltage in the specfied limits. The excitation system used is burshless excitation
system controlled by the digital automatic voltage regulator.
AVR is the thristor embedded system which compares the output voltage of generator and provides the necessary excitation voltage to the generator
Or grid
One line diagram
Earthing Mat earthing Maintained 0.1
ohm earth resistance
Body earthing and neutral earthing
The lightining arrester.
Switchgear and protection
Circuit breaker Relays
CT PT
Problem and Recommendation Small area of the
settling basin so the sand does not settle properly in the basin;
Problem in diversion system and intake construction.
There is no SCADA system in use.
The settling basin should be upgraded.
The direction of the flow of water should be managed at diversion weir.
The SCADA system should be maintained as soon as possible
References www.nea.org.np www.google.co
m Handbook of
Modikhola hydropower
Thank you !!!