Noble Fire Request For Quotation Prepared by Julian Kalac, P.Eng 11/7/2012

RFQ -WELDING

Embed Size (px)

Citation preview

Noble Fire Request For Quotation

Prepared by

Julian Kalac, P.Eng

11/7/2012

Page 2 of 11 Noble Fire RFQ 7 November 2012

Description:

Noble Fire, known as Don Park Fire, is the leading fabricator of sprinkler heads in Ontario. Noble Fire produces Sprinkler Systems for both residential and commercial industries as

per the NFPA and Ontario Building Code standards Noble Fire is requesting a quote to design, build and integrate preselected Cypress

Welding & Plasma Burning machines as per Noble Fire requirements. It is the responsibility of the machine builder/integrator to become familiar with all Noble Fire

production environment plant conditions. STANDARDS & REGULATIONS:

The machines and integration of the machines must fully comply with:

Ontario Health Safety Act National Fire Protection Association (NFPA)

National Standard for Sprinkler System Design (FC 403 ) CSA Certified

Ontario Building Code

The type of outlets and quality Noble Fire produces are shown below:

Page 3 of 11 Noble Fire RFQ 7 November 2012

Production Processes The production requirement is to be able to burn and weld a minimum

DESIRED EQUIPMENT INTEGRATION Noble Fire would like to integrate the following equipment into their production facility:

1. CYPRESS CWE-1500-MG Circle Welder With Remote

2. CB-1P Plasma Circle Burner

Noble Fire Production requirement is 900 welded outlets/day

Based The Cypress Machine Capability is 6-10 seconds for cutting and 15-20

seconds for welding. Therefore the total combined cycle time = 30 seconds

Therefore the Cypress Capacity should be the following:

Integrated at our facility with our pipe bench by machine builder/integrator

The pipe rack system we have is shown below in a front view & side view

Cycle Time AnalysisCutting Time

(sec)

Welding Time

(Sec)

Total Time

(Sec)

Outlets/

Min Outlets/HrOutlets/Shift

(8Hrs)

Outlets/

Week

Outlets/

Month Outlets/Year

Burn + Weld 2 Cycles 10 20 30 2 120 960 4,800 19,200 230,400

Burn/Weld in 1cycle 10 20 20 3 180 1440 7,200 28,800 345,600

CYPRESS MACHINE CAPACITY EXPECTATION

Page 4 of 11 Noble Fire RFQ 7 November 2012

SIDE VIEW OF THE PIPE BENCH RACK

Page 5 of 11 Noble Fire RFQ 7 November 2012

Run-Off Acceptance Criteria

Machine acceptance at Machine builder facility is defined as per below:

Min 8 hr run time at supplier facility prior to shipping, demonstrating a 95%

Machine Efficiency with a total of 1300 good welded outlets

Max downtime of 1%

Quality—Min 99.9% Quality validated by leak testing using air and die

penetrate testing as per Noble Fire standards & specifications

Max changeover time = 5 min

Full CSA certification and compliance

Full OHSA compliance by machine builder/integrator and approval to use

without a PSHR required under 851 OHSA section 7

Ventilation and Air Quality Testing results to be provided prior to any

acceptance indicating the minimum ventilation speed is 0.5 m/s as per

Government Canada Welding Regulation

Full compliance to section 5.48 of the OHS Regulation approval regarding

ventilation and OEL

Acceptance at Noble Fire Criteria:

Min 8 hr run time at Noble Fire facility same 95% Machine Efficiency with a

total of 1300 good welded outlets

Max downtime of 1%

Quality—Min 99.9% Quality validated by leak testing using air and die

penetrate testing as per Noble Fire standards & specifications

Max changeover time = 5 min

Page 6 of 11 Noble Fire RFQ 7 November 2012

Documents required:

User manuals and drawings

PM schedule and parts needed to be inspected

Proposed PM service plan

Parts submission Warranty from Cypress

DELIVERY

Required delivery is 8-10 weeks. If longer lead time is needed then options

need to be submitted on how to reduced the delivery time and what Noble Fire

can do to assist.

ON SITE ASSISTANCE:

All prices must include full On-Site assistance and support until the final

acceptance is achieved. No additional costs nor charges.

Payment terms:

1. 25% with Purchase Order

2. 50% after acceptance at supplier facility as per above

3. 15% after approval at Noble Fire facility

4. 10% after 30 days as assurance for any premature integration and/or

warranty issues

Reference Cypress Equipment and design below shown;

Page 7 of 11 Noble Fire RFQ 7 November 2012

Page 8 of 11 Noble Fire RFQ 7 November 2012

Page 9 of 11 Noble Fire RFQ 7 November 2012

Sequence of Operation

Position your pipe and move the CB-1P along the pipe to cut smooth, accurate holes. Position the CW-5 with a step adapter on the fitting and make the contour weld.

Page 10 of 11 Noble Fire RFQ 7 November 2012

Please provide quote ASAP attention to Julian Kalac.

Thank you very much

Page 11 of 11 Noble Fire RFQ 7 November 2012

Sincerely,

Julian Kalac, P.Eng.