Upload
palla-narasimhudu
View
166
Download
9
Tags:
Embed Size (px)
Citation preview
Project
Execution
12-03-2015 1
one step towards project management excellence...
Palla Narasimhudu
12-03-2015 2
Introduction:-
12-03-2015 3
Objectives:-
Identify, Analyze the Risk Factors
Perform Qualitative and Quantitative Analysis
Plan for Risk Mitigation
Monitor and Control throughout the project life cycle
Control of future risks and Pro-activeness
Develop Risk Response strategies and Contingency plans for unexpected
Risk register for further similar projects
Scope :-
12-03-2015 4
Risks in EPC Project:-
12-03-2015 5
Engineering
• Project Feasibility
• Viability
• Technology selection
• Design
• Joint venture
• Geographical conditions
• Funding
Construction
• Utility and Traffic diversion*
• Survey works
• Diaphragm Walling*
• Excavation
• Decking and steel struts*
• Tunnel mining and cross passage*
• Accidents/ Losses of lives
• Non- availability of manpower
• Confined space
• Quality
• Clarity less communication
• Soil condition
• Bad Infrastructure
Procurement
• Underestimate the need
• Quality supplier selection
• Offers fail to meet the needs
• Insufficient funds
Unforeseen
• Sudden collapse of soil
• Heavy rains and floods
• Sudden settlements
• Extreme temperature
Execution
• Delay in land acquisition
• Inexperience project management/ team
• Ineffective decomposition of work
• Regulatory issues
• Failure to forecast
• Design changes
• Stake holder management
• Safety/ Environmental
• Political
• Decision making
• Currency / commodities fluctuation
*varies for different projects
228m
24m19m
228m
24m19m
228m
24m19m
EGMORE NEHRU PARK KMC PACHAIPPA SHENOY
NAGAR
Station Length = 228m + 228m + 228m = 684m
Tunnel Length = 947m + 573m + 898m + 966 = 3384m
22m 22m 24m
Cross Passage = 3nos + 2nos + 3nos + 3nos = 11nos
12-03-20156
Case Study- UAA-04 CMRL Project
Risk identification and action plans- UAA-04
12-03-2015 7
12-03-2015 8
Existing Diverted-1 Diverted-2
Impact- Road diversion and D-Wall Construction
Mitigation-1) Stage wise diversion2) Interchange and inter-displacement of utilities for D-Wall construction
Risk-Space constraint in Utility diversionUtilities running across station
12-03-2015 9
Risk-Space constraint in traffic diversion
Impact-D-Wall ConstructionShaft Handover for TBM launching
Mitigation-1) Stage wise diversion 2) Decking for traffic
12-03-2015 10
UG Metro Station - Plan
20m 20m40m
60m
Risk- Excavation with strut Impact- Possible Delay in shaft handover for TBM launch
Mitigation-1) D-Wall design change without strut2) Modified excavation sequence of 12m max with additional centre opening
12m
Post Risk Analysis-
• Poly-mud level was 1.5mt below the Ground Level
• Due to heavy rain there was contamination of seepage water and polymer properties may reduce which may beinsufficient to withstand the top loose strata
• Continuous rain, rise in ground water level immediately below the guide wall due to the heavy rain, higher than thepoly-mud level
• Vibration due to chiselling
12-03-2015 11
Diaphragm Wall Trench Collapse- P147
Impact-1) Progress hamper for other panels2) Plan for mitigation
Mitigation-1. Bund making over the guide wall and Keeping poly-mud level always
higher than the GW level2. Equal quantity of crusher dust was stoked for immediate risk mitigation.
Immediate risk response-Collapsed trench filled with M5 grade concrete
Bund
Risk factor-Likelihood- 0.25Potential impact- Time- 1 week delay, Cost- Rs 14 Lacs
Risk cost= 14 Lacs x 0.25= 3.5 LacsRisk Time= 1 week x 0.25= 0.25 Week
Post Risk Analysis-
1. Volume losses due to water ingress from the joint locations
2. Under cut/ Over cut while grabbing of D-Wall Panels
3. Honey comb formation due to underwater concreting
4. Chances of soil collapse while concreting affecting quality of concrete
5. Improper fixing of Water bars at joints
12-03-2015 12
Cavity formation at base level of P101 and 102
Impact-1) Sink hole formation on road2) Dangerous occurrence3) Ingress of water and slush inside station
Immediate risk response-Traffic diversionBackfilling near affected areaSink hole filled with concrete40mm Plate laid over top surface of road
12-03-2015 13
Risk factor-Likelihood- 0.25Potential impact- Time- 4 week delay, Cost- Rs 44 LacsRisk cost= 44 Lacs x 0.25= 11 LacsRisk Time= 4 weeks x 0.25= 1 Week
Mitigation-1. Installation of bore-well adjacent to the affected D-Walls2. Lowering the water table with the help of installed bore wells3. Excavating inside the station box near the affected panel up to a depth of 1m4. Steel plate fixing at the affected location5. Micro-concrete grout in the affected panels.
Action taken-
1. Contiguous pile 2. Provision of grouting column around the Contiguous pile
Risk Assessment Matrix
12-03-2015 14
Innovations in Method of Constructions
12-03-2015 15
Utility Diversion
Inter displacement and interchange of Utility diversion Methodology to expedite Diaphragm wall Construction for streamlining with the planned programme.Training of one team to take off the diversion works internally to reduce the contractor dependency risk
Provision of a new opening at Roof for carrying excavation without strutsElimination of struts at Base level by modified design for D-Walls
By making bund over the guide wallKeeping the poly-mud level always higher than the ground water level
Installation of bore-well adjacent to the affected D-Walls and lowering water table to reduce the ingress of water and micro-concrete at 1m at intervals as a control measure to avoid the risk of sink hole
Excavation Sequence
Soil Collapse in D-Walls
D-Wall Cavity formation
Conclusion and Learnings:-
12-03-2015 16
12-03-2015 17