OBJECTIVESteam blowing of MS lines, CRH,HRH,SH,RH,HP & LP bypass pipe lines of turbine is carried out in order to remove welding slag, loose foreign materials, iron pieces, rust etc. from the system, generated during manufacturing, transportation & erection.PRINCIPLE OF STEAM BLOWINGTo ensure that sufficient cleaning forces are applied to the piping, the steam momentum during the steam blow must be equal to or greater than the steam momentum at normal maximum load condition. The Cleaning Force Ratio (CFR) is typically used to evaluate if satisfactory blow conditions are obtained.

PRECONDITIONS FOR STEAM LINE BLOWINGChemical cleaning should be completedSH primary and secondary de-superheater piping and RHs emergency de-superheater piping ready for operationAll permanent piping & temporary piping insulated and supports/hangers are released with cold settingSilencer should be connected at temporary pipe exitSoot blowing for APH should be availableMake up for deaerator made readyMotor Driven BFP with all controls made ready

8) Hydraulic test of the following lines completed:Feed LinesMS, HRH, CRH LinesMS to Aux. PRDS LineAll other auxiliary lines identified for steam blowing 9) Sampling system made ready10) All safety valve disc installed after removing hydro-static plug in drum(sub-critical), superheaters and reheaters11) Adequate communication between control room, boiler and TG area ensured.

12) Flow nozzle, control valves and NRV flaps wherever applicable should be not erected before steam blowing and suitable spool pieces are erected. Strainers in the path should be removed.

13) Required number of Target Plates and holder made available

BASIC TECHNIQUE USEDPUFFING METHOD

PURGING METHOD / CONTINEOUS BLOW METHOD

To give a thermal shock to the contour being purged, to dislodge the scale etc.

Procedure: Raise the boiler pressure to a pre-determined value (40-60 kg/cm2), shut off firing and at the same time open the quick opening valve(EOTV), thus allowing the steam to escape to atm. with high velocity carrying with it the loose debris.PUFFING METHOD

The initial procedure is same as puffing method except shutting off the firing during blowing.

Continuous firing till the completion of steam blowing.

Maintain constant pressure during the blowCONTINEOUS BLOWING METHOD

STAGESSteam blowing done in stagesStage-1(a)- SH, MSL, ESV, temporary lines from ESV to EOTV, EOTV to CRH line, CRH lines upto boiler end with temporary exhaust pipe.

stage 1a end point will be concluded by observing the indents on the target plate.

STAGE- 1(a)

STAGE- 1(b)

SH,MSL, HP bypass inter connection, hand operated valve mounted in place of HP bypass valve and CRH lines upto Boiler end with temporary exhaust piping.

In this stage 6 to 8 blows will be given through HP bypass lines to ensure cleanliness of the limb.

EOTV will be kept closed. Manually Operated Isolation Valves in HP bypass lines will be kept opened fully.

STAGE- 1(b)

STAGE-2(a)

1a plus reheater, HRH lines , Interceptor Valve and temporary pipe.

CRH line along with attemperator shall be welded with reheater before start of stage 2a. LP bypass lines shall be blanked during stage 2a. Stage 2a end point will be concluded by observing the indents on target plates

STAGE- 2(a)

STAGE- 2(b)

2a upto IV + LP bypass lines with temporary exhaust pipe.

Stage 2b blowing will be parallel blow in the path 2a & 2b. LP Bypass blanks shall be removed for stage 2b. 4 blows will be given through L.P. Bypass line to ensure cleanliness of the limbs

STAGE- 2(b)

TARGET PLATE Generally Stainless steel panel Target plate set at the first, sixth, ninth, twelfth purging, thereafter set target for each purging until purging results qualified . Width about 8% of the steam vent tubes inner diameter(ID) and length equal to ID Brinell hardness < 90 Steam velocity 258 m/sec Target plates to be introduced just before steam blowing / light upto be removed soon after blowing is completed.

STEAM BLOWING COMPLETION CRITERIA At least 2 continuous target plates should not have ORIFICE GRANULARITY on the target shall be not larger than 0.8 mm

No impacts with a diameter larger than 1 mm.

Not more than 4 impacts with a diameter larger than 0.5 mm. Not more than 10 impacts with a diameter of 0.2 to 0.5 mm .

Final SH

Final SHESVESVMartyr V/vMartyr V/vHP BypassCRH LineCRH NRVCRH Drain PotRH O/L HdrHRH Line

MSVLP BypassIP SV

OpenCloseMartyr Valve

Steam Blow Line

Temporary LinePre Step # 1 : MS Line Steam Blowing

Final SH

Final SHESVESVMartyr V/vMartyr V/vHP BypassMS LineCRH NRVCRH Drain PotRH O/L HdrHRH Line

MSVMSVLP BypassIP SV

OpenCloseMartyr Valve

Steam Blow Line

Temporary LinePre Step # 1 : MS Line Steam Blowing

LPBP V/ v

Final SH

Final SHESVESVMartyr V/vMartyr V/vHP BypassMS LineCRH LineCRH NRVCRH Drain PotRH O/L HdrHRH Line

MSVMSVLP BypassIP SV

OpenCloseMartyr Valve

Steam Blow Line

Temporary LinePre Step # 2 : HPBP / CRH Line Steam Blowing

Final SH

Final SHESVESVMartyr V/vMartyr V/vHP BypassMS LineCRH LineCRH NRVCRH Drain PotRH O/L HdrHRH Line

MSVMSVLP BypassIP SV

OpenCloseMartyr Valve

Steam Blow Line

Temporary LineMain Step # 1 : HRH Line Steam Blowing

Final SH

Final SHESVESVMartyr V/vMartyr V/vHP BypassMS LineCRH LineCRH NRVCRH Drain PotRH O/L HdrHRH Line

MSVMSVLP BypassIP SV

OpenCloseMartyr Valve

Steam Blow Line

Temporary LineMain Step # 2 :LPBP Line Steam Blowing

THANK YOU