Upload
sara-e-viernum
View
105
Download
0
Embed Size (px)
Citation preview
Avoiding and Minimizing Wetland and Wildlife
Impacts in the Van Loon Bottoms During Powerline
Construction
Sara Viernum, Wildlife Biologist
Project Description• Dairyland Power Cooperative (DPC)
• Not-for-profit Electric Generation and Transmission Cooperative
• Rural Electrification in four states – WI, MN, IA, IL• Headquarter La Crosse, WI
• Regional Touchstone Energy Cooperative Partner
Project Description• Rebuilt 161 kilovolt (kV) Electric Transmission Line
• Transmission line was built in 1950; 65 years old• Need of rebuild
• Old structures• Power and fiber optic outages due to failing structures
Original Structure
Project Description• Rebuilt 161 kV Electric Transmission Line
• Fall 2015• 13 miles total
• 3 miles within Van Loon Bottoms– Black River floodplain in La Crosse County – 0.9 miles USFWS Upper Mississippi National Wildlife and Fish
Refuge – 0.3 miles WDNR Van Loon Wildlife Area– 1.8 miles private lands
Van Loon Bottoms
DPC ROW
USFWS
WDNR
Stantec
Tank
Cre
ek
Black R
iver
Project Description• Rebuilt 161 kV Electric Transmission Line
• Uplands: 69 H-frame steel structures 500-700 feet apart• Wetlands: 28 Y-frame steel structures 600-800 feet apart
• 3-mile Black River Floodplain – 22 Y-frames installed with heavy-lift helicopter– Only 65 feet of existing 80-foot right-of way used
New Y-frames
Impact Concerns• Wetland Impacts
• Soil disturbance and compaction• Species Impacts
• Eastern Massasauga (Sistrurus catenatus)• State endangered; Federally proposed
• Wood Turtle (Glyptemys insculpta) • State threathened
• Loggerhead Shrike (Lanius ludovicianus )• State endangered
• Bell’s Vireo (Vireo belli)• State threatened
• Cerulean Warbler (Setophaga cerulea)• State threatened
©WDNR
Mitigation and Conservation• DPC, AECOM, Stantec, USFWS, and WDNR
• Project-specific Mitigation and Conservation Plan• Incidental Take Permit
• Eastern massasauga• Wood Turtle
• Avoidance• Loggerhead Shrike• Bell’s Vireo• Cerulean Warbler
Mitigation and Conservation• Based on:
• Desktop reviews of recent aerial photography• Discussions with USFWS and WDNR• Habitat observations from previous field visits• Alternative analyses –
• Relocating to CapX Project• Three alternative routes
– Hwy 35 Route– Seven Bridges Route– Galesville Route
» Impacted more residences» Increased line length» Substantially more costly » Greater environmental impacts
Wetland Mitigation•Wetland Impact Minimizations
• Amphibious UTVs• Foot Travel• Helicopters• Temporary Matting
• Around new structures only• No transmission structures placed in waterbodies• Impact monitoring by onsite Stantec Environmental
Inspector, WDNR Biologists, and USFWS Biologists
Wetland Mitigation• Foot Travel
• Minimize soil disturbance and compaction
• Amphibious UTVs• Argo, Hydratrek, and Marsh Master
• Transport personnel and small equipment
• Low ground pressure rubber tracks or tires
• Minimize soil disturbance and compaction– Limited traffic in ROW to single access
paths up to 12ft wide
Wetland Mitigation
Wetland Impact Avoidance• Helicopters
• Smaller Helicopters• Personnel• Small equipment
Two Linemen
Wetland Impact Avoidance• Helicopters
• Heavy-lift Sikorsky S-64 Air Crane • Large equipment
― New and Old Utility Structures― Mats― Hammer and Power Unit
©Erik Daily, La Crosse Tribune
Hammer
Wetland Mitigation• Impacts
• Permanent• Approx. 0.01 acres for new structures
• Temporary• Approx. up to 0.3 acres for new structure matting• Approx. up to 5 acres for access routes
Wetland Mitigation• DPC Long-term Maintenance
• Conduct a ground inspection• Restore all areas of temporary disturbance to pre-existing
or improved habitat conditions• Every 5 years
• Prepare and implement Vegetation Management Work Plans with USFWS and WDNR
Species Conservation• Avoidance
• Loggerhead Shrike• Bell’s Vireo• Cerulean Warbler
• Construction activities conducted after August 15 avoided breeding season
Species Conservation• Onsite Monitoring
• Eastern Massasauga• Wood Turtle
• Up to two onsite Stantec Biologists― Trained to handle and relocate
species to nearby habitat― Hold E/T permits for target species― Equipped with snake tongs― VES ahead of all construction
activities― Remain near crews at all times― Monitored from construction start
September 1 until the start of WDNR designated species inactive season October 31
*note eastern gartersnake hence why I’m free handling it
Species Conservation• Impacts
• No massasaugas or wood turtles observed during monitoring
• DPC Long-term Maintenance• Conduct an updated endangered resources review
within one year
Species Conservation• Additional Wildlife Sightings
• Northern Leopard Frogs• Green Frogs• Blue-spotted Salamanders• Eastern Gartersnakes• Midland Brownsnakes• Northern Watersnakes• Blanding's Turtle• Snapping Turtle • Midland Painted Turtles• Bald Eagles• Mink• Wolf prints• White-tailed Deer
Questions?