23
The webinar will begin shortly… Live Webinar on Getting MNRE Exemptions for Rooftop Solar Plants

MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

Embed Size (px)

Citation preview

Page 1: MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

The webinar will begin shortly…

Live Webinar on Getting MNRE Exemptions

for Rooftop Solar Plants

Page 2: MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

Your Host

HOST

Puneet Singh Jaggi

Director, ezysolare

[email protected]

+91 9998025820

Page 3: MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

Questions

You can type in the Questions and we will take them at

the end of the Webinar

Page 4: MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

Key MNRE Notifications

http://www.mnre.gov.in/solar-mission/jnnsm/introduction-2/

Page 5: MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

Notification for Rooftop Projects

Although, the wordings mention that the policy is applicable only to the plants

not connected to the grid but grid connected solar plants are also accepted.

Page 6: MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

Notification for Rooftop Projects

Minimum Capacity of 100 KW (individual or bundled)

Only Excise Exemption; Not Customs Exemption, but….

Page 7: MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

Notification for Rooftop Projects

Civil work, Earthing material, Lighting material , Lightning Arrestors, Security,

CCTV, Fencing, Gates & misc items are excluded

Page 8: MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

Process for Claiming Exemptions

3 STEP PROCESS

1. Online Registration (7 days)

2. State Nodal Agency Approval (3 - 10 days)

3. MNRE Approval & Exemption Certificates (7 - 30 days)

Page 9: MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

Online Registration

Make an account on MNRE Portal:

http://164.100.194.45/ccm

Page 10: MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

Online Registration

The following details are to be filled while making the account:

• Name of Solar Project CEO: [Please nominate the person who shall be readily

available for signing the material dispatch documents as this activity generally

trickles to last minutes and is a recurring activity]

• Developer Name: [Full Name of the firm]

• Address: [Exact address of the location where solar plant is to be installed]

• Mobile No.: [of the CEO of the Solar project nominated above]

• Email ID: [of the CEO of the Solar project nominated above]

CEO should be of the project owning company and not of the EPC Contractor

Page 11: MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

Online Registration

Fill in online

Total Bill of Materials by

giving Block

and giving Equipment Name,

Quantity, Unit and Specs.

Page 12: MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

Online Registration

Submit the Total Bill of Materials when finalised and wait

for online MNRE Approval

Page 13: MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

Online Registration

Snapshot of Bill of Material approved by MNRE

Page 14: MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

Online Registration

Snapshot of Bill of Material approved by MNRE

3 - 7

Days

Page 15: MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

State Nodal Agency Approval

3 files need to be prepared with the following documents:

• Bill of Materials (once it is approved by MNRE) after signing by the CEO and certified by

Chartered Engineer

• Cover Letter

• Proof of Possession of Roof/Building for Solar Project

• MoA/AoA of the Project Owner Company

• Self Certified Affidavit confirming that the certificates would be used only for the project for

which they are being taken

• CA Certificate for Project Cost

• Power Evacuation Permission / Chief Electrical Inspector Approval (if applicable)

• Single Line Diagram of the Plant

• Layout of the Plant

• Detailed Project Report (DPR)

Page 16: MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

State Nodal Agency Approval

These 3 files are then submitted to the Renewable Energy State Nodal Agency

After Approval:

Nodal Agency keeps 1 file for itself

1 file is given back to the owner

1 file is submitted to MNRE with Cover Letter

Page 17: MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

State Nodal Agency Approval

These 3 files are then submitted to the Renewable Energy State Nodal Agency

After Approval:

Nodal Agency keeps 1 file for itself

1 file is given back to the owner

1 file is submitted to MNRE with Cover Letter

3 - 10

Days

Page 18: MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

MNRE Approval & Exemption Certificates

PART 1: MNRE APPROVAL

On submitting these file to MNRE, MNRE checks and approves the documents.

MNRE may ask for technical clarifications, particularly for cable and structure quantities.

Once approved, you can print the Exemption Certificates

PART 2: EXEMPTION CERTIFICATES

For each of the Exemption Certificate, you need to specify:

Excise Range Division

Commissionerate Excise No.

Page 19: MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

MNRE Approval & Exemption Certificates

Page 20: MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

MNRE Approval & Exemption Certificates

2 copies of the Exemption Certificate and the relevant Purchase Orders are

signed by the Project CEO and certified by Chartered Engineer after which they

are again submitted to MNRE.

Lastly, the certificates are signed and stamped by Director at MNRE.

1 certificate is handed over to the Owner while the other certificate is signed by

the Owner and given back to MNRE as a proof of receiving.

Page 21: MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

MNRE Approval & Exemption Certificates

2 copies of the Exemption Certificate and the relevant Purchase Orders are

signed by the Project CEO and certified by Chartered Engineer after which they

are again submitted to MNRE.

Lastly, the certificates are signed and stamped by Director at MNRE.

1 certificate is handed over to the Owner while the other certificate is signed by

the Owner and given back to MNRE as a proof of receiving.

7 - 30

Days

Page 22: MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

Advantage EZYSOLARE!

Ezysolare.com provides

FREE EXCISE EXEMPTION GUIDANCE FOR

EQUIPMENT PURCHASED THROUGH SOLARKART.

So call us to book your orders for anything solar - modules, inverters, cables,

structures, earthing and more at negotiated prices delivered at your doorstep.

www.SolarKart.ezysolare.com

Page 23: MNRE Exemption procedure for Rooftop Solar Projects: Webinar Presentation

That’s all folks…

Mohit Agarwal: +91 9925345121

[email protected]

Puneet Singh Jaggi: +91 9998025820

[email protected]

SolarKart