12
OR126/Tom McCall OR126/Tom McCall (Prineville) Budget/ Layout August 2, 2016

OR126/ Tom McCall (Prineville) Budget / Layout

Embed Size (px)

Citation preview

Page 1: OR126/ Tom McCall (Prineville) Budget / Layout

OR126/Tom McCall

OR126/Tom McCall

(Prineville)Budget/Layout

August 2, 2016

Page 2: OR126/ Tom McCall (Prineville) Budget / Layout

Budget

TOTAL Budget

Region 4 (ODOT)

Enhance (ODOT)

Enhance Match

(ODOT)

City of Prineville (cash) *

Crook County (cash) **

Crook County

(“In Kind”)

$4,500,000 $500,000 $2,649,009 $303,191 $283,300 $180,000 $584,500

OR126@Tom McCall (Prineville) Project

Budget as of August 2, 2016

Page 3: OR126/ Tom McCall (Prineville) Budget / Layout

Proposed Project Layout

Page 4: OR126/ Tom McCall (Prineville) Budget / Layout
Page 5: OR126/ Tom McCall (Prineville) Budget / Layout
Page 6: OR126/ Tom McCall (Prineville) Budget / Layout

Roundabout Field Testing (Rodeo)

Deschutes County Fairgrounds

August 17 & 18, 2016

Page 7: OR126/ Tom McCall (Prineville) Budget / Layout
Page 8: OR126/ Tom McCall (Prineville) Budget / Layout
Page 9: OR126/ Tom McCall (Prineville) Budget / Layout

Central Oregon TruckingTractor with 53’ flat-bed trailer, Total Length=73’

Page 10: OR126/ Tom McCall (Prineville) Budget / Layout

Art Davis TowingClass C semi tow truck (37’ long) with Semi- and Trailer in towTotal Length=106’

Page 11: OR126/ Tom McCall (Prineville) Budget / Layout

Redmond Heavy HaulTractor with 110’ booster trailerTotal Length=130’

Page 12: OR126/ Tom McCall (Prineville) Budget / Layout

Project Schedule

OR126 Corridor Plan (2012)

Prineville TSP (2012/13)

City/County Requests STIP Funding (2012)

Project Design/Stakeholder Outreach (2015/16)

City and Freight Concurrence (2016)

Construction 2017/18

DesignConcepts

Design Refinement