14
PHASE II OPEN HOUSE June 9, 2015 ; June, 16 2015

Silver Lake Reservoir Complex Storage Replacement; Open House Event Presentation

Embed Size (px)

Citation preview

PHASE II OPEN HOUSEJune 9, 2015 ; June, 16 2015

AGENDA

• Welcome and Introductions• WOL-JV Remarks• LADWP Greetings• Phase II Presentation• Contractor Bonding• Bid Package Q&A Discussion• Networking

DAN RAKERS/VINCE QUINONES | Project Director, WOL-JV

• Welcome • Introductions • Management Team• Community Based Organizations• Attendees

MARK TURNER | Senior VP, Webcor

• Introduction of WOL-JV Partners• Webcor• Obayashi• Lyles

• Project Overview

STEPHAN TUCKER | Project and Construction Management, LADWP

• LADWP Greetings• Outreach Goals and Commitment to

Project

DAN RAKERS/VINCE QUINONES | Project Director, WOL-JV

• Phase II Presentation• Project Scope• Project Details• Prequalification Packages• Subcontract Agreement• CCIP Manual• Additional Statement and Federal Requirements• PLA

BID PACKAGE A • Sub Drains, Onsite Piping, RSC1A West

• Excavation/Installation/Backfill 3,000 LF of 78” WSP• Excavation/ Installation/Backfill 102 LF of 72” Overflow WSP• 13,334 LF of 8”subdrain pipe• 2,900 LF of 6” wall/roof drains• 3,121 LF of 12” Collector system, including manholes and

associated miscellaneous metal items • Survey Services

• Fee Based Proposal and Award • Field crew rate and office engineering rate to be included

• Geomembrane Liner & Miradrain System• Placement of 550,000 SF of BGM & 330,000 SF of Miradrain

TENTATIVE DATES | Package A

July 6th, 2015- Prequalification RFQ Release

August 5th, 2015- Prequalification RFQ Deadline

August 14th, 2015- RFP Release

September 25th, 2015- RFP Deadline

BID PACKAGE B • Concrete

• 90,000 CY Reservoir & Inlet Vault • Chemical Mixing System• Miscellaneous Metals for reservoir structure, and inlet vault

• Site Earthwork • Reservoir Backfill• Topsoil Placement• Grading for Site Concrete

• Electrical• Installation of electrical equipment • Construction of duct banks• Installation of power and control wiring• Function test/Check out of all Project Electrical systems

BID PACKAGE B • HVAC

• Ventilation systems at Inlet Vault and Manholes• Site Concrete

• Access Roads, Crane Pads, V Gutters, Curbs • Painting

• Finish coating of all exposed piping, valves and equipment, including items within buildings and vaults

TENTATIVE DATES | Package B

July 6th, 2015- Prequalification RFQ Release

August 5th, 2015- Prequalification RFQ Deadline

November, 2015- RFP Release

December, 2015- RFP Deadline

KRISTINE MENDEZ | Director, Western Region Surety, AON Construction Services Group

• Contractor Bonding

NEW WEBSITE | Silverlake-wol.com