Environmental Sustainability Considerations in Asset Management and Planning Glen Hadfield Manager, Asset Systems & Sustainability Western Sydney Local Health District 1

Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Embed Size (px)

DESCRIPTION

Glen Hadfield, Manager Asset Systems & Sustainability, WSLHD, Westmead Hospital delivered this presentation at the 15th Annual Health Congress 2014. This event brings together thought leaders and leading practitioners from across the Australian health system to consider the challenges, implications and future directions for health reform. For more information, please visit http://www.informa.com.au/annualhealthcongress14

Citation preview

Page 1: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Environmental Sustainability Considerations in Asset Management and Planning

Glen Hadfield Manager, Asset Systems & Sustainability

Western Sydney Local Health District

1

Page 2: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Introduction

• Improving Energy Efficiency in existing facilities (Case Study Westmead Hospital)

– The Environmental Footprint of Westmead Hospital

– Improving Energy Efficiency of major plant

• Feasibility of Embedded Solar Generation in Hospitals

• Empowering staff to reduce office consumption

• Planning for Sustainability in new Healthcare facilities

2

Page 3: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Improving Energy Efficiency in existing facilities

Westmead Hospital

Environmental Footprint

2009-10 Pre-Project Baseline

2012-13 2013-14 forecast

Change from Baseline

Electricity (MWhrs) 52,093 48,570 48,000 -8%

Electricity Costs $4,761,152 $5,911,628 $5,700,000 20%

Gas (Gigajoules) 144,122 146,100 130,000 -10%

Gas Costs $936,125 $1,260,962 $1,350,000 44%

TOTAL Costs $5,697,277 $7,172,590 $7,050,000 24%

CO2e tonnes 58,056 54,360 53,439 -8%

Equivalent Cars 12,901 12,080 11,875 -8%

3

1st January 2014 – 24th March 2014 13% drop in electricity

despite record heat.

Page 4: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Improving Energy Efficiency in existing facilities

Case Study – Westmead Hospital

Energy Efficiency Upgrades 2012- 2014

• Chiller Upgrade target : – 8% or $500,000 p.a.

• Lighting Upgrade target savings: – 8% or $500,000 p.a.

TOTAL $1,000,000 p.a.

4

Page 5: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Improving Energy Efficiency in existing facilities

Westmead Hospital Lighting & Controls Upgrade (Contractor – Total Energy Solutions)

– Scope • 12,798 light fittings upgraded

• Dimmable LED downlights in Lecture Theatres saving up to 80% electricity.

• Phillips Dynalite Lighting Control – 4,000 lights controlled by occupancy sensors – savings yet to be verified

but estimated at > 25% of consumption of the lights controlled.

– Controls mainly Corridor lights

• Upgrade of emergency lighting (EXIT lights)

– Capital Cost $3,728,765

– Long life lamps (75,000 hours) or 8 years

– Completed January 2014

5

Page 6: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Improving Energy Efficiency in existing facilities

Westmead Hospital

Lighting Controls Upgrade • Control of 4000 Corridor lights

3 different schedules identified – Patient care areas

– Public areas

– Office areas (8am – 6pm)

6

Page 7: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Improving Energy Efficiency in existing facilities

Westmead Hospital Lighting & Controls Upgrade

Outcome

• Lighting Upgrade Savings – 3317 megawatt hours saving (calculation using measurement &

deemed operating hours

– $480,000 p.a.

• Lighting controls upgrade – Estimated savings ~ $50,000 p.a. to be verified

7

Page 8: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Improving Energy Efficiency in existing facilities

Air Conditioning Plant Upgrade Contractor - Dalkia

– 2 x 4000kW high efficient TRANE chillers

• Supplies 90% of the air conditioning (cooling) for Westmead Hospital

• 30% savings on electricity

– 10 new energy efficient pumps installed with variable speed drives

– 2 new cooling towers installed

– Total Capital $2.2 million

– Completed November 2012

– Fine tuning of controls ongoing

35 year old CARRIER replaced

New variable flow TRANE chillers

8

Page 9: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Improving Energy Efficiency in existing facilities

Air Conditioning Plant Upgrade Outcome

• Chiller Upgrade – verified 2580 megawatt hours p.a. or $375,000 p.a. savings

• Automatic controls and pumps upgrade – in process of fine tuned but likely to be > $140,000 p.a.

9

Page 10: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Feasibility of Embedded Solar Generation in Hospitals

Future Projects Solar Photovoltaic

• Pilot Project - 10kW Photovoltaic Installation – to supply Westmead Education Conference Centre ~ saving verified $2,200 p.a.

• Today’s cost of 10kW system ~ $18,000

• Payback ~ 9 years

10

Page 11: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Feasibility of Embedded Solar Generation in Hospitals

Solar Photovoltaics

Opportunity for hospitals

• Peak output of Solar PV coincident with Peak Demand of Hospitals

• Lots of roof space

• Can utilise all in house not dependent on feed-in tariff

Source: http://reneweconomy.com.au/2014/will-iea-and-governments-

be-the-last-to-discover-solar-pv-revolution-80280

11

Page 12: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Feasibility of Embedded Solar Generation in Hospitals

Solar Photovoltaics Opportunity for hospitals

• Ideal of Car Parks and covered walkways.

• Can be used to mitigate additional electrical infrastructure costs by reducing maximum demand (e.g. may be able to forego upgrade of substations and cables.)

Source: http://www.solarselections.co.uk/blog/solar-panels-and-electric-cars-

the-next-legtonenergy

12

Page 13: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Feasibility of Embedded Solar Generation in Hospitals

Business Case for Westmead Hospital

1000 kW Solar PV system • Capital ~ $1.8m

• Output ~ 1,300 megawatt hours or 2.7% of site

• REC Certificates generated 1200 p.a.

• Income

• Savings Grid Electricity ~ $195,000 p.a.

• Value of RECs @ 30ea = $36,000

• Total $231,000 p.a.

• Simple Payback ~ 8 years

• 3,800 panels covering 6,100sqm or ~ 10% of gross area of roof space.

13

Page 14: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Feasibility of Embedded Solar Generation in Hospitals?

Risks Renewable Energy Certificates

• Large Generation Certificate (LGCs) price falling due to uncertainty around Liberal Government’s review of the Renewable Energy Target.

14

Page 15: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Empowering Staff to Reduce Office Consumption

Empowering staff to reduce office consumption •Estimated Office consumption > $1 million per year (20%)

•Inspiring staff to save Office Energy – 3 determining factors

– Identify Energy Champion in the department to drive efficiency.

– Feedback information about how we contribution to consumption

• How much do computers, the office fridge, photocopiers, ice machines, Zip urns, and microwaves consume. Do your office lights remain on when unoccupied ?

• Contribution of equipment standby power.

– Simple Tool(s) to equip staff to make a difference

15

“Everything should be made a simple as possible but no simpler” – Albert Einstein.

Page 16: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Empowering Staff to Reduce Office Consumption

Empowering staff to reduce office consumption • The “plugwise” solution.

– Controls everything in your office at the plug level

– Provides daily and hourly consumption information of your site

– Enables you to schedule equipment on/off

– Lighting can be controlled by sensors.

16

Page 17: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Empowering Staff to Reduce Office Consumption

Empowering staff to reduce office consumption

• The “Plugwise” solution. – Pilot Project – Westmead Hospital Asset Services. Project

installed 15 Oct 2013

– 81 modules, on 54 Appliances

– Lighting & Appliance Control with wireless intelligent switching, no rewiring

– Minimal interruption during installation

– Take control of wasted electricity and reduce energy consumption

– Increase awareness and change behavior

– Full control and Visibility and Easy Self Management

– Payback around 3-6 years depending on scale of project and existing tariff rates

17

Page 18: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Empowering Staff to Reduce Office Consumption - 2 weeks Lighting WITHOUT appliance control

18

Light being left on, no control

Page 19: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Empowering Staff to Reduce Office Consumption - 2 weeks lighting with appliance control

Lights OFF when NO occupation turning off more frequently

Page 20: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Base Line 220 watts – Can be reduced

significantly

System left on when people have gone home – Can be reduced significantly

Empowering Staff to Reduce Office Consumption

- without appliance control - Aircon left on for extended periods

Page 21: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Standby power removed, controlled with a Schedule

Empowering Staff to Reduce Office ConsumptionSchedules Implemented to AC units

Page 22: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Schedule Implemented

Empowering Staff to Reduce Office Consumption

-Actual Saving after schedules implemented

Page 23: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Baseline as high as 308 watts over a weekend

Empowering Staff to Reduce Office Consumption

-Copiers always on with very high standby power

Page 24: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Empowering Staff to Reduce Office Consumption

-Copiers with Actual Schedules

Page 25: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Planning Sustainability into New Facilities

•How to improve the uptake of Sustainable Initiatives in new facilities

– New hospital facilities mandatory 4 star rating

• Currently nominal only – no need to undergo independent verification.

– Project Management approach ignores legacy issues of existing infrastructure.

• Continuing dichotomy between Capital and Recurrent.

• Legacy issues of existing infrastructure considered responsibility of LHDs to fund out of recurrent budget.

– Decision Makers need to enforce Sustainability into the agenda at very early stage

• Increased investment in most energy efficient plant.

• Quarantine capital for installing embedded renewable generation.

25

Page 26: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Planning Sustainability in New Facilities

New Development Case Study – Mt Druitt Hospital

• Mt Druitt Hospital – chronic air conditioning shortage in summer months – need to main Chiller plant.

• Business case focused on project outcomes, not whole of facility outcomes.

• Instead of upgrading central chiller plant, packaged air conditioning units were installed to extensions in lieu of upgrading central plant.

• Package units installed immediately above central chiller plant.

• Upgrading central plant should have been identified at Project Definition Phase

26

Page 27: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Planning Sustainability in New Facilities

27

•Lessons learnt – New Capital Projects offer a one in 40 year opportunity to get the

building energy efficient

– Retrofitting energy efficiency is both very expensive and logistically far more complex.

– Need for holistic approach that uses business case covering long term operational costs of whole building

– Need to be more specific in defining the energy efficient technologies to be installed in new projects.

– Good space management and operational efficiency have major impact on energy and water efficiency.

Page 28: Glen Hadfield, Westmead Hospital - Environmental Sustainability Considerations in Asset Management and Planning

Conclusion

Questions ??

Glen Hadfield, B.E. MBA, CPEng, MIHEA

Manager, Asset Systems & Sustainability

Western Sydney Local Health District

Ph 02 9845 8751

Email : [email protected]