Peer Dalland Dalland Associates Pty Ltd

1

ADR OPTIONS ON AUSTRALIAN CONSTRUCTION CONTRACTS

The Case for Single Person Dispute Boards

withPeer Dalland

LEADR&IAMA Forum Wednesday 19th August 2015 Sydney

LEADR&IAMA Forum 19 AUGUST 2015

Page 2: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

2

General Conditions of Contract

• The building and construction industry in Australia use a large number of different standard forms of contract.

• These standard forms are often modified extensively, resulting in the interpretation of standard terms and phrases becoming uncertain.

• Bespoke General Conditions of Contract used in many industries and by some Principals generally transfer all or most risks to the Contractor.

LEADR&IAMA Forum 19 AUGUST 2015

Page 3: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

3

“standard forms of contract”

• How standard forms of contract are used and on what type of project, has been the subject of several studies and reports over recent years.

• Some of the more recent reports provide enlightened reading for anybody involved in the drafting and administration of construction contracts in Australia:

LEADR&IAMA Forum 19 AUGUST 2015

Page 4: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

4

Reports on Construction Contracts in Australia

1. Standard Forms of Contract in the Australian Construction

Industry Research Report by Melbourne Law School, chaired by Professor John Starkey. June 2014

2. Scope for Improvements 2014 by Ashurst Australia, Australia Constructors Association and Infrastructure Partnerships Australia

3. Standard Form of Contracting; the Role for FIDIC Contracts Domestically and Internationally by Toby Shnookal and Dr. Donald Charrett – 2010

4. Guide to Global Construction Dispute Resolution published by Clyde & Co 2015

LEADR&IAMA Forum 19 AUGUST 2015

Page 5: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

5

FINDINGS

LEADR&IAMA Forum 19 AUGUST 2015

• The consensus from all the reports indicates that over 60% of projects use standard forms

• 60-80% of these are amended • Amendments mostly involved changes to

the risk allocation, • which in turn is believed to lead to

increased cost and more claims (1).

Page 6: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

6

Scope for Improvement • The Ashurst/ACA report observes that:

• “The trouble with many of the standard forms of contracts are that they are quite old now and so heavily amended in most projects that they are not serving the purpose they were originally intended for. They do not allow contractors to quickly and efficiently appreciate the risk profile for any specific project.” (2)

LEADR&IAMA Forum 19 AUGUST 2015

Page 7: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

7

History of Australian standard General Conditions of Contract

• The first standard general conditions of contract in Australia was the CA24 published by the Institution of Engineers in 1952.

• Was published as AS 2124 in 1978 and in 1992 took JWP publication NO DISPUTE into account

• AS 4000 published in 1997 was intended to replace AS 2124

• AS 11000 draft 2015 (revision of AS 2124 – 1992 and AS 4000 – 1997)

LEADR&IAMA Forum 19 AUGUST 2015

Page 8: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

8

Objectives of Australian General Conditions of Contract

• Defines the responsibilities and obligations of the Parties to the Contract.

• Provide rules and guidelines for the administration and execution of the works under the contract.

• Defines risk allocation, insurance provisions, payment regimes etc.

• Facilitates day to day administration and execution.• Provides rules and procedures for disputes

resolution.

LEADR&IAMA Forum 19 AUGUST 2015

Page 9: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

9

PHILOSOPHY

• The Australian General Conditions of Contract mostly reflect a different, more old fashioned philosophy, than do the General Conditions of Contract used internationally such as the FIDIC General Conditions of Contract and the Engineering and Construction Contracts published by the Institution of Civil Engineers ICE) in the UK.

LEADR&IAMA Forum 19 AUGUST 2015

Page 10: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

10

Engineering and Construction Contract (ECC)

• In their introduction to ECC contracts, the ICE states that

• “The ECC is the first of what could be termed a ‘modern contract’ in that it seeks to holistically align the setting up of a contract to match business needs as opposed to writing a contract that merely administers construction events.”

LEADR&IAMA Forum 19 AUGUST 2015

Page 11: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

11

Ethos of ECC

• “The whole ethos of the ECC, or indeed the NEC suite generally is one of simplicity of language and clarity of requirement. It is important that roles and responsibilities are equally clear in definition and ownership”

LEADR&IAMA Forum 19 AUGUST 2015

Page 12: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

12

Philosophy of AS 11000

• The draft AS 11000 attempts to bridge the gap and provides inter alia that the “Overriding obligations” of the Contract is one of “Good faith”

LEADR&IAMA Forum 19 AUGUST 2015

Page 13: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

13

Mutual trust, cooperation and good faith

• “The Principal and Contractor each agree:(a) to act reasonably in a spirit of mutual

trust and cooperation, and generally in good faith towards each other; and

(b) that such action shall not derogate from their obligations to comply with the Contract.”

LEADR&IAMA Forum 19 AUGUST 2015

Page 14: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

14

Contra proferentum

• It will be interesting to see how the obligations in AS 11000 will sit with the recent trend in some Common Law jurisdictions to amend Contracts to exclude the doctrine of “contra proferentum”.

• The risks will then become unidentifiable and very difficult to price on any project, with the intention clearly to give the Principal an “unfair” advantage.

• This doctrine is embedded in Civil Codes around the world, were a contractual clause to exclude it from a Contract would be void.

LEADR&IAMA Forum 19 AUGUST 2015

Page 15: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

15

What happened to “No Dispute”

• Where are we heading in Australia with these trends.• The JWP “No Dispute” published in May 1990 by the

NPWC (National Public Works Conference) and NBCC (National Building and Construction Council) was for a while the new bible for construction contracts.

• It also advocated mutual understanding and trust between the parties as an objective in the dispute resolution process.

LEADR&IAMA Forum 19 AUGUST 2015

Page 16: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

16

“NO DISPUTE”Summary of guidelines for Dispute Resolution (1990)

• Encourage, facilitate and expedite genuine negotiation• Avoid legal representation• Avoid arbitration and litigation processes• Specify compulsory conferences of senior management of

both parties before embarking on formal third party processes• Concentration on cost mitigation of the problem area, rather

than procrastination about negotiating and resolving the dispute.

• Be cost-conscious, contemplating end financial implications of resolution processes once genuine negotiation have failed

• Encourage use of alternative dispute resolution processes

LEADR&IAMA Forum 19 AUGUST 2015

Page 17: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

17

25 years later

• Do we use these guidelines today?• We still have excessive legal representation• Do government bodies adhere to the guidelines

and principles of “No Dispute” – no reference in GC21, although conferences of senior management has been retained

• Non-government contracts seem to be heading back to the pre-”No Dispute” regimes, by amending the standard forms of contract.

LEADR&IAMA Forum 19 AUGUST 2015

Page 18: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

18

EXISTING FORMS

• At this point in time we seem to be stuck with the old favorites;

• AS 2124• As 4000• GC21 Edition 2

LEADR&IAMA Forum 19 AUGUST 2015

Page 19: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

19

DISPUTE RESOLUTION PROCESSES COMMONLY USED IN AUSTRALIAN CONSTRUCTION CONTRACTS

• Arbitration• Expert Determination• Dispute Boards – 3 member boards• Litigation

LEADR&IAMA Forum 19 AUGUST 2015

Page 20: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

20

LESS USED OPTIONS

• Single Person Dispute Board (SDBM)• Dispute Advisory Services (Hong Kong model)• Facilitation – similar to above, but can be

structured to suit a particular project.

• In addition there is also SOP adjudication under various state legislations.

LEADR&IAMA Forum 19 AUGUST 2015

Page 21: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

21

MEDIATION

• This is often included as the first step in a tiered approach to dispute resolution on some contracts

LEADR&IAMA Forum 19 AUGUST 2015

Page 22: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

22

ARBITRATION

• Under current procedures this can be long-winded and costly, but it will eventually deliver a fair and robust decision in most construction disputes.

• IAMA developed procedures for a fast track arbitration process

LEADR&IAMA Forum 19 AUGUST 2015

Page 23: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

23

EXPERT DETERMINATION

• A well-known ADR process in Australia - entrenched in some government forms of contract, such as the GC21 used in NSW, for disputes up to a value of $ 500,000

• Depending on the Rules, it can be a relatively quick process and the outcome will generally be determined on written submissions only.

• The Expert Determination will normally give reasons and will be contractually “Final and Binding” with no recourse to litigation or arbitration.

LEADR&IAMA Forum 19 AUGUST 2015

Page 24: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

24

DISPUTE BOARDS

• THE AUSTRALIAN MODEL • Normally 3 person Dispute Board based on

DRBF procedures• Delivers non binding recommendations

LEADR&IAMA Forum 19 AUGUST 2015

Page 25: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

25

SINGLE PERSON DISPUTE BOARD (SDBM)

• FIDIC Single Dispute Board Member provisions apply to projects of all sizes

• I introduced SDBM provisions on an AS 4000 contract in NSW in 2003 with an initial value of 10mill.

• I also successfully argued for the establishment of a SDBM on a major road project in Afghanistan with a Bid value of around USD 450mill and several hundred km in length.

LEADR&IAMA Forum 19 AUGUST 2015

Page 26: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

26

DISPUTE ADVISOR/FACILITATOR

• Similar to a Single Person Dispute Board, but is not determinative. The DRA is a one-person standing board set up in the conventional manner at the commencement of a construction project.

• In all cases, the DRA is appointed by agreement between the owner and the contractor immediately after the construction contract is signed. The DRA fees are paid equally by the parties.

LEADR&IAMA Forum 19 AUGUST 2015

Page 27: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

27

STATUTORY ADJUDICATION PROCESSES

• Very time efficient, but can deliver “rough justice”

• SOP adjudications are only intended to be binding in the interim

LEADR&IAMA Forum 19 AUGUST 2015

Page 28: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

28

AS 4000 dispute resolution provisions

Standard form of contract:Conference and Arbitration

LEADR&IAMA Forum 19 AUGUST 2015

Page 29: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

29

GC21 EDITION 2

• Issue Resolution by Senior Executives• Referral to Expert Determination; <$500,000• Litigation

LEADR&IAMA Forum 19 AUGUST 2015

Page 30: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

30

AS 11000 (draft) dispute resolution provisions

Various options are listed to be selected by the user, normally the Principal prior to calling tenders

Conference and ArbitrationConference Expert Determination LitigationContract Facilitation Dispute Resolution Board

LEADR&IAMA Forum 19 AUGUST 2015

Page 31: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

31

FIDIC

• Claims procedures• Engineer’s determination• Referral of dispute to DAB• Dispute Adjudication Board (mandatory)

LEADR&IAMA Forum 19 AUGUST 2015

Page 32: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

32

TIME COMPARISON CLAIM ASSESSMENT

• AS 11000 – • Superintendent’s decision – 90 days

• AS 4000• Superintendent’s decision – 56 days

• GC21 EDITION 2• Principal’s decision - 56 days

• FIDIC• Engineer’s sc.3.5 determination – 84 days

LEADR&IAMA Forum 19 AUGUST 2015

Page 33: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

33

TIME COMPARISON REFERRAL/OBTAIN ADR DECISION

• AS 11000 – • ADR referral only - 110 days

Decision/award plus plus• AS 4000• Referral only to Arbitration - 126 days

Award; anybody’s guess• GC21 EDITION 2• Expert Determination - 215 days

• FIDIC• Dispute Board Decision - 140 - 168 days

LEADR&IAMA Forum 19 AUGUST 2015

Page 34: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

34

SUMMARY

• The claims procedures under standard forms of contract take too long

• The dispute referrals take too long• Determination of disputes take too long• Current processes do not work easily with SOP

LEADR&IAMA Forum 19 AUGUST 2015

Page 35: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

35

Suggested improvements

• Determinative Dispute Resolution by Single Person DB; 3 person DB on larger more complex projects appointed at the start of the project

• Shorten claims procedures – GC21 and FIDIC both identify an issue or dispute within 84 days. AS 11000 takes 110 days – needs to be shorter

LEADR&IAMA Forum 19 AUGUST 2015

Page 36: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

36

AS 4000

• AS 4000 can easily be amended to provide for Single Person Dispute Boards

• Contain provisions which are familiar to most Principals, Contractors and Supervision Engineers in Australia.

• FIDIC provides alternative well established standard forms of contract (refer 3)

LEADR&IAMA Forum 19 AUGUST 2015

Page 37: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

37

Fast dispute resolution processes

• Determinations within 56 – 84 days must be binding and “final and binding” if Notice of Dissatisfaction has not been issued within a certain time (28 days is popular)

• Total time therefore between 140 days and 168 days (calendar days)

• Remedy must be arbitration, which should be referred within a minimum and maximum time period.

LEADR&IAMA Forum 19 AUGUST 2015

Page 38: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

38

CONTRACTUAL ADJUDICATION

• Contractual Adjudication is likely to avoid SOP Adjudication Applications, as its decisions can review and override the SOP Determinations

• DB Tripartite Agreements provided for in the Contract, will stand outside the Contract if the Contract is terminated and should be able to determine issues arising from termination.

LEADR&IAMA Forum 19 AUGUST 2015

Page 39: ADR options on construction contracts

Peer Dalland Dalland Associates Pty Ltd

39

THANK YOU

LEADR&IAMA Forum 19 AUGUST 2015