Upload
dentons
View
2.572
Download
2
Embed Size (px)
Citation preview
Current Permitting Processes
and Challenges for New Mines
and Re-Opening Old Mines
Water Management for Mining Summit 2014
Bernard J. Roth
Partner
May 15, 2014
Dentons Canada LLP
Agenda - Permits and Approvals to Cover
May 15, 2014 Dentons Canada LLP 2
• Permit under the Mines Act in BC
• Exploration and Small Mines
• Notice of Work
• Multi-year area-based (MYAB) permitting
• Major Mines Permit
• BC Environmental Assessment Certificate
• Canadian Environmental Assessment
• Fisheries Act Approval
• Navigable Protection Act Approval
Mines Act Permit Requirement
May 15, 2014 Dentons Canada LLP 3
• Section 10(1) of the Mines Act
• Must have a permit before starting any work in, on or about a mine
• Permit is issued by the Chief Inspector
• The application must include
• A plan of the proposed work
• A program for conservation of cultural heritage resources
• A program for protection and reclamation of the land, watercourses and cultural heritage
• Exemptions are possible (s. 10(1.1) and (2))
Mines Act Permit - Notice of Work (NoW)
May 15, 2014 Dentons Canada LLP 4
• Intended for coal or mineral exploration programs and for approvals of
placer mining, or sand and gravel pits and quarries
• The permit must be obtained before any mechanized work can occur
• Application must include the following regarding water management:
• Plan(s) outlining the details of the proposed work and a program for the
protection and reclamation of the land, watercourses and cultural heritage
resources which may be affected by the proposed activities
• Information about the present state of the land
• Description and estimated cost of reclamation program for each activity
Deemed Authorizations and Mines Act Permit
Exemptions
May 15, 2014 Dentons Canada LLP 5
• The following are deemed authorized activities:
• If a proponent holds an exploration permit, induced polarization surveys using
exposed electrodes
• For an operating mine, additional exploration drill programs and IP surveys in
the permitted area of disturbance
• Extension of exploration activities for up to two years
• Notification to the Ministry is required
Multi-Year Area Based Mines Act Permits
May 15, 2014 Dentons Canada LLP 6
• Authorizes exploration activities for up to 5 years in an area (s. 10(3) of
Mines Act)
• Provides flexibility to proponent to adjust work based on field results and
market conditions
• First Nations can review information for an area in one application, rather
than several applications
• Streamlines administrative process
• Follows the same approval process as NoW
• Engineering, water and archaeological studies may be needed during
review process
• Proponent submits annual updates to MMRD
Mines Act Permits for Major Mines
May 15, 2014 Dentons Canada LLP 7
• A detailed ‘Mine Plan and Reclamation Program’ must be submitted and
must include the following regarding water management:
• Design, construction, operation and mine closure details that consider the
safety of the public, mine workers, and the protection of the environment;
• A program for the protection and reclamation of the land and watercourses
during the construction and operational phases of the mining operation;
• A conceptual final reclamation plan for the closure or abandonment of the
mining operation;
• An estimate of the annual cost of outstanding reclamation obligations over the
planned life of the mine including the cost of long-term monitoring and
abatement; and
• Any other relevant information that may be required by an Inspector.
BC Environmental Assessment
May 15, 2014 Dentons Canada LLP 8
• An environmental assessment will be required if the project meets the
criteria for a reviewable project
• An application for a mine permit and environmental assessment may be
submitted concurrently, but an environmental assessment certificate
must be obtained before a mine permit can be issued
BC Environmental Assessment – Reviewable Projects
May 15, 2014 Dentons Canada LLP 9
Project Category –
Column 1
Criteria for a New Project – Column 2 Criteria for Modification of Existing Project –
Column 3
Coal Mines A new mine facility that, during operation, will
have a production capacity of > 250 000
tonnes/year of clean coal or raw coal or a
combination of both clean coal and raw coal.
The facility meets the criteria in Column 2 and the
modification will result in the disturbance of
(i) at least 750 hectares of land that was not
previously permitted for disturbance, or
(ii) an area of land that was not previously permitted
for disturbance and that is at least 50% of the area of
land that was previously permitted for disturbance at
the existing facility.
Mineral Mines A new mine facility that, during operations, will
have a production capacity of > 75 000
tonnes/year of mineral ore.
The facility meets the criteria in Column 2 and the
modification will result in the disturbance of
(i) at least 750 hectares of land that was not
previously permitted for disturbance, or
(ii) an area of land that was not previously permitted
for disturbance and that is at least 50% of the area of
land that was previously permitted for disturbance at
the existing facility.
Sand and Gravel Pits A new pit facility that will have a production
capacity of
(a) > 500 000 tonnes/year of excavated sand or
gravel or both sand and gravel during at least
one year of its operation, or
(b) over a period of < 4 years of operation,
> 1 000000 tonnes of excavated sand or gravel
or both sand and gravel.
The facility meets the criteria in Column 2 and the
modification of the existing pit facility will result in the
disturbance of an area of land that was not previously
permitted for disturbance and that is at least 35% of
the area of land that was previously permitted for
disturbance at the existing facility.
BC Environmental Assessment – Reviewable Projects - 2
May 15, 2014 Dentons Canada LLP 10
Project Category –
Column 1
Criteria for a New Project – Column 2 Criteria for Modification of Existing Project –
Column 3
Placer Mineral Mines A new mine facility that, during operations,
will have a production capacity of > 500 000
tonnes/year of pay-dirt.
The facility meets the criteria in Column 2 and the
modification of the existing pit facility will result in the
disturbance of an area of land that was not previously
permitted for disturbance and that is at least 35% of the
area of land that was previously permitted for disturbance
at the existing facility.
Construction Stone
and Industrial Mineral
Quarries
A new quarry facility or other operation that
(a) involves the removal of construction
stone or industrial minerals or both,
(b) is regulated as a mine under the Mines
Act, and
(c) during operations, will have a production
capacity of > 250 000 tonnes/year of
quarried product.
The facility meets the criteria in Column 2 and the
modification will result in the disturbance of
(i) at least 750 hectares of land that was not previously
permitted for disturbance, or
(ii) an area of land that was not previously permitted for
disturbance and that is at least 50% of the area of land
that was previously permitted for disturbance at the
existing facility.
Off-shore Mines
A new off-shore mine facility. The facility meets the criteria in Column 2 and the
executive director has determined that the modification
has the potential to result in a significant adverse
environmental, economic, social, heritage or health effect.
BC Environmental Assessment Pre-Application Process
May 15, 2014 Dentons Canada LLP 11
Proponent initiates exploration and
consultation
Proponent initiates baseline
environmental studies
Proponent submits project description
to BC EAO
BC EAO determines whether an environmental
assessment is triggered
Proponent submits draft application
information requirements (AIR)
Public review period for draft AIR
BC EAO issues AIR
BC Environmental Assessment Application Process
May 15, 2014 Dentons Canada LLP 12
Proponent submits application in
accordance with AIR
BC EAO screens application against
AIR - 30 days
BC EAO initiates formal review of application – 180
days
BC EAO prepares report
BC EAO refers application and
report to Minister for decision
Minister makes decision on whether
to issues a certificate - 45 days
BC EAO issues certificate
BC Environmental Assessment – Water Management
May 15, 2014 Dentons Canada LLP 13
• Water management aspects that must be considered in a BC
environmental assessment:
• Site Water Management
• Surface Water Quality
• Surface Water Quantity
• Ground Water Quality
• Ground Water Quantity
• Domestic Water Quality
Canadian Environmental Assessment
May 15, 2014 Dentons Canada LLP 14
• Changes made to requirements in CEAA 2012
• Assessment no longer triggered by authorization or approval from a
federal body
• Assessment required for designated projects
• Regulation sets thresholds for designated projects
• Amendments to regulation made in 2013
Canadian Environmental Assessment Thresholds for Construction, Operation, Decommissioning or
Abandonment of Mines
May 15, 2014 Dentons Canada LLP 15
Mine Type Change Threshold
Rare element New Ore production greater than 600 t/d
Diamond New Ore production of 3,000 t/d
Potash/apatite Changed from potash mine of
1,000,000 t/y of product to apatite
mine of 3,000 t/d of ore
Ore production of 3,000 t/d
Stone quarry Changed from 1,000,000 t/y to
3,500,000 t/y.
Production of 3,500,000 t/y
Oil sands mine Changed from more than 10,000 m3/d
production capacity
Production capacity of 10,000 m3/d
or more
Canadian Environmental Assessment Thresholds for Expansion of Existing Mines
May 15, 2014 Dentons Canada LLP 16
Mine Type Change Threshold
Metal mine Changed measurement from ore production
to mine area and changed production
threshold
50% increase in the area of the mine
operations with a resulting total production of
at least 3,000 t/d
Rare earth
element or
gold mine
Changed measurement from ore production
to mine area and changed production
threshold
50% increase in the area of the mine
operations with a resulting total production of
at least 600 t/d
Coal mine Changed measurement from ore production
to mine area and changed production
threshold
50% increase in the area of mine operations
with a resulting total production of at least
3,000 t/d
Diamond
mine
New 50% increase in the area of the mine
operations and a resulting total ore capacity of
3,000 t/d
Apatite
/potash mine
Changed measurement from potassium
chloride to ore production and changed
production threshold
50% increase in the area of mine operations
with a resulting total production of at least
3,000 t/d
Stone quarry
or sand or
gravel pit
Changed from 35% increase in production to
50% increase in mine area
50% increase in the area of the mine operation
and a resulting total production of 3,500,000
t/year or more
Oil sands
mine
New 50% increase in the area of the mine operation
and increase in productivity capacity of 10,000
m3/d or more
Canadian Environmental Assessment Requirements
May 15, 2014 Dentons Canada LLP 17
• Environmental Effects that must be considered in the EA include:
• A change to the following components of the environment:
• fish and fish habitat as defined in subsection 2(1) of the Fisheries Act;
• aquatic species as defined in subsection 2(1) of the Species at Risk Act;
• migratory birds as defined in subsection 2(1) of the Migratory Birds Convention Act, 1994;
• A change to the environment that would occur
• in a province other than the one in which the act or thing is done or where the physical activity, the
designated project or the project is being carried out; or
• outside Canada; and
• With respect to aboriginal peoples, an effect occurring in Canada of any
change to the environment on:
• health and socio-economic conditions;
• physical and cultural heritage;
• the current use of lands and resources for traditional purposes; or
• any structure, site or thing that is of historical, archaeological, paleontological or architectural
significance.
• Any effects triggered by a federal approval for the project
Canadian Environmental Assessment Process
00 Month 2013 Dentons Canada LLP Document reference # 18
• Proponent of designated project must submit project description to Agency
(s. 9)
• Agency decides if environmental assessment required (s. 10(b))
• Responsible authority can delegate conduct of environmental assessment
(s. 26)
• Federal Minister can substitute provincial process for a CEAA review if no
referral to a review panel has been made (ss. 32 and 33)
• Project can be exempted by Federal Government from application of CEAA
as long as provincial process has justification and mitigation process for
significant adverse effects (s. 37)
• Two types of assessment – screens or review panels
• 1 year time limit for screenings (s. 27)
• 2 year time limit for panels (s. 38(3)
Fisheries Act Approval
May 15, 2014 Dentons Canada LLP 19
• Authorization required from DFO under s. 35 of the Fisheries Act
• Authorization is required for activities that will result in serious harm to
fish that are part of a commercial, recreational or Aboriginal fishery, or to
fish that support such a fishery
• Prior to June 2012, authorization was required for harmful alteration,
disruption, or destruction (“HADD”) of fish habitat
• A number of water body types and types of activities have been identified
by DFO as not requiring review (http://www.dfo-mpo.gc.ca/pnw-
ppe/index-eng.html)
• Prohibition of deposit of deleterious substances in water frequented by
fish
• Currently can only be authorized by regulations under 36(4) and (5) (e.g.
Metal Mining Effluent Regulations)
Navigation Protection Act Approvals
May 14, 2014 Dentons Canada LLP 20
• Previously, under the Navigable Waters Protection Act, approval was
required from Transport Canada for works built or placed in, on, over,
under, through or across any navigable water
• On April 1, 2014, the new Navigation Protection Act (NPA) came into
force
• Now authorization is only required for work on water bodies listed in the
schedule in the NPA
• The Minor Works Order establishes classes of works that do not require
approval (http://www.tc.gc.ca/eng/programs-633.html)
Thank you
Bernard J. Roth
403-268-6888
Dentons Canada LLP
21
The preceding presentation contains examples of the kinds of
issues companies dealing with mining could face. If you are
faced with one of these issues, please retain professional
assistance as each situation is unique.
Dentons Canada LLP
22