Upload
mukherjee-dk
View
72
Download
3
Embed Size (px)
Citation preview
del2infinity Energy Consulting Pvt. Ltd. (An accurate solution for Wind Power &
Solar Power Forecasting & Scheduling) [email protected] / [email protected]
www.del2infinity.xyz
Delhi || Kolkata || Bangalore
Karnataka Electricity Regulatory Commission has notified the “Forecasting, Scheduling, Deviation
settlement and related matters for Wind and Solar Generation Sources) Regulation 2015
(KERC/CT/1/15 dated 31 May 2016.
Karnataka is the first state to release the Forecasting & Scheduling regulation in the country.
Executive Summary of “Forecasting, Scheduling, Deviation settlement and related matters for Wind
and Solar Generation Sources) Regulation 2015
Applicability of Regulations (Section 3.2)
All wind generators having combined installed capacity of 10 MW and above at the pooling
station (Section 3.2 (a)).
All wind generators having combined installed capacity of 5 MW and above at the pooling station
(Section 3.2 (b)).
Existing wind and solar generators needs to comply with the regulation within six months from
the date of publication of the regulations in the official gazette (Section 4.1).
All the new wind and solar generators which shall be commissioned after six months from the
effective date of the regulation shall comply these norms before commissioning of the project
and connecting with the state grid (Section 4.2).
Virtual Pool (Section 4.8)
The wind & solar generators either by themselves or through the Aggregator/QCA may opt for
aggregation of Forecasting and Scheduling of different pooling stations to enable larger
geographical integration and furnish scheduling of Integrated pools at 15 minutes time block to
SLDC and in such case any pooling and depooling of the DSM charges shall be done only at
their level.
Computation of Error (Section 2(j) & 7.1)
Computation of error quantity
The following formula shall be adopted for this purpose:
% Error (deviation) = ((Actual Generation – Scheduled Generation)X 100) / ((Available
Capacity (AvC))
F&S at Inter- State level (Section 7.4)
The energy charges shall be paid to the generators
i. As per the actual energy supplied irrespective of the Schedule quantum of energy for the
generators for intra-State Transactions
ii. As per the Schedule energy for the inter-State transmission which are governed by the
CERC regulations.
Frequency of Revision (Sec 4.9)
Deviations will be calculated on the basis of Available Capacity (AvC). 16 revisions allowed during the
intraday with each revision effective from 4th time block.
del2infinity Energy Consulting Pvt. Ltd. (An accurate solution for Wind Power &
Solar Power Forecasting & Scheduling) [email protected] / [email protected]
www.del2infinity.xyz
Delhi || Kolkata || Bangalore
Tolerance limits and deviation bands (Sec 7.3)
The permissible deviation for all the wind and solar generators shall be (+/-) 15% beyond which penalty
is applicable.
Sl
No
Particulars Deviation range Payment to DSM account by
generators
1 For Wind and Solar
generators having
PPAs with ESCOMs
and / or supplying
power to consumers
availing open access
facilities for wheeling
the power within
State
>±15% ≤±25% Rs 0.50 per kWh for the quantum of
short fall or excess energy beyond
±15% and upto ±25% of deviation from
the schedule (i.e. ±10% above tolerable
limits of ±15%
>±25% ≤±25% Rs. 0.50 Ps per kWh up to ±25%
deviation + Rs 1.0. per kWh for the
remaining quantum of short fall or
excess of energy for deviation from
schedule beyond ±25% up to ±35%.
More than
>±35%
Rs. 0.50 Ps per kWh up to ±25%
deviation + Rs 1.0. per kWh for the
remaining quantum of short fall or
excess of energy from deviation to
schedule beyond ±25% up to ±35% +
Rs 1.50 per KWh for the quantum of
short fall or excess of energy beyond
±35% deviation from schedule .
------------------------------------------------------------------------------------------------------------- Del2infinity Energy Consulting (P) Ltd. provides solution for Accurate Wind Energy & Solar Forecasting and Scheduling, Load Forecasting & Qualifying Coordinating Agency (QCA). del2infinity works with some marquee names across industries.
del2infinity Wind Energy Forecasting and Scheduling Solution has achieved efficiency with unprecedented accuracy of 87%
time-blocks is under +/-10% error margin depending on the accuracy of real time data.
del2infinity Solar Energy Forecasting & scheduling solution has achieved efficiency with unprecedented accuracy of 98%+
time-blocks is under +/- 5% error margin depending on the accuracy of real time data. Del2infinity is the only accurate Solar Energy Forecasting Solution provider at the moment. Feel Free to mail us for any query or updates.
We are offering a limited Free Trials, please let us know if you are interested for the same.