DESCRIPTION
The risk identification is the first operating process in the Project Risk Management and it expects the active involvement of the project Stakeholders, through the use of specific tools and techniques. It's the process in which creativity, iterativity and a joint use of the tools and techniques are strategic in order to perform an effective and efficient Project Risk Management. The risk identification techniques are presented in the slides conforming to the PMBOK Guide ©, fifth edition
Citation preview
PROJECT RISK MANAGEMENT
FOCUS ON RISK IDENTIFICATION TECHNIQUES
Author: Marco De Santis, PMP, 2014
3
The project risk management is the systematic process of identifying, analyzing and responding to project risks in order to increase the probability and/or the impact of positive events and to decrease the probability and/or the impact of negative events in accordance with the constraints.
Author: Marco De Santis, PMP, 2014 Based on "Project Management Plan and process map" and "Project Risk Management - Methodology and Application", published on Slideshare and LinkedIn, 2014
Manifesto
Author: Marco De Santis, PMP, 2014
Focus on Risk Identification techniques
Please, Cl ick ON hyperl ink for the deta ils
5
Assumptions analysis
Brainstorming
Nominal group
Delphi technique
Interviews
Route Cause Analysis
Information gathering
techniques
Checklist analysis
Pareto Diagram
SWOT analysis Expert
judgement
Diagramming techniques
Cause and effect diagram (Ishikawa)
System or process flow charts
Influence diagrams
Author: Marco De Santis, PMP, 2014
Documentation reviews
6
Focus on Risk Identification techniques
Control lists
1
Project Checklist
Project objectives, constraints, assumptions, WBS, contracts
Analysis and homogenize step
3
2
Project Team
Risk Owner
Based on "Corso di preparazione all'esame PMP", TI HR Services - Eureka Service, 2013
Checklist analysis
Author: Marco De Santis, PMP, 2014
7
List of Project Risks
2
1
Project Team
Facilitator
Brainstorming
Author: Marco De Santis, PMP, 2014 Based on "Corso di preparazione all'esame PMP", TI HR Services - Eureka Service, 2013
Focus on Risk Identification techniques
8
Project Team
Identify the participants
Evaluation step
Project Team
List of grouped risks
List of risks
Unique list of results
List of risks List of risks
Project Team
Results approval step
6
5
1
3
2
4
7
8
List of Project Risks
Risk Owner
Risk Owner
Risk Owner
Risk Owner
Nominal group
Author: Marco De Santis, PMP, 2014 Based on "Corso di preparazione all'esame PMP", TI HR Services - Eureka Service, 2013
Focus on Risk Identification techniques
9
Risk Owner
List of Project
Risks
Unique list of risks and opinions
Experts identification (anonymous list)
Risk Owner
2 2 2 Risks and opinion
Risks and opinion
Risks and opinion
3 1
Review and update
Updated unique list of risks and opinions
4
5 Review and
update Review and
update
5 5
Risk Owner 7
Consensus
Yes
No
8
6
? ? ? ?
? ? ? ?
Delphi technique
Author: Marco De Santis, PMP, 2014 Based on "Corso di preparazione all'esame PMP", TI HR Services - Eureka Service, 2013
Focus on Risk Identification techniques
10
2
1
Project Team, experts and other Project Manager
Risk Owner
Project objectives, constraints, assumptions, WBS, contracts
List of Project
Risks
Basis of risk interviews
Objectives, WBS, historical data
Experts identifications
Analysis of answers
Risk Owner
4 4
3
5
Interviews
Author: Marco De Santis, PMP, 2014 Based on "Corso di preparazione all'esame PMP", TI HR Services - Eureka Service, 2013
Focus on Risk Identification techniques
11
Problem idetification
Action
Problem analysis
Analysis
Project standard compliance
Check
Control
Qualità
Sicurezza
Efficienza
Effectiveness
Quality Security
Why
Why
Why
Why Why
Based on Lean Leadership, 7 step to 5-why, Paulsen & Paulsen LLC, 2010
Route cause analysis
Author: Marco De Santis, PMP, 2014
Focus on Risk Identification techniques
12
Project objectives, constraints, assumptions, WBS, contracts
Team di progetto
Bad effect for the project
Effetto 1
Effetto 2
Effetto 3 List of Project Risks and
generation causes
1 2
3
4
Cause and effect Diagram
oR Ishikawa diagram "fishbone"
Author: Marco De Santis, PMP, 2014 Based on "Corso di preparazione all'esame PMP", TI HR Services - Eureka Service, 2013
Focus on Risk Identification techniques
13
Product requirements
Prototype development
Prototype Internal approval
Technical specifications
Start of internal test
phase
Customer approval
User Acceptance
Test
Prototype Approval
Production
no
yes
no
no
yes yes
system or process Flow charts
Author: Marco De Santis, PMP, 2014 Based on "Corso di preparazione all'esame PMP", TI HR Services - Eureka Service, 2013
Focus on Risk Identification techniques
14
Examples: • If R1 doesn't occur, R4 cannot occur. • If R9 is influenced by R7: if R7 occurs, the probability of occurrence of R9 increases from 10% to 30%. • If R9 is positively influenced by R5 and R2, too: if R5 or R2 occurs the impact of the risk of R9 decreases in measure of 50%. • R3 is influenced only by the jointly occurrence of R6 and R8: in this case, R3 double both its probability of occurrence and
its impact on the project.
R1
R4
R7
R5
R2
R9
R3
R8
R6
Occurrence
Impact
Probability of occurrence
Probability of occurrence and impact
OR
AND
Influence Diagrams
Author: Marco De Santis, PMP, 2014 Based on "Corso di preparazione all'esame PMP", TI HR Services - Eureka Service, 2013
Focus on Risk Identification techniques
15
Project objectives, constraints, assumptions, WBS, contracts
List of Project Risks
Meeting
3
1
Project Team Risk Owner
Strengths Weakness
Opportunities Threats
2 2 2 SWOT Analysis
Strengths, Weakness, Opportunities, Threats
Author: Marco De Santis, PMP, 2014 Based on "Corso di preparazione all'esame PMP", TI HR Services - Eureka Service, 2013
Focus on Risk Identification techniques
16
Pareto Diagram
0,0%10,0%20,0%30,0%40,0%
Rischio1
Rischio2
Rischio3
Rischio4
Rischio5
Impact on cost
0,0%10,0%20,0%30,0%
Rischio1
Rischio2
Rischio3
Rischio4
Rischio5
Impact on schedule
0,0%10,0%20,0%30,0%40,0%
Rischio1
Rischio2
Rischio3
Rischio4
Rischio5
Impact on quality
Author: Marco De Santis, PMP, 2014 Based on "Corso di preparazione all'esame PMP", TI HR Services - Eureka Service, 2013
Focus on Risk Identification techniques
17
Expert judgment
Author: Marco De Santis, PMP, 2014 Based on Project Management Body Of Knowledge (PMBOK Guide®), Project Management Institute, Fifth Edition, 2012 , p. 327
Experts
2 3
Basis of risk interviews
Objectives, WBS, historical data
Experts identification
List of Project Risks
Evaluations Evaluations Evaluations
Project Manager and Risk Owner
1
Focus on Risk Identification techniques
18
Based on Project Management Body Of Knowledge (PMBOK Guide®), Project Management Institute, Fifth Edition, 2012, p. 324-325 Author: Marco De Santis, PMP, 2014
Assumptions analysis and
documentation reviews
Project Manager, Risk Owner and Project Team 1 1 1
2
List of Project Risks
Focus on Risk Identification techniques
Attachments
FOCUS on 6 RISK MANAGEMENT processes PMBOK Guide®, Fifth Edition
20 Author: Marco De Santis, PMP, 2014
The process of defining the rules for the development of the risk management plan, which includes: methodology, responsibility, definition and management of reserves and changes
The process of identifying project risks, accurately describing and giving a first response hypothesis
Risks are classified by importance, in order to define a priority based on a Risk Factor (RF)
The overall effect of the project risks (Expected Monetary Value, EMV) is measured numerically. The contingency reserve, which is the pre-reserve economic response to the risks , will be defined
Here are being planned necessary responses for facing the threats in order to reduce the probability and / or the impact of threats and / or to amplify those opportunities
The process of implementing the responses, of updating the status of the risks (identified, secondary, residual and new) and evaluating the effectiveness of the risk management.
PLA
NN
ING
M
ON
TIO
RIN
G A
ND
CO
NTR
OLI
NG
1. Plan Risk Management
2. Identify Risks
3. Perform Qualitative Risk Analysis
4. Perform Quantitative Risk
Analysis
5. Plan Risk Responses
6. Control Risks
Based on "Corso di preparazione all'esame PMP", TI HR Services - Eureka Service, 2013
Threats Risk Strategy OpportunityAvoid Uncertaincy removal Exploit
TransferReallocation of responsibilities Enhance
MitigateExposition level
modification ShareAccept Current management Accept