21
January 16, 2014 Building Design Branch Huntington Levee Community Meeting 1

Huntington Levee Community Meeting

Embed Size (px)

DESCRIPTION

Huntington Levee Community Meeting January 16, 2014

Citation preview

Page 1: Huntington Levee Community Meeting

1

January 16, 2014

Building Design Branch

Huntington Levee Community Meeting

Page 2: Huntington Levee Community Meeting

Building Design Branch

Purpose of Meeting

• Review levee conceptual design features and recommendations

• Receive feedback from the community on project features before moving forward with final design

2

Page 3: Huntington Levee Community Meeting

3Building Design Branch

Agenda

I. Project Background

II. Conceptual Design Features

III. Accreditation

IV. Questions

3

Page 4: Huntington Levee Community Meeting

4Building Design Branch

• June 2006 -160 homes were flooded from a storm event

• 2009 – US Army Corps of Engineers (USACE) completed a study to evaluate flood damage reduction measures in the Huntington Community

4

Project Background

Page 5: Huntington Levee Community Meeting

5Building Design Branch

• September 2011- Tropical Storm Lee caused damage to 160 homes in the Huntington Community

•November 6, 2012 – Fairfax County voters approved stormwater bond referendum to fund design and construction of flood damage reduction measurers

•November 9, 2012 – Fairfax County advertised for consultant design services

• June 2013 – Fairfax County awarded the levee design contract to ARCADIS

5

Project Background

Page 6: Huntington Levee Community Meeting

6Building Design Branch 6

Project Background

Page 7: Huntington Levee Community Meeting

7Building Design Branch

• November 2013 – ARCADIS submitted the Phase I design package to Fairfax County

• Survey – 300 acre of aerial survey, 80 acre field survey, 26 field run cross sections of Cameron Run, utility survey

• Geotechnical Investigation – collection and analysis of 13 additional soil borings

• Wetland delineation

• Conceptual Design

• Review USACE 2009 study and conceptual design

• Evaluate potential refinements/alternatives

7

Project Background

Page 8: Huntington Levee Community Meeting

8Building Design Branch

• Phase II (January 2014-Winter 2017)

• Schematic Design (30%)• Design Development (60%)• Permitting• Land Acquisition• Construction Documents (100%)• Bidding

• Phase III (Winter 2017-Spring 2019)

• Construction

• Original schedule condensed by 7 months

8

Project Background

Page 9: Huntington Levee Community Meeting

9Building Design Branch

Conceptual Design Features

• Collection Drains vs. Cut Off Wall• Pump Station Location• Stormwater Diversion • Earthen Levee vs. Earthen Levee/I-Wall

Combination

Key Design Considerations

9

Page 10: Huntington Levee Community Meeting

10Building Design Branch

Collection Drains vs. Cutoff Wall

Pros• Lower cost

• Ease of construction

Cons• Maintenance of toe

drainage pipe

• Higher risk of piping thru levee due to clogging of toe drain

• Additional pumping capacity required (6,700 gpm)

Pros• No maintenance

of toe drainage

• Reduced risk of piping thru levee

Cons• Higher cost

• Specialized construction

• Concern that it could raise groundwater levels and flood basements

Collection Drain (Recommendation)

Cut Off Wall

10

Page 11: Huntington Levee Community Meeting

11Building Design Branch

Potential Pump Station Locations

Westside SWPSLocation

Eastside SWPSLocation

Central SWPSLocation

11

Page 12: Huntington Levee Community Meeting

12Building Design Branch

Center of Levee Western End Eastern End (Recommendation)Property requirements

• Fairfax owned park property

• Would occupy space otherwise available for the excavated ponding area or park recreation area

Permanent Access• From Liberty Dr. over raised road

through excavated ponding area - Very exposed during storm events, safety concern

Neighbor concerns / buffering• In center of neighborhood park

recreation area

• Very visible from neighborhood

Drainage• Requires a third channel to

Cameron run with additional wetlands impacts and maintenance

Property requirements• Adjacent commercial parcel is

ideal, but prohibitively costly

Permanent Access• Easy access off Fenwick Dr. or

new access road from Metroview Pkwy.

Neighbor concerns / buffering• Very close to homes at Fenwick

Dr.

Drainage• Divert all flow to Western end

• Slightly smaller diversion channel than Eastern option

Property requirements• Fairfax owned park property

Permanent Access• New access road from Hunting

Creek Rd.

Neighbor concerns / buffering• Far from residential properties in

Huntington Neighborhood

• Buffered by wooded area

• Backs up to apartment complex recreation area

Drainage• Divert all flow to Eastern end

• Slightly larger diversion channel than Western option

12

Potential Pump Station Locations

Page 13: Huntington Levee Community Meeting

13Building Design Branch 13

Stormwater Diversion

Page 14: Huntington Levee Community Meeting

14Building Design Branch

Stormwater Diversion Options

Grass Lined Drainage Ditch• Erosion concern from high

flow velocities

• 30’ wide @ 2:1 side slopes

• Maintenance concerns and mowing

• Standing water concerns due to flat grades

• Lowest installation cost

Concrete Drainage Ditch• Not as wide due to steeper

side slopes (1:1 = 15’-20’ or vertical = 10’)

• Fence to prevent access• High construction cost for

cast in place• Less maintenance than grass

lined

Precast Concrete Box Culvert

*Recommendation• Limited access points –

security bars to prevent entry

• Buried – any potential standing water is not exposed

• Precast construction – culvert segments trucked to site

• Maintenance - confined space entry

14

Page 15: Huntington Levee Community Meeting

15Building Design Branch

Earthen Levee vs. Earthen Levee/Wall Combination

Earthen Levee Earthen Levee / I-Wall Combination

(Recommendation)Pros• More natural aesthetic

• Clear access to Cameron Run

Cons• Higher cost

• Generates greater construction traffic

• Greater overall levee mass, width varies from 60 feet – 85 feet

Pros• Reduced construction traffic

• Lower cost

• Smaller overall levee mass, width reduced by 17’

• Reduced backwater impacts

• Reduced impact to treesCons• Maintenance of wall

• Access thru wall

15

Page 16: Huntington Levee Community Meeting

16Building Design Branch

Examples Architectural Facades

16

Earthen Levee/Wall Combination

Page 17: Huntington Levee Community Meeting

17Building Design Branch 17

Earthen Levee

Earthen Levee / I-Wall Combination

Levee Cross Sections

Page 18: Huntington Levee Community Meeting

18Building Design Branch 18

Earthen Levee/Wall Combination

Page 19: Huntington Levee Community Meeting

19Building Design Branch

Earthen Levee/I-Wall Combination

21

Page 20: Huntington Levee Community Meeting

20Building Design Branch

Accreditation

• Levee will be designed to meet FEMA accreditation standards

• Fairfax County will submit an accreditation package to FEMA for their consideration

22

Page 21: Huntington Levee Community Meeting

21Building Design Branch

Questions

Contact Information – Huntington Levee Project Phone #: 703-324-5800 Email address:

[email protected]

Contact Information – Stormwater Questions Phone #: 703-324-5821 Email address:

[email protected]

Huntington Levee Website: www.fairfaxcounty.gov/dpwes/huntingtonlevee

To request this document in an alternate format call 703-324-5800, TTY 711.

23