Fast and easy to construct, environmental timber frame homes are precision engineered, energy efficient and warm. OFP timber frame homes are carefully fabricated in our own workshops in kent and the South East of England, using timber from managed resources. Each stage of production is carefully monitored to ensure that our customers receive a quality product, with delivery arranged to suit their build programme.

Citation preview

Page 1: The Knoll 2

An OFP Case Study: The Knoll

A four storey residential nursing project

Page 2: The Knoll 2

Overview

The Knoll, Nursing Home, Deal, Kent

•4 storey build featuring a lift shaft throughout

•38 residential rooms

•2 storey ‘day room’ area

•Nurses office

Page 3: The Knoll 2

Stage 1 – The plans

1. Elevations

The architectural drawings are sent to OFP in CAD format for the design team to look through and assign to a designer.

Page 4: The Knoll 2

Stage 1 – The plans

2. The architect’s CADs are then drawn up to suit timber frame using TRADA timber frame standards.

Page 5: The Knoll 2

Stage 1 – The plans

3. Once the architects drawings have been approved by the client the designer can start the design process.

Page 6: The Knoll 2

Stage 1 – The plans

4. When the timber frame drawings have been signed off by the client and the architect then the panels and floor cassettes can be generated.

These are accurately engineered drawings used to produce the walls in the building.

These are then sent to the production team and scheduled in to the factory.

Page 7: The Knoll 2

Stage 2 – Manufacture

The completed panel drawings are added to the production package and sent to the factory for manufacture.

Page 8: The Knoll 2

Stage 2 – Manufacture

After the design has been completed a CSV file is generated. This works in conjunction with our optimaster saw to produce a waste managed cutting list.

1. The quantity of timber required is calculated and loaded in to the saw.

2. The saw is electronically programmed for the scheduled works.

3. The timber is efficiently and accurately cut. This minimises any waste.

Page 9: The Knoll 2

Stage 2 – Manufacture

4. The optimaster saw prints the exact position of each stud in the panel and its position within the building.

5. The timber is loaded in to the rack for the manufacture process to begin.

6. Each compartment is organised according to the timber reference.

Page 10: The Knoll 2

Stage 2 – Manufacture

7. The timber is taken from the rack.

8. The panel is laid out on the manufacture bench with the panel drawing beside it.

9. The panel is assembled in a controlled environment to the designer’s specifications.

Page 11: The Knoll 2

Stage 2 – Manufacture

10. The completed panel is loaded in to the plot stack.

12. The completed stack is taken to the loading bays ready to go to site…

11. The stack is checked for quality and accuracy.

Page 12: The Knoll 2

Stage 3 – On site erection

Once the panels have been manufactured the erection process can begin…

Page 13: The Knoll 2

Stage 3 – On site erection

Day One

The first element to go to site is the soleplate. This is the footprint of the building.

Duration: 1 day.

Page 14: The Knoll 2

Stage 3 – On site erection

Day Two

Once the soleplate has been fitted the ground floor panels are delivered.

144 panels were installed over 2 days.

Page 15: The Knoll 2

Stage 3 – On site erection

Day Three

Here we can see the landed and erected internal panels.

Page 16: The Knoll 2

Stage 3 – On site erection

Day Four

If any steels are required in the build these can be sent as part of the production schedule.

32 steels were required in the ground floor in this project.

Page 17: The Knoll 2

Stage 3 – On site erection

Day Six

Once the panels have been fitted the floors can start going in.

45 cassettes were landed in 2 days.

Page 18: The Knoll 2

Stage 3 – On site erection

Day Nine

Once the cassettes have been fitted and decked the next floor can be installed.

144 panels were installed over 2 days.

Page 19: The Knoll 2

Stage 3 – On site erection

Day Nine

Here you can see the external panels sheathed in OSB.

Page 20: The Knoll 2

Stage 3 – On site erection

Day Nine

The first floor panels are in and ready for the second floor cassettes to be landed.

Page 21: The Knoll 2

Stage 3 – On site erection

Page 22: The Knoll 2

Stage 3 – On site erection

Day ElevenThe second floor cassettes are landed.42 cassettes were landed in 2 days.

Page 23: The Knoll 2

Stage 3 – On site erection

Day TwelveThe cassettes are decked out. The starter plate is then laid for the next stage of panels to be erected.

Page 24: The Knoll 2

Stage 3 – On site erection

Day ThirteenThe 2F panels are landed and erected.105 panels were landed in a day.

Page 25: The Knoll 2

Stage 3 – On site erection

Page 26: The Knoll 2

Stage 3 – On site erection

Day FifteenThe third floor cassettes are landed.17 cassettes were fitted in a day.

Page 27: The Knoll 2

Stage 3 – On site erection

Page 28: The Knoll 2

Stage 3 – On site erection

Day SeventeenThe third floor panels are landed.49 panels are landed in a day.

Page 29: The Knoll 2

Stage 3 – On site erection

Day SeventeenThe roof trusses are also landed with the 3F panels.

Page 30: The Knoll 2

Stage 3 – On site erection

Page 31: The Knoll 2

Stage 3 – On site erection

Day NineteenThe roof timbers are fitted.

Page 32: The Knoll 2

Stage 3 – On site erection

Page 33: The Knoll 2

Stage 4 - Completion

After OFP have completed the roof and the building is signed off the second fix can begin.

Here are a number of recently completed projects illustrating OFP’s finished product…

Page 34: The Knoll 2

Stage 4 – Completion

Page 35: The Knoll 2

Stage 4 – Completion

Page 36: The Knoll 2

Stage 4 – Completion