Agile planning with Rational Team Concert (RTC) workshop provides tip for agile team to successfully use RTC to support for the three innermost levels of Mike Cohn's planning onion: product, release and sprint / iteration planning. RTC also provides extensive support source code management and integration to CI build and automated release deployment tools such as UrbanCode Deploy For more information see https://jazz.net/library/article/593 Details Rational Team Concert (RTC) provides a lightweight tool to help project teams plan, executing and monitor agile, waterfall and scaled agile development projects (such as Scrum, Scrum of Scrums, Disciplined Agile Delivery - DAD, or Scaled Agile Framework - SAFe. For agile projects / programs, RTC provides tools to create product, release and sprint backlogs for teams, to create individual plans for developers, and to track the progress during an iteration and to balance the work load of developers. For waterfall projects / programs, RTC provides development teams with traditional project management capabilities such as work breakdown structures, schedule dependencies, constraints and Gantt charts.

Citation preview

Page 1: Agile planning with rational team concert

Agile Planning with Rational Team Concert (RTC)

Reedy Feggins JrAgile Coach / CSM / WW Solution Architect

[email protected]

September 1, 2013

Page 2: Agile planning with rational team concert

© 2013 IBM Corporation2

Rational Software

Webinar Overview

� Agile planning is one of the key strengths of RTC

� From planning a simple iteration, to a release for one team, or a whole project with multiple iterations and teams - RTC Agile Planning comes with a set of ready-to-use plan types and plan views

� In this webinar, see how to get started with RTC Agile Planning, as well as tailoring plans to suit your needs

Page 3: Agile planning with rational team concert

© 2013 IBM Corporation3

Rational Software

Agile Planning Onion*

• Strategy – defines the vision associated with a business need or direction.

• Portfolio – defines the overall product offering that consists of applications and tools and how they integrate.

• Product – defines a product vision and outlines the road-map for the product.

Strategy

Portfolio

Product

Release

Iteration

Day

(*) Mike Cohn, Agile Estimating and Planning

Page 4: Agile planning with rational team concert

© 2013 IBM Corporation4

Rational Software

Agile Planning Onion*

Product – defines a product vision and outlines the road-map for the product.

Release – represents a prioritized backlog of product features that are committed to be delivered inagiven time period.

Sprint / Iteration – defines short, fixed-length subsets of releases, typically 2-4 week time frame.

Day – represents the actions taken in a day to achieve the iteration goals.

Strategy

Portfolio

Product

Release

Iteration

Day

(*) Mike Cohn, Agile Estimating and Planning

Agile team plans at the innermost three levels. RTC offers support for all these levels

Page 5: Agile planning with rational team concert

© 2013 IBM Corporation5

Rational Software

Planning Onion Layers: Development Project

Agile team plans at the innermost three levels. RTC offers support for all these levels

Strategy

Portfolio

Product

Release

Iteration

Day

Page 6: Agile planning with rational team concert

© 2013 IBM Corporation6

Rational Software

Rational Team Concert (RTC) Plan Definition

Page 7: Agile planning with rational team concert

© 2013 IBM Corporation7

Rational Software

Rational Team Concert (RTC) Plan Definition

• Unified view of Information

– What - Work Items

– Who – Project Area / Team Area

– When – Iteration

• Plans are owned by a team or project and are associated with an iteration

• Plan content is derived fromAll work items which have a Filed Against value set to a category owned by the Plan’s team or project and are planned for plan’s iteration.

• Plans have a plan type, which define the layer in the planning “onion”.

Page 8: Agile planning with rational team concert

© 2013 IBM Corporation8

Rational Software

TIP: Named Iterations vs Calendar-based Iterations

� Use calendar-based iterations when individual teams have their own sprint schedules that differ from other teams

� Lowest common denominator is the calendar

� All teams need to reach the same end point but get there at their own pace

� Use named iterations when all teams are sync’d to the same schedule

NOTE: •Iterations are displayed and sorted by name•Iterations with the same names will not be easily differentiated during selection•TRICK: Use a naming convention that makes selection easy!

Page 9: Agile planning with rational team concert

© 2013 IBM Corporation9

Rational Software

Rational Team Concert (RTC) Planning Support

� Process neutral

– Out of box templates (works with Scrum, OpenUp, Formal Project Management)

– Customized templates

� No separation between planning/implementing of features and bug fixing

– Both planning and defect management share a common data model

– They are supported in the same tool and are highly integrated

– Plans are in fact a query for work items

� Supports:

– Top down planning (project manager, product owner, team leads, …) AND

– Bottom Up (team members) AND

– Plan consolidation (Sprint planning meetings, stand-ups, …)

Page 10: Agile planning with rational team concert

© 2013 IBM Corporation10

Rational Software

What is a backlog?

� The product backlog is an ordered list of "requirements" that is maintained for a product.

� The release backlog is an ordered list of "requirements" that is planned for the next release.

� The sprint backlog is the list of work the Development Team must address during the next sprint.

– The stories/features are broken down into tasks by the Development Team

– Tasks on the sprint backlog are never assigned; rather, tasks are signed up for by the team members

Product ‘Backlog’ iteration(no dates)

Sprint ‘Backlog’ iteration

Release ‘Backlog’ iteration

TIP: Until a work item is actively being worked on it is really on ‘the backlog’ at some planning level

Page 11: Agile planning with rational team concert

© 2013 IBM Corporation11

Rational Software

Planning Onion Layer: Product Backlog

• Prioritized feature list

• Plan Views• Ranked List• Work Breakdown

• Work Item Types• Plan items: Work items that are relevant forplanning. Ex: Epics, Stories, etc.

Product

Release

Iteration

Day

• Reports• How your product backlog is evolving?• How many items are there on the product backlog?• Can we find out how long it would take to complete the product backlog?

• Top down Planning

Page 12: Agile planning with rational team concert

© 2013 IBM Corporation12

Rational Software

Managing a Product Backlog

• High-level plan that contains stories not planned for any release or iteration yet

• Targeted for the iteration marked as Backlog Iteration

• Prioritized feature list based on risk,business value, etc.

• Plan items – include only non executionitems such as Epics and Stories

• Customize with themes,business value, etc• Define the Done Criteria

Page 13: Agile planning with rational team concert

© 2013 IBM Corporation13

Rational Software

Managing a Product Backlog

• Sizing in Story points - rough estimates based on complexity and development effort

• Ranking - ensure that the most valuable functionality is delivered first

TIP: Plans are an actionable interface. Drag and Drop, in-context editing and new work item creation are supported

Page 14: Agile planning with rational team concert

© 2013 IBM Corporation14

Rational Software

Planning Onion Layer: Release Backlog

• Planned/Committed features for the release of the product

• Plan Views• Iterations• Ranked List• Roadmap• Teams• Traceability (optional)• Work Breakdown

• Work Item Types• Plan items: Work items that are relevant for theplanning. Ex: Themes, Epics and Stories

• Reports• Team Velocity

All the story points that were 'achieved' grouped by the iteration they were targeted for.• Release Burndown

Amount of outstanding work for the release, broken down by iteration.

• Top down Planning

Product

Release

Iteration

Day

Page 15: Agile planning with rational team concert

© 2013 IBM Corporation15

Rational Software

Managing a Release Backlog

• Connects the business value and the execution items.

• Iterations view: holistic view of which stories are planned for which iteration.

• Drag and drop : assign the stories to specific iterations.

• Progress/Load bars: avoid overloading an iteration considering the team's velocity and to track overall progress.

• Coarse grained: Estimation in size; estimated in relative values such as Story Points, lines of code, function points, etc.

Page 16: Agile planning with rational team concert

© 2013 IBM Corporation16

Rational Software

Managing a Release Backlog …

• Single view for all sprints in the release

Page 17: Agile planning with rational team concert

© 2013 IBM Corporation17

Rational Software

• Overview for multiple teams

Managing Release Backlog …

Page 18: Agile planning with rational team concert

© 2013 IBM Corporation18

Rational Software

Track progress

• Team velocity: measures a team rate of progress.• Completing 2 Stories of 5 story points in one iteration gives a velocity of 10• Good guess is to assume the same velocity for the next iteration

Page 19: Agile planning with rational team concert

© 2013 IBM Corporation19

Rational Software

Planning Onion Layer: Sprint Backlog

• Tasks planned for the iteration

• Plan Views• Planned Time• RankedList• Roadmap• Taskboard / Kanban• Workbreakdown

• Work Item Types• Execution items: Work items which have work assigned. Ex: Task and Defect.

• Reports• Sprint Burndown

Estimated hours required to complete remaining work items.

Product

Release

Iteration

Day

Page 20: Agile planning with rational team concert

© 2013 IBM Corporation20

Rational Software

Planning a Sprint

• Focus on Execution : large stories broken down into smaller sub-stories and execution items

• Fine grained: Estimation of effort: typically estimated in Ideal Hours/Days

• Custom view: Does the execution task rank relate to the business value expressed on the product backlog?

Page 21: Agile planning with rational team concert

© 2013 IBM Corporation21

Rational Software

Planning a Sprint …

• Roadmap view: illustrates the schedule of the execution items (e.g. defects and tasks) and the rolled-up schedule of the plan items (e.g. stories and epics).

Page 22: Agile planning with rational team concert

© 2013 IBM Corporation22

Rational Software

Planning a Sprint …• Taskboard view:

• shows plan items in the left column and execution items in the state group columns. • visualize the progress of the stories and their children.• ability to adjust the state quickly with drag and drop from this view.• color tags can be used to show the state of the plan items.

Page 23: Agile planning with rational team concert

© 2013 IBM Corporation23

Rational Software

Planning a Sprint …• Kanban

• Define limits (counts or complexity or estimates).• Deviations from the ideal are shown as a small box in the column header. The further you are from your

ideal, the more red the box gets.• Shows where capacity is available as well as when capacity limits might be exceeded

Page 24: Agile planning with rational team concert

© 2013 IBM Corporation24

Rational Software

Planning a Sprint …

• Load Bars : capacity planning• Do I have enough time to finish all my work in this iteration?

• Progress Bars : track progress• Considering all my work for this iteration. Where am I now?

Aids in assessment of the health of the Plan

Page 25: Agile planning with rational team concert

© 2013 IBM Corporation25

Rational Software

Planning a Sprint …Quality of Planning:• The more work items you estimate the more precise the work can be computed.

• The quality is excellent if all work items are estimated, it is good if the majority is estimated, ...

• Visually, the percentage of estimated work items is represented as a fill-level.

• The height of load and progress bars shows how many work items have an estimate.

• If no work item is estimated, the bar is not visible, if all work items are estimated, the bar is fully visible.

Page 26: Agile planning with rational team concert

© 2013 IBM Corporation26

Rational Software

TIP: Plans Are Fancy Queries & Queries Answer Questions

� Primary query/filter parameters are:

– Owner (i.e. Team)

– Iteration

– Plan item types or all items (Plan & Execution)

� Additional parameters for filtering, grouping and display can be defined in a Plan View

– Setup views to help answer specific questions or to draw attention to anomolies

Example:Verification

View

Page 27: Agile planning with rational team concert

© 2013 IBM Corporation27

Rational Software

TRICK: Work Item Exclusion vs Inclusion in Plan Views

� Plan default is to EXCLUDE work items based on selected parameters

� Behavior is to show only current and future work, which burns down over time

Show work itemsthat includethis string

Exclude workitems meeting

this criteria

How manywork items are

not shown

Expression Syntax:type:Defect [Excludes]

!type:Defect [Includes]

Page 28: Agile planning with rational team concert

© 2013 IBM Corporation28

Rational Software

TIP: Performance recommendations

� Large plans unmanageable

� Build simpler view modes (outsource other plan view modes into separate plans and link them together so that navigation is easier)

Page 29: Agile planning with rational team concert

© 2013 IBM Corporation29

Rational Software

Planning Onion Layer in Rational Team Concert: Day

• My Work View : Developers plan their assigned work and adjust estimates• Managing new work

• Managing current work

• Managing future work

• Work Load

• Find, filter, and colorize planned work items

• Daily Stand ups : Developer Taskboard view to see what people are working on.

• Planned Time : Developers sort the work items in the order in which they intends to work onthem

• Bottom Up Planning

Product

Release

Iteration

Day

Page 30: Agile planning with rational team concert

© 2013 IBM Corporation30

Rational Software

How does an individual developer work during a sprint?

• My work view: in place estimation, feeds, …

• Planned time view: Developers sort the work items in the order in which they intend to work on them in my work view.

• Warnings/errors are shown if the work is lagging behind the schedule

• My work view approximation in the web: Customized Planned Time View show a specific owner.

Page 31: Agile planning with rational team concert

© 2013 IBM Corporation31

Rational Software

How does an individual developer work during a sprint? …

• One place to view queries that impact my work

Page 32: Agile planning with rational team concert

© 2013 IBM Corporation32

Rational Software

Additional Information

� Effective Planning with Rational Team Concert 4.0

–https://jazz.net/library/article/594

� Cross-Project Tracking with Rational Team Concert, Version 4.0

–https://jazz.net/library/article/1152

Page 33: Agile planning with rational team concert

© 2013 IBM Corporation33

Rational Software

www.ibm.com /software/rational

Page 34: Agile planning with rational team concert

© 2013 IBM Corporation34

Rational Software

© Copyright IBM Corporation 2012. All rights reserv ed. The information contained in these materials is provided for informational purposes only, and is provided AS IS without warranty of any kind, express or implied. IBM shall not be responsible for any damages arising out of the use of, or otherwise related to, these materials. Nothing contained in these materials is intended to, nor shall have the effect of, creating any warranties or representations from IBM or its suppliers or licensors, or altering the terms and conditions of the applicable license agreement governing the use of IBM software. References in these materials to IBM products, programs, or services do not imply that they will be available in all countries in which IBM operates. Product release dates and/or capabilities referenced in these materials may change at any time at IBM’s sole discretion based on market opportunities or other factors, and are not intended to be a commitment to future product or feature availability in any way. IBM, the IBM logo, Rational, the Rational logo, Telelogic, the Telelogic logo, and other IBM products and services are trademarks of the International Business Machines Corporation, in the United States, other countries or both. Other company, product, or service names may be trademarks or service marks of others.

www.ibm.com /software/rational

Page 35: Agile planning with rational team concert

© 2013 IBM Corporation35

Rational Software

Tips & Tricks: Summary

� A plan is an actionable interface

� Iterations

– Names vs Calendar

� Cross project planning

� Work Item Exclusion vs Inclusion

� Performance recommendations

– Large plans unmanageable

– Build simpler view modes (outsource other plan view modes into separate plans and link them together so that navigation is easier)

� Dashboards

– Dashboard in a plan

– Plan in a dashboard

� Additional information:

– Effective Planning with Rational Team Concert 4.0: https://jazz.net/library/article/594