TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Prepared by Ashik Ahmed
Section Manager Technical Services
In a Multinational Fertilizer Company Tel.: +880 31 618972~4; Ext.: 2237 (Office)
Email : [email protected],[email protected] Mobile: +880 1730059920
Project No.: CT- IMP - 2010 Project Name: Cooling Tower Improvement Project
Total Daily Activity of Cooling Tower Cell-H Renovation Work
Fill Material
Air In
Induced Draft Fan
Drift Air to Atmosphere
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
1Film Filling (Packing)
Fabrication(H - Cell)
600 233 73 39
Very Good.
Please note that 150 Pcs packings were made during previous (G Cell) Work.
70 pcs
2Drift Eliminator
Fabrication248 212 0 85
No drift eliminitors are made today cause the critical path of the shedule is to build scaffolding inside the cell.So,the people are involved on scaffolding works (North Side).
212 pcs of drift eliminators were made on G cell working time.
Continue Scaffolding
Works (North Side)
3Removal of Old
Eliminators,Nozzles ,etc
N/A N/A N/A N/A
The drift eleminators are 1st shifted to the concrete base then the following items are removed.i) Nozzles : 324 Pcsii) Nozzle Holder (Big): 144 Pcsiii) Nozzle Holder (Small): 180 Pcs
Install the new nozzle
holders
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 17/10/2012 CELL- H Activity Performance Date: 17/10/2012 CELL- H Activity Performance Date: 17/10/2012 CELL- H Activity Performance Date: 17/10/2012 CELL- H
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 17/10/2012 CELL- H Activity Performance Date: 17/10/2012 CELL- H Activity Performance Date: 17/10/2012 CELL- H Activity Performance Date: 17/10/2012 CELL- H
4Scaffolding works on
south side100% - 40%
Following quantity of items are required for each side scaffolding:i) Timber :- 200 Pcsii) Pipe (6m) :- 38 Pcsiii) Pipe (3m) :- 18 Pcsiv) Clamp :- 252 PcsThe frame has made ready with all the pipes & clamps.The timber installation will be done on tomorrow.
Timber Installation
5Scaffolding works on
North side100% - 30%
The north side scaffolding material quantity is same like written on the
column above.Only 10 Pcs (6m) pipes are left for making the frame. The remaining few pipes & timber installation will be carried out from tomorrow.
Timber Installation
6
Marking the Scaffolding Pipes for
making future cell scaffolding easy
100% - - 100%
All the pipes of north & south side cell scaffoldings are marked from west to east side from 1 to 18 numbers.
It will ease the next 02 cellsscaffolding works.
N/A
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 17/10/2012 CELL- H Activity Performance Date: 17/10/2012 CELL- H Activity Performance Date: 17/10/2012 CELL- H Activity Performance Date: 17/10/2012 CELL- H
7 Manpower N/A - - N/A
Skilled (Local) –10 nos.CNCEC – 4 nos.Unskilled (local) – 11KAFCO: Mr. Sobhan(SFMC)Supervisor: Mr. Ashik & Mr. Badrul
- -
8Safety & House Keeping
- - - - Satisfactory -
REMARKS & BACKLOG :
I) The work progress is satisfactory.
II) All type of works will be suspended for 3 days due to Eid vacation from 27th Oct to 29th Oct, 2012.
So, decision has taken to continue the work on next Friday (19.10.12).
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
1Film Filling (Packing)
Fabrication(H - Cell)
600 304 71 51
Very Good.
Please note that 150 Pcs packings were made during previous (G Cell) Work.
70 pcs
2Installing new nozzle
holders324 162 162 50
Nozzle holders of half of the cell was installed.
i) Nozzle Holder (Big): 72 Pcsii) Nozzle Holder (Small): 90 Pcs
Install the new nozzle
holders
3Scaffolding works on
South side100% - 70%
The timber installation have almost completed today.Out of 200 pcs,we have installed 150 pcs .
Tying Timber with the pipes & place cover
on the whole scaffolding
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 18/10/2012 CELL- H Activity Performance Date: 18/10/2012 CELL- H Activity Performance Date: 18/10/2012 CELL- H Activity Performance Date: 18/10/2012 CELL- H
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 18/10/2012 CELL- H Activity Performance Date: 18/10/2012 CELL- H Activity Performance Date: 18/10/2012 CELL- H Activity Performance Date: 18/10/2012 CELL- H
4Scaffolding works on
North side100% - 30%
The north side scaffolding has not carried out today.As the packing removal start from south side,all the people are involve on south side works.
**Only 10 Pcs (6m) pipes are required for making the frame on North side.It will be carried out after completion of scaffold on South side. **
Continue Timber
installation on south
side.
5 Manpower N/A - - N/A
Skilled (Local) –08 nos.CNCEC – 4 nos.Unskilled (local) – 13KAFCO: Mr. Sobhan(SFMC)Supervisor: Mr. Ashik & Mr. Badrul
- -
6 Safety & House Keeping - - - - Satisfactory -
REMARKS & BACKLOG :
I) The work progress is satisfactory.
II) All type of works will be suspended for 3 days due to Eid vacation from 27th Oct to 29th Oct, 2012.
So, decision has taken to continue the work on next Friday (19.10.12).
I) The North side scaffolding has not carried out today.As the packing removal start from south side, all the people are involved on south side works.
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
1Film Filling (Packing)
Fabrication(H - Cell)
600 366 62 61
Satisfactory.70 pcs
2Installing new nozzle
holders324 162 0 50
Nozzle holders installation had not carried out today.The people are engaged on removal of old packing.
Install the new nozzle holders
3Scaffolding works on
South side100% - 100%
The timber installation have completed today. After tying all timbers with pipes, the stage is covered by Tarpaulin.
Timber installation on North side.
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 19/10/2012 CELL- H Activity Performance Date: 19/10/2012 CELL- H Activity Performance Date: 19/10/2012 CELL- H Activity Performance Date: 19/10/2012 CELL- H
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 19/10/2012 CELL- H Activity Performance Date: 19/10/2012 CELL- H Activity Performance Date: 19/10/2012 CELL- H Activity Performance Date: 19/10/2012 CELL- H
4 Removal of old packing 2400 300 300 13
At first a whole made on the south -west corer of South side of cell-H.**Please note that the old packings are 1/4 size of new packing size.So,total no is 2400 apprx.**
700 pcs
5Shifting old packing to
Scrape Yard2400 98 98 4
The old packing’s are shifted to scrap yard by Tractor.
**01 Tractor can load 98 Pcs of old packing’s (Approx).**
7 Tractor(~700 Pcs
Old Packing)
6 Manpower N/A - - N/A
Skilled (Local) –08 nos.Unskilled (local) – 13KAFCO Supervisor: Mr. Ashik SPIG Supervisor: Mr. Andrew Lautka
- -
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 19/10/2012 CELL- H Activity Performance Date: 19/10/2012 CELL- H Activity Performance Date: 19/10/2012 CELL- H Activity Performance Date: 19/10/2012 CELL- H
7Safety & House Keeping
- - - - Satisfactory -
****It indicates it is possible that we could finish this cell on 12 working days which would be a great milestone.****
REMARKS & BACKLOG :
I) The work progress is satisfactory.
III) Tomorrow we will require civil labors for cleaning dry air inlet side concrete & painting of structures.
V)On cell -G we had removed & shifted all old packing's on 9th working day & the scaffolding of south side was completed on 4th working day.
On cell-H the scaffolding on south side & packing’s removal has started from 3rd working day.
So,if the weather condition will suit & minimum 6 tractors of old packing's can be removed, all the old packing's removal could be possible on 7th
working day. So we are 02 days ahead of previous schedule.
IV) *****Today's work has been carreid out without any CNCEC people without any work hamper.*****
II) The North side scaffolding has not carried out today.As the packing removal start from south side,
all the manpower are involve on south side works.
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
1Film Filling (Packing)
Fabrication(H - Cell)
600 437 71 73
As the weather condition is good, the packing fabrication work is going on smoothly.
70 pcs
2Installing new nozzle
holders324 324 162 100
Nozzle holders installation has
completed today.Removal of old packing from top side.
3Scaffolding works on
North side100% 60% 30% 60%
The north side scaffolding has carried out today.Frame making is completed & timber installation is going on.Out of 200 pcs of Timber,we have installed 120 pcs .
Continue Timber
installation & tying the timbers with pipes on North side.
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 20/10/2012 CELL- H Activity Performance Date: 20/10/2012 CELL- H Activity Performance Date: 20/10/2012 CELL- H Activity Performance Date: 20/10/2012 CELL- H
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 20/10/2012 CELL- H Activity Performance Date: 20/10/2012 CELL- H Activity Performance Date: 20/10/2012 CELL- H Activity Performance Date: 20/10/2012 CELL- H
4 Removal of old packing 2400 800 500 33
As 03 persons who are involved on
nozzle holder installation will be free
from tomorrow,packing removal
from top will be faster.
**Please note that the old packings
are 1/4 size of new packing
size.So,total no is 2400 apprx.**
600 pcs
5Shifting old packing to
Scrape Yard2400 686 588 29
The old packing’s are shifted to scrape yard by Tractor.
**01 Tractor can load 98 Pcs of old packing’s (Approx).**Today we have shifted 6 tractor of old packing's.
6 Tractor(~600 Pcs
Old Packing)
6
Cleaning of Debris from the air inlet
concrete & painting of structures
100%50% of
South side N/A 25
The cleaning has done for 02 sides out of 04 on south side.The Civil department has given their manpower for the cleaning work.
100% on south side
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 20/10/2012 CELL- H Activity Performance Date: 20/10/2012 CELL- H Activity Performance Date: 20/10/2012 CELL- H Activity Performance Date: 20/10/2012 CELL- H
7 Manpower N/A - - N/A
Skilled (Local) –10 nos.Unskilled (local) – 13CNCEC: 04 NosCivil :04 NosKAFCO Supervisor: Mr. Ashik & Mr. BadrulMr. Sobhan (SFMC)SPIG Supervisor: Mr. Andrew Lautka
- -
8Safety & House Keeping
- - - - Satisfactory -
REMARKS & BACKLOG :
I) The work progress is satisfactory.
II)**We are still on track that we could finish this cell on 12 working days.**
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
1Film Filling (Packing)
Fabrication(H - Cell)
600 507 70 85
As the weather condition is good, the packing fabrication work is going on smoothly.
The required no of packing’s for Cell-H (600 Pcs) will be fabricated by morning session of 23rd Oct work.
70 pcs
2Checking the pipe support concrete
CheckingN/A _ _ N/A
04 concrete supports are found broken out of 18.
The civil department will be requested to repair those support by Lock fix P Hardener. (Maker FOSROC)
Repair 04
Supports
3Scaffolding works on
North side100% 90% 30% 90%
The north side scaffolding has almost finished today. Timber installation has completed & only 50 timbers remains untied with pipes.
Continue tying the 50 nos timbers with pipes on North
side & give tarpaulin to cover them.
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 21/10/2012 CELL- H Activity Performance Date: 21/10/2012 CELL- H Activity Performance Date: 21/10/2012 CELL- H Activity Performance Date: 21/10/2012 CELL- H
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 21/10/2012 CELL- H Activity Performance Date: 21/10/2012 CELL- H Activity Performance Date: 21/10/2012 CELL- H Activity Performance Date: 21/10/2012 CELL- H
4 Removal of old packing 2400 1300 500 54
Satisfactory.
**Please note that the old packing’s
are 1/4 size of new packing size.So,
total no is 2400 apprx.**
600 pcs
5Shifting old packing to
Scrape Yard2400 1274 588 53
The old packing’s are shifted to scrape yard by Tractor.
**01 Tractor can load 98 Pcs of old packing’s (Approx).**
Today we have shifted 6 tractor of old packing's.
6 Tractor(~600 Pcs
Old Packing)
6
Cleaning of Debris from the air inlet
concrete & painting of structures
100%80% of
South side
30% of
South side 40
The cleaning & painting works has hampered today due to old packing removal on south side.
As the north side scaffolding will be completed, the painting will be faster by tomorrow.
Start cleaning on North side.
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 21/10/2012 CELL- H Activity Performance Date: 21/10/2012 CELL- H Activity Performance Date: 21/10/2012 CELL- H Activity Performance Date: 21/10/2012 CELL- H
7 Manpower N/A - - N/A
Skilled (Local) –12 nos.Unskilled (local) – 11CNCEC: 04 NosCivil :04 NosKAFCO Supervisor: Mr. Ashik & Mr. BadrulMr. Sobhan (SFMC)SPIG Supervisor: Mr. Andrew Latka
- -
8Safety & House Keeping
- - - - Satisfactory -
REMARKS & BACKLOG :
I) The work progress is satisfactory.
II) We are still on the way to complete this cell on 12 working days.
**(If we can complete removal of old packing's by 23.10.12 & No weather difficulties)**
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
1Film Filling (Packing)
Fabrication(H - Cell)
600 579 72 97
As the weather condition is good, the packing fabrication work is going on smoothly.
We require only 21 pcs packing’s for Cell-H (600 Pcs) .
70 pcs .The packing work will be continued for future II Cells.
2Repairing pipe support
concrete N/A _ _ N/A
04 concrete supports are found broken out of 18.Civil department informed us that the Lock fix P Hardener. (Maker FOSROC) is not available on site.They assure that they will manage the Hardener from Dhaka.
Waiting For Material
3Scaffolding works on
North side100% 100% 10% 100%
The north side scaffolding has finished today. Timber installation has completed & tarpaulin is placed to cover them.
Remove Old
Packing's from Top
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 22/10/2012 CELL- H Activity Performance Date: 22/10/2012 CELL- H Activity Performance Date: 22/10/2012 CELL- H Activity Performance Date: 22/10/2012 CELL- H
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 22/10/2012 CELL- H Activity Performance Date: 22/10/2012 CELL- H Activity Performance Date: 22/10/2012 CELL- H Activity Performance Date: 22/10/2012 CELL- H
4 Removal of old packing 2400 1900 600 79
Very Good.
**Please note that the old packing’s
are 1/4 size of new packing size.So,
total no is 2400 apprx.**
Complete All the Old Packing's
5Shifting old packing to
Scrape Yard2400 1862 588 78
The old packing’s are shifted to scrape yard by Tractor.
**01 Tractor can load 98 Pcs of old packing’s (Approx).**
Today we have shifted 6 tractor of old packing's.
Complete All the Old Packing's shifting to Scrape Yard
6
Cleaning of Debris from the air inlet
concrete & painting of structures
100%
100% of
South side
& 60% of
South side
40% 80%
The cleaning & painting works has completed on south side.
Half of the north side painting has completed today.
Complete cleaning & painting on North side.
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 22/10/2012 CELL- H Activity Performance Date: 22/10/2012 CELL- H Activity Performance Date: 22/10/2012 CELL- H Activity Performance Date: 22/10/2012 CELL- H
7Movable Frame
Scaffolding Making For Packing's installation.
N/A N/A N/AFrame scaffolding has prepared on North Side.
Make frame scaffolding on South
side.If all the packing's got
removed.
7 Manpower N/A - - N/A
Skilled (Local) –12 nos.Unskilled (local) – 11CNCEC: 04 NosCivil :04 NosKAFCO Supervisor: Mr. Ashik & Mr. BadrulMr. Sobhan (SFMC)SPIG Supervisor: Mr. Andrew Latka
- -
8Safety & House Keeping
- - - - Satisfactory -
REMARKS & BACKLOG :
I)The work progress is very good.
V) We are suppose to complete this cell on 12 working days.
II)All old packing’s, drift eliminator removal will be completed by tomorrow.
III)Civil department is requested to arrange Lock fix P Hardener asap.(Maker FOSROC).It is required for 04 no’s concrete support repairing.
IV) If weather is fine then we may start packing installation from 24th October (Wednesday).
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
1Film Filling (Packing)
Fabrication(H - Cell)
600 614 35 102
All the required packing's for Cell -H has fabricated today.The people are engaged on packing shifting on the evening work.
1st Shift some 100 pcs of
packings to North side & then
fabricate 50 pcs of
packings.
2Cleaning works on
North side100% 100% 100% 100%
The north side cleaning has finished today. The frame scaffolding is ready on North Side.
Install New Packing's.
3 Removal of old packing 2400 2400 500 100
All the old packing's are removed
today.
**Please note that the old packing’s
are 1/4 size of new packing size.So,
total no is 2400 apprx.**
Install New Packing's.
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 23/10/2012 CELL- H Activity Performance Date: 23/10/2012 CELL- H Activity Performance Date: 23/10/2012 CELL- H Activity Performance Date: 23/10/2012 CELL- H
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 23/10/2012 CELL- H Activity Performance Date: 23/10/2012 CELL- H Activity Performance Date: 23/10/2012 CELL- H Activity Performance Date: 23/10/2012 CELL- H
4Shifting old packing to
Scrape Yard2400 2320 588 97
The old packing’s are shifted to scrape yard by Tractor.Today we have shifted 7 tractors of old packing's.Only two (1 for Packing & 1 for Debris) tractor old materials are left on south side.
So,it means we requires 28
tractors to shift 1 Cell
materials.(24 for Packing's,03 for
drift eliminators & 1 for Debris)
Complete 02 Tarctor material shifting.Then shift
new packing to North side
(120 Pcs).
5
Cleaning of Debris from the air inlet
concrete & painting of structures
100%
100% of
South side
& 100% of
South side
20% 100%
The cleaning & painting works has completed on both North & South side.
N/A
6Movable Frame
Scaffolding fabricationN/A N/A N/A N/A
Make frame scaffolding on South side form Packing
Installation .
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 23/10/2012 CELL- H Activity Performance Date: 23/10/2012 CELL- H Activity Performance Date: 23/10/2012 CELL- H Activity Performance Date: 23/10/2012 CELL- H
7 Manpower N/A - - N/A
Skilled (Local) –12 Nos.Unskilled (local) – 11 NosCNCEC: 04 NosCivil :04 NosKAFCO Supervisor: Mr. Ashik & Mr. BadrulSPIG Supervisor: Mr. Andrew Latka
- -
8Safety & House Keeping
- - - - Satisfactory -
IV) Packing installation will start from tomorrow.
VII) We are going to complete this cell on 12 working days.(If No Weather Difficulties)
REMARKS & BACKLOG :
I)The work progress is very good.
II)All old packing’s, drift eliminator removal has completed today.Only 02 Tractor old matterials are left & it will be done by Tomorrow morning.
III)Civil department has managed Lock fix P Hardener today.But as all the packings are removed,the work will be done after packing installation.
(Probably on 30.10.12)
V)All type of works will be suspended for 3 days due to Eid vacation from 27th Oct to 29th Oct, 2012. So, decision has taken to continue the work on tomorrow.
VI)Mr.Nur Islam & Mr. Himel Barua will be as supervisor for 24th & 25 th October.Mr. Ashik & Mr. Badrul Alam are on leave for Eid Vacation.
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
1Film Filling (Packing)
Fabrication(H - Cell)
600 614 0 102
As all the required packing's for Cell -H has fabricated, people are engaged on old packing removal.
Fabricate 70 Pcs
2Cleaning works on
South side100% 100% 100% 100%
The south side cleaning has finished today. The frame scaffolding is ready on South Side.
Install New Packing's.
3Shifting old packing to
Scrape Yard2400 2400 80 100
The old packing’s are shifted to scrape yard by Tractor.
Today we have shifted 3 tractors of old packing's
So,it means we requires 29
tractors to shift 1 Cell
materials.(24 for Packing's,03 for
drift eliminators & 2 for Debris)
Shift new packing to North side(200 Pcs).
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 24/10/2012 CELL- H Activity Performance Date: 24/10/2012 CELL- H Activity Performance Date: 24/10/2012 CELL- H Activity Performance Date: 24/10/2012 CELL- H
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 24/10/2012 CELL- H Activity Performance Date: 24/10/2012 CELL- H Activity Performance Date: 24/10/2012 CELL- H Activity Performance Date: 24/10/2012 CELL- H
4 Manpower N/A - - N/A
Skilled (Local) –12 Nos.Unskilled (local) – 11 NosKAFCO Supervisor: Mr. Nur & Mr. Himel BaruaSPIG Supervisor: Mr. Andrew Latka
- -
5Safety & House Keeping
- - - - Satisfactory -
IV) We are suppose to complete this cell on 12 working days.(If No Weather Difficulties)
REMARKS & BACKLOG :
I)The work progress is moderate.
II) Packing installation will start from tomorrow.
III)All type of works will be suspended for 3 days due to Eid vacation from 27th Oct to 29th Oct, 2012.
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
1Film Filling (Packing)
Fabrication(H - Cell)
600 85 71 14
Packing Fabrication Again start Today.
a) This packing quantity is for next Cell-IAs the packing installation is almost finished, we will not continue packing fabrication tomorrow.
Fabricate 70 Pcs
2 Packing Installation 600 200 200 33The packing installation has started today.
Continue Packing
Installation.
3Shifting new packing's
to North Side300 100 100 33
The new packing’s are shifted to North Side by Tractor. Shift new
packing to North side(200 Pcs).
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 25/10/2012 CELL- H Activity Performance Date: 25/10/2012 CELL- H Activity Performance Date: 25/10/2012 CELL- H Activity Performance Date: 25/10/2012 CELL- H
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 25/10/2012 CELL- H Activity Performance Date: 25/10/2012 CELL- H Activity Performance Date: 25/10/2012 CELL- H Activity Performance Date: 25/10/2012 CELL- H
4 Manpower N/A - - N/A
Skilled (Local) –12 Nos.Unskilled (local) – 11 NosCNCEC: 04 NosKAFCO Supervisor: Mr. Nur & Mr. Himel BaruaSPIG Supervisor: Mr. Andrew Latka
- -
5Safety & House Keeping
- - - - Satisfactory _
III) We probably complete this cell on 13 working days. (Ahead of Eid Ul Azha the labors did not work satisfactorily)
REMARKS & BACKLOG :
I)The work progress is satisfactory.
II)All type of works will be suspended for 3 days due to Eid vacation from 27th Oct to 29th Oct, 2012.
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
1Film Filling (Packing)
Fabrication(H - Cell)
600 156 71 26
Satisfactory
a) This packing quantity is for next Cell-IAs the packing installation is almost finished, we will not continue packing fabrication tomorrow.
Remove scaffolding on South Side
2Shifting new packing's
to North Side300 300 200 100
All the required new packing’s has shifted to North Side today.
Shift new Drift
Eliminator from top of the cell
3 Packing Installation 600 500 300 83
The packing installation has carried our smoothly on both South & North side.
Install all the Packing's before
Lunch Break
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 30/10/2012 CELL- H Activity Performance Date: 30/10/2012 CELL- H Activity Performance Date: 30/10/2012 CELL- H Activity Performance Date: 30/10/2012 CELL- H
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 30/10/2012 CELL- H Activity Performance Date: 30/10/2012 CELL- H Activity Performance Date: 30/10/2012 CELL- H Activity Performance Date: 30/10/2012 CELL- H
4 Nozzle Installation 324 54 54 17
Nozzle installation has started after lunch break.As all the manpower are busy with packing fixing ,only 01 guy has started
nozzle installtion.
Install nozzles & protection layers.
5 Manpower N/A - - N/A
Skilled (Local) –12 Nos.Unskilled (local) – 11 NosCNCEC: 04 NosKAFCO Supervisor: Mr. Ashik & Mr. BadrulSPIG Supervisor: Mr. Andrew Latka
- -
6Safety & House Keeping
- - - - Satisfactory -
IV) Drift eliminator installation will start from tomorrow.Autoshop has assured to give 100T crane support.
V) We probably complete this cell on 13 working days. (If all the labors work hard, we still got chance to complete this cell work on 12 days)
REMARKS & BACKLOG :
I)The work progress is good.
II) New packing’s installation has almost completed today. Only 100 pcs of new packing's are left & it will be done by Tomorrow morning.
III) civil department will manage Lock fix P Hardener tomorrow. They will fix the broken concrete supports.
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
1 Packing Installation 600 600 100 100
The packing installation has completed on both South & North side.
Clean the terpauline & remove scaffoldingon South
side
2Repairing the concrete pipe supports
5 Nos 5 Nos 5 Nos 100%
05 Concrete Supports has found Broken. Civil dept personel has repaired those supports by Lockfix P Hardener (Polyester resin anchoring grout).
It is a combination of filler & glue. Maker FOSROC
N/A
3Mobilizing Drift Eiminators to Cell -H through 100T crane
248 120 120 48
120 pcs of drift eleminators has mobilized to the cell-G through 100 T crane.
Shift 128 pcs Drift
Eliminators(7 times lifting
required)
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 31/10/2012 CELL- H Activity Performance Date: 31/10/2012 CELL- H Activity Performance Date: 31/10/2012 CELL- H Activity Performance Date: 31/10/2012 CELL- H
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 31/10/2012 CELL- H Activity Performance Date: 31/10/2012 CELL- H Activity Performance Date: 31/10/2012 CELL- H Activity Performance Date: 31/10/2012 CELL- H
4 Nozzle Installation 324 324 270 100Nozzle installation has completed today.
Install 248 pcs of drift eliminators.
5Installing protection layers
253 125 125 49
125 pcs protectection layers has installed today.The rest could be installed by tomorrow.
Install 128 pcs of
protection layers
6 Cleaning on north side N/A N/A N/A N/A
North side cleaning has been completed.We also remove debris(Salt) from top of the concrete beams.
Clean the terpauline & remove scaffoldingon South
side
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 31/10/2012 CELL- H Activity Performance Date: 31/10/2012 CELL- H Activity Performance Date: 31/10/2012 CELL- H Activity Performance Date: 31/10/2012 CELL- H
7Dismantling moveable scaffolding on North Side
N/A N/A N/A N/AMoveable scaffolding on North side has completed today..
Dismantle the
moveable scaffoldingon South
side
8Removal Of timbers,Scaffolding pipes
100% - 40%
North side A)All timbers of had removed.B) 50% scafflding pipes had removedSouth SideA)Removal will start from tomorrow
100%
9Marking on Timbers forease installation on next two cells
N/A N/A
The timbers has marked for each row.Total 4 rows on each South & North side has marked.
N/A
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 31/10/2012 CELL- H Activity Performance Date: 31/10/2012 CELL- H Activity Performance Date: 31/10/2012 CELL- H Activity Performance Date: 31/10/2012 CELL- H
10 Manpower - - - -
Skilled (Local) –12 nos.CNCEC – 4 nos.Unskilled (local) – 11KAFCO: Mr. Kalam (SFMC)Supervisor: Mr. Ashik & Mr. BadrulSPIG Supervisor: Mr. Andrew Latka
-
11Safety & Hosue Keeping
- - - - Satisfactory -
V) Removal of scaffolding on south side will be started from tomorrow.We hope to complete removal by tomorrow evening.
VI) The H- Cell works will be finished by tomorrow(12th Working Day).The probable test run will be carried out on evening time.
II) New drift eliminators mobilization has started today.Autoshop will continue 100T crane support on tomorrow also.
REMARKS & BACKLOG :
I) The work progress is very good. The labors have worked very satisfactorily today.
II) New packing’s installation has completed today.
IV) Civil department has repaired the broken concrete pipe supports by Lock fix P Hardener.
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
1Mobilizing Drift Eiminators to Cell -H through 100T crane
248 248 128 100
128 pcs of drift eleminators has mobilized to the cell-G through 100 T crane. N/A
2Drift eliminators Installation
248 248 248 100
Drift eliminators installation has completed today.**Please notice during the installation that the small length flat side should be on bottom.**
N/A
3Installing protection layers
253 253 128 100128 pcs of protectection layers has installed today.
N/A
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 01/11/2012 CELL- H Activity Performance Date: 01/11/2012 CELL- H Activity Performance Date: 01/11/2012 CELL- H Activity Performance Date: 01/11/2012 CELL- H
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 01/11/2012 CELL- H Activity Performance Date: 01/11/2012 CELL- H Activity Performance Date: 01/11/2012 CELL- H Activity Performance Date: 01/11/2012 CELL- H
4 Cleaning on South side N/A N/A N/A N/A
South side cleaning has been completed.We also remove debris(Salt) from top of the concrete beams.
N/A
5Dismantling moveable scaffolding on South Side
N/A N/A N/A N/AMoveable scaffolding on South side has removed today..
N/A
6Removal Of Timbers,Scaffolding pipes
100% 100 60 100%
North side & South SideA)All timbers has removed.B) 100% scaffolding pipes has removed.
N/A
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 01/11/2012 CELL- H Activity Performance Date: 01/11/2012 CELL- H Activity Performance Date: 01/11/2012 CELL- H Activity Performance Date: 01/11/2012 CELL- H
7Checking Nozzles,Protection Layers
N/A N/A N/A N/AThe nozzles,protection layers are checked & found OK.
N/A
8Cleaning on South & North Side Besin
N/A N/A N/A N/A Cleaning has done properly. N/A
9 Manpower - - - -
Skilled (Local) –13 nos.CNCEC – 4 nos.Unskilled (local) – 14KAFCO: Mr. Kalam (SFMC)Supervisor: Mr. Ashik & Mr. BadrulSPIG Supervisor: Mr. Andrew Latka
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011
TECHNICAL SERVICES DEPARTMENT
DAILY WORK PROGRESS REPORT AND NEXT DAY’S PROGRAM
Sr.
NoToday’s Activity
Total
Qty
Reqd
Total
Prod.
Qty (pcs)
Q’ty
Prod.
Today
(Pcs)
% of
individual
work item
on H (8th)
Cell
RemarksNext Day’s
ProgramImages
Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010 Project No.: CT- IMP - 2010
Project Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement ProjectProject Name: Cooling Tower Improvement Project
Activity Performance Date: 01/11/2012 CELL- H Activity Performance Date: 01/11/2012 CELL- H Activity Performance Date: 01/11/2012 CELL- H Activity Performance Date: 01/11/2012 CELL- H
10Safety & Hosue Keeping
- - - - Satisfactory -
III)The work had completed on only 12 Days. It was possible due to the well skill & dedication of the workers.
I) The Cooling Tower Cell-H work has completed today. The labors have worked very satisfactorily today also.
II)After safely electrical isolation removal,the test run was done at 16:45 PM.The H cell overall operating condition was found satisfactory.
** For any cell operation please first open the inlet butterfly valve atleast 30 % & then start the fan.Otherwise the protection layers got
scattered during no load operation.**
REMARKS & BACKLOG :
K-IMS-PRJ-F-05 Rev-00 Eff. Date: Feb, 2011