Upload
nasapmc
View
13.717
Download
1
Tags:
Embed Size (px)
DESCRIPTION
Citation preview
National Aeronautics and Space Administration
www.nasa.gov
Risk Management during Integrated Systems Research Technology Development
NASA Project Management (PM) Challenge 2012February 22-23, 2012
Presented by: Douglas Brown, Environmental Responsible Aviation (ERA) Risk ManagerGaudy Bezos-O’Connor, ERA Deputy Project ManagerSteven Hirshorn, Integrated Systems Research Program Systems Engineering & Integration Manager
2
AbstractCo-Authors: Justin Hornback (former ERA RM), Gaudy Bezos-O’Connor (ERA DPM), Steve Hirshorn (ISRP SE&I Mgr), and Douglas Brown (ERA RM)
The Environmental Responsible Aviation (ERA) Project, through system-level analyses, will select promising N+2 vehicle and propulsion concepts and technologies to develop based on their potential benefit toward simultaneously reducing fuel burn, noise and emissions.
These concepts and technologies will then be matured and their performance will be evaluated at the system and sub-system level in relevant environments.
Risk management is a set of activities aimed at achieving success by proactively risk-informing the selection of decision alternatives and then managing the implementation risks associated with the selected alternative.
In technology development efforts the measure of success to apply risk management assessment criteria is not easily defined. The ERA Risk Management Process developed a process to define and assess risks to achieving project success across a portfolio of independent sub-project technology development, that, when combined are required to maximize likelihood of achieving ERA project goals. ERA project goals are to select promising N+2 vehicle and propulsion concepts and technologies based on their potential benefit toward simultaneously reducing fuel burn, noise and emissions. The ERA risk management process added another layer of risk assessment; identifying a contribution factor based on subject matter expert input for each technology weighing each technology potential contribution to ERA goals. This was then applied to risks identified to the ERA project. The additional weighting factor improves identification of the true impact of project risks to achieve goals compared to traditional risk management processes. This presentation describes the process used to develop the weighting factor and share ERA's experience during implementation.
N+1, N+2 and N+3 reflect time periods for technology insertion into the aircraft fleet:• N+1: 2015-2020, N+2: 2020- 2025, N+3: 2025 +
3
Presentation Focus: The Risk Management Challenge
• What is the appropriate risk management construct for an Aeronautics Technology Development Project responsible for maturing airframe and propulsion technologies from TRL 3 to 5/6 through Integrated Systems Research?
• Factors:– Cultural and Project Execution Paradigm Shift from Fundamental Research to
Technology Development– Technology Development Projects are finite life, not enduring– Geographically dispersed government team – High Degree of Industry/OGA Partnerships/Collaborations with significant
costshare across Project Portfolio (FY10-12)– Varied or limited experience with project risk management outside of
airworthiness risks for aeronautics flight research projects.– The large number of independent tasks part of the portfolio of ERA
• No project integrated critical path– Must balance portfolio content versus schedule margin and budget reserves
• Budget reserves address prototype test article challenges and unique capability investments.
• Schedule margin address technical risks and facility challenges
4
Presentation Outline
• What is Aeronautics Integrated Systems Research– How does it differ from Aeronautics Fundamental Research?
• Overview of ARMD, ISRP and ERA Project• Aeronautics National Goals and ERA Project Technical Challenges• ERA Project Goals, Approach and Deliverables• ERA’s Risk Informed Decision Making Strategy
5
What is Aeronautics Integrated Systems Research?
N+1, N+2 and N+3 reflect time periods for technology insertion into the aircraft fleet:• N+1: 2015-2020• N+2: 2020- 2025• N+3: 2025 +
NASA Aeronautics Portfolio
6
Conduct cutting-edge research that will produce innovative concepts, tools, and technologies to enable revolutionary changes for vehicles that fly in all speed regimes.
Directly address the fundamental ATM research needs for NextGen by dev-
eloping revolutionary concepts, capabilities, and technologies that
will enable significant increases in the capacity, efficiency and
flexibility of the NAS.
Fundamental Aeronautics Program Airspace Systems Program
Conduct cutting-edge research that will produce innovative concepts, tools, and technologies to improve the intrinsic safety
attributes of current and future aircraft.
Preserve and promote the testing capabilities of one of the United States’ largest, most versatile and comprehensive set of flight and ground-based research facilities.
Aeronautics Test Program
Integrated Systems
Research Program
Conduct research at an integrated system-level on promising concepts and
technologies and explore/assess/demonstrate the benefits in a relevant environment
Aviation Safety Program
Program Goal: Conduct research at an integrated system level on promising concepts and technologies and demonstrate the benefits in a relevant environment
Integrated Systems Research Program Overview
7
Environmentally Responsible Aviation (ERA) Project
Explore and assess new vehicle concepts and enabling technologies through system-level experimentation to simultaneously reduce fuel burn, noise, and emissions
Unmanned Aircraft Systems (UAS) Integration in the National Airspace System (NAS) Project
Contribute capabilities that reduce technical barriers related to the safety and operational challenges associated with enabling routine UAS access to the NAS
ERA Project Technical Challenges (FY10-15)
Innovative Flow Control Concepts
for Drag Reduction
Advanced Composites for
Weight Reduction
Advanced UHB Engines for SFC & Noise Reduction
Advanced Combustors for
LTO Oxides of Ni reductions
Airframe & Engine Integration for
Community Noise Reduction
ERA Project Goals: Simultaneous Achievement of
the NASA Subsonic Transport System-Level Metrics (N+2 Timeframe)-75% LTO & -70% Cruise NOx Emissions
below CAEP6
-42dB below Stage 4 Community Noise
-50% Aircraft Fuel/ Energy Consumption
National R&D PlanEnergy and Environment
Enhance Mobility National Security
Traceability from National R&D Plan to ERA Project Technical Challenges
8
ERA Project Goals, Approach and Deliverables
9
• Project System-Level Performance Metrics:• Simultaneous achievement of the community noise, emissions and fuel burn
metrics defined in the NASA Subsonic Transport System Level Metrics in the N+2 timeframe
• Project Approach: • Combine rigorous systems analysis with large-scale, integrated systems
research demonstrations of promising airframe and propulsion technology solutions to TRL 5/6 by 2015
• Increase the viable trade space of vehicle configurations that can simultaneously meet the goals
• Project Definition: • 6-year life; • 2 Phases: Phase 1 (FY10-12); Phase 2 (FY 13-15)
• Project Deliverables: Key Performance Parameters (KPPs)• Technology Readiness Level (TRL) Maturation Maps• Product Transition Opportunities: Technology Transition Maps• Vehicle-level system metrics to measure progress towards the Project Goals• Technical data to validate/enhance system and physics-based assessment
tools
10
ISRP and ERA Risk Management Plan
Implement both Continuous Risk Management (CRM) and Risk Informed Decision Making (RIDM)– 8000.4A, Agency Risk Management Procedural Reqs.– 7120.08, NASA R&T Program & Project Mgmt. Reqs.
• Research and Technology Risk Management – Flight hardware focused– Risk management must balance the need
to conduct challenging technology development that will realize significant gains.
Advanced Combustor Testing
Lightweight Integrated Structures Testing
Propulsion Airframe, Aeroacoustic, and Propulstion Airframe AeroAcoustic Wind
Tunnel Testing
Flight Testing and Advanced Vehicle Concepts
Advanced Propulsor Testing
11
ISRP and ERA Project Risk Management Strategy
• Risk management at the program level will tend to be strategic and focused on ensuring the success of the projects, while risks that focus on the tactical technical / cost / schedule execution risks will be largely managed at the project-level with program insight.– ISRP Projects will manage their technical performance, schedule, and cost risks
according to their Risk Management Plans. – Significant project risks or risks requiring resources beyond those available to the
Project will be “Tracked” by or “Elevated” to the Program.
• A common frame of reference for Likelihood and Consequence (L&C) exists between ISRP and its Projects and across Projects:– Stems from the need to be able to reference both Program and Project risks in an
apples-to-apples comparison when communicating risks to the ISRP Program Director and to the Mission Directorate.
– Enable traceability of risks from Project task level to ISRP Programmatic Risks
• In order to ensure both Program and Project processes remain in sync and remain aware of risks at both levels, frequent good communications must be maintained .
12
Assessment of Risk in a TechnologyDevelopment Project• Technology risks follow a different risk pattern than other types of risks• The level of maturity for a technology affects the risk profiles of that technology,
i.e. lower maturity levels come with higher risks• The technology landscape is constantly changing with new technologies coming
online promising increased performance. Risk assessment must weigh the promise of new performance against the confidence of what has been done before
• These considerations do not require us to change likelihood and consequence criteria but consider the lens through which we view these scales
13
Technological Considerations For Risk Assessment
Technology Maturity Support BaseRating Value
ERA Likelihood Ratings
Technical
Some Research Completed/ Never Done Before
No Other Program Developing Similar Technology 5 Very High PTCS > 75%
New Design Based On Existing Technology
One Other Program Developing Similar Technology 4 High 50% < PTCS <= 75%
Major Redesign Of Existing Technology More Than One Program Developing Similar Technology 3 Moderate 20% < PTCS <= 50%
Minor Redesign A Few Parallel Programs 2 Low 5% < PTCS <= 20%
Existing Multiple Parallel Programs 1 Very Low PTCS <= 5%
Rating 5 4 3 2 1
ERA Risk Ratings Consequences
Major impact to achievement of Subsonic Transport System Level Metrics, Technical Deliverables, and KPP Goals
Moderate impact to achievement of Subsonic Transport System Level Metrics, Technical Deliverables, and KPP Goals
Some impact to achievement of Subsonic Transport System Level Metrics, Technical Deliverables, and KPP Goals
Minor impact to achievement of Subsonic Transport System Level Metrics, Technical Deliverables, and KPP Goals
Negligible or no impact to achievement of Subsonic Transport System Level Metrics, Technical Deliverables, and KPP Goals
Contingency Solutions
No Acceptable Alternatives
Some Possible Alternatives
Single Acceptable Alternative
A Few Known Alternatives
Several Acceptable Alternatives
Reliability Factor Reliability May Not Be Increased
Fairly Confident Reliability Will Increase Somewhat
Highly Confident Reliability Will Increase Somewhat
Fairly Confident Reliability Will Increase Significantly
Highly Confident Reliability Will Increase Significantly
Considerations
Con
sid
era
tion
s
14
ERA Project’s Risk Assessment Approach
• ERA has applied a tailored continuous risk management process that enable risk- informed decision making– For Phase 1 Portfolio (FY10-12)– For Phase 2 Portfolio Development in FY12 for authorization to proceed through a
Key Decision Point R(KDP) Review Process
• Risk Management Process defined:– Risk Factors for technical, cost and schedule– Consequence and Likelihood Definitions and Scoring– Parent-Child Risk Construct– ERA Project Risk Reporting– ERA Risk Factor Weighting
• Current Phase 1 Portfolio• Assessment of Phase 2 Portfolio Opportunities
15
ERA Project Phase 1 Portfolio Continuous Risk Management Process
• Risk Factors:– Technical Risk
• Industry/OGA contributions• Technical Complexity (Test Article, Experiment/Test)• Technical Benefit /System Impact
– Cost Risk:• Workplan cost estimate maturity/fidelity• Technical Complexity• Workplan resource availability• Acquisition/Procurement cost • Industry/OGA collaboration dependency
– Schedule Risk:• Workplan maturity/WBS fidelity• Technical Complexity• Workforce resource availability• Facility/Flight test asset availability• Acquisition/Procurement schedule • Industry/OGA collaboration dependency
16
ERA Risk Consequence Criteria
Rating Value
ERA Risk Ratings Consequences
Technical Cost ScheduleDecision/
NotificationCommunication
5Major impact to achievement of
Subsonic Transport System Level Metrics, Technical Deliverables,
and KPP Goals
Greater than 20% increase over that
allocated budget (Sub-Project, Element or
Task level)
Level 1 (APGs) any impact
Level 2 Milestone(s):< 1 month impact
Level 3,4 Milestone(s): ≤ 1 month impact
Integrated Systems Research
Program (ISRP) & Centers
Aeronautics Research Mission
Directorate
4Moderate impact to achievement of Subsonic Transport System Level Metrics, Technical Deliverables,
and KPP Goals
Between 15% and 20% increase over allocated budget (Sub-Project,
Element or Task level)
Level 2 Milestone(s):< 1 month impact
Level 3,4 Milestone(s): ≤ 1 month impact
ERA Project Management
(PM)ISRP & Centers
3Some impact to achievement of
Subsonic Transport System Level Metrics, Technical Deliverables,
and KPP Goals
Between 10% and 15% increase over allocated budget (Sub-Project,
Element or Task level)
Level 2 Milestone(s):< 1 month impact
Level 3,4 Milestone(s): ≤ 1 month impact
ERA PM Centers
2Minor impact to achievement of
Subsonic Transport System Level Metrics, Technical Deliverables,
and KPP Goals
Between 5% and 10% increase over allocated budget (Sub-Project,
Element or Task level)
Level 2 Milestone(s):< 1 month impact
Level 3,4 Milestone(s): ≤ 1 month impact
ERA Sub-Project
Managers (SPM)
ERA Project Manger (PM)/ Deputy PM
(DPM)
1Negligible or no impact to
achievement of Subsonic Transport System Level Metrics, Technical
Deliverables, and KPP Goals
Between 0% and 5% increase over allocated budget (Sub-Project,
Element or Task level)
Level 2 Milestone(s):< 1 month impact
Level 3,4 Milestone(s): ≤ 1 month impact
SPM DPM, Element & Task Leads
Cost and Schedule easy to quantify and assess.
Challenge to define Negligible, Minor, Moderate, and Major impact
17
ERA Project Phase 1 Portfolio Continuous Risk Management Process• Consequence Elements:
– Technical Risk• Achievement of Subsonic Transport System Level Metrics, • Technical Deliverables, • Key Performance Parameters (KPPs)
– Technical Challenges– TRL Maturation– Technology/Product Transition Roadmap
– Cost Risk :• % increase over that allocated budget (Sub-Project, Element or Task level)
– Schedule Risk:• Level 1 Milestones: ISRP Program Level• Level 2 Milestones: Project Level• Level 3,4 Milestones: Sub-Project and Task Level
18
ERA Project Phase 1 Portfolio Continuous Risk Management Process• Likelihood Criteria may be defined in either Generalist terms or Probabilistic
terms:• Generalist: Improbable Unlikely May Likely Very Likely• Probabilistic: % or occurrence, Probability distribution (i.e. 10-5), etc.
19
ERA Parent and Child Risks
• All identified project risks start as Child Risks. Risks that apply to project level metrics are then elevated to the Parent level and are then managed by the Risk Management Board.– Child risks reported to Risk Management board, votes to make the risk a parent
based on the risks assessment at the project level.– Allows risk owner at the sub-project, element or task level to assess the risk in terms
of their approved plan.– Allows ERA project management to assess the risk at the project level where they
have a better understanding of the entire project • Preventing filtering or tweaking of the risk at the sub-project/element/task level.
WBS Parent Parent Risk TrendID # Open Date Risk Title Risk Statement L C Affinity Group Owner
1.00 PM Y ERA Schedule and Resources
5 68 14-Sep-11 ERA Schedule and Resources
Given the high cost and schedule uncertainty inherent to technology development projects, there is a possibility that planned funding and schedules will not support meeting ERA goals.
4 3Schedule (3)
Cost (3) Fay CollierTim Warner
3.0.0, 3.1.3, 3.3.4,
PT N ERA Schedule and Resources g
6 15-Jun-11 Shared Personnel & Services at GRC Facilities
Given that the large wind tunnel facilities at GRC share personnel and services, there is a possibility of schedule conflicts arising between ERA and other test programs (e.g., FAP: SUP, FAP: HYP), resulting in potential ERA propulsion test schedule slips.
5 3Schedule (3)
Cost (3) Ken Suder
1.00 PM N ERA Schedule and Resources g
24 15-Jun-11 Continuing Resolutions
Given the expectation for Continuing Resolutions during FY12, there is possibility that ERA technology development activities will be delayed, resulting in schedule slips and loss of productivity
5 3Technical (3)
Cost (3)Schedule (3)
Fay Collier
20
ERA Risk ReportingRank Trend
Risk ID #
Affinity GroupApproach(M,W,A,R)
Risk Title
1 h 11Cost (5)
Schedule (5)Technical (5)
M
Discrete Roughness Elements Laminar Flow Glove Experiment
(DRE) Programmatic Planning and Control
2 h 13Cost (3)
Schedule (5)W
Pultruded Rod Stitched Efficient Unitized Structure (PRSEUS) Programmatic Estimates and
Control
3 g 65Technical (5)Schedule (5)
M Combustor Development and Test
4 g 66 Technical (5) MUHB Geared Turbo Fan Engine
Development Noise Characteristics
5 g 76 Schedule (5) RERA Key Decision Point (KDP)
Schedule
6 5 77 Schedule (5) RFlow Control Experiment for AFC
Rudder
7 g 68Schedule (3)
Cost (3)A ERA Schedule and Resources
8 g 69 Technical (3) M ERA Technical Challenges
9 i 67 Technical (3) R
Insufficient Resources to Mature Vehicles Concepts and Associated
Technologies to Simultaneously meet ERA Goals
10 i 64 Schedule (5) WHybrid Wing Body (HWB)
Community Noise Assessment
Risk Matrix
LIKELIHOOD
5 11,13
4 68, 69
3 . . . . . . . 65,66,76,77
2 . .67
. . . . . . .
1 64
1 2 3 4 5
CONSEQUENCE
Note: The numbers on the risk matrix refer to the Risk ID numbers.
Approach
M - Mitigate
W - Watch
A - Accept
R - Research
Med
High
Low
CriticalityL x C Trend
Decreasing (Improving)
Increasing (Worsening)
Unchanged
New Since Last Period
Project “Parent” Risks
Denotes assessment and number of “Child” risks.
21
ERA Project Phase 1 Portfolio Weighting of RiskTranslating Child to Parent Risks
ERA WBS MatrixTitle
Sub-project Resource
Level Milestone Milestone
02.01.4
Demonstrate low-weight, damage-tolerant stitched composite structural concept on curved panel subjected to combined tension and internal pressure loads.(COLTS Large Scale Pressurized Fuselage Test Complete) (Proposed FY12 APG)Complete
AT 1
Complete Noise Transmission Assessment of PRSEUS panels
Milestone Deliverable KPPKPP Goal APG
Technical Challenge
Technical Maturation
Subsonic Transport System Level Metric
Technical Deliverable and Validation Method Cost Weight
Report development of predictive noise transmission models for like structural concepts
N/A N/A Yes N/A .75
ERA Risk Assessment Matrix
Very Low Low Medium High Very High5 10 16 20 23 254 7 13 18 22 243 4 9 15 19 212 2 6 11 14 171 1 3 5 8 12
1 2 3 4 5
Very Low Low Medium High Very High5 8 12 15 17 194 5 10 14 17 183 3 7 11 14 162 2 5 8 11 131 1 2 4 6 9 1 2 3 4 5
Weighted table, based on WBS task weight. *Values rounded
In this example, if this risk was assessed at a Likelihood of 4 and Consequence of 5 by the task lead. LxC: 4 x 5. The risk would be scored at 24, red, at the ERA project level. By creating the weighting factor to reflect the task’s contribution to ERA goals, the risk would be scored at LxC: 4x3 as the likelihood would not change, only the potential consequence. This allows the task lead to asses the risk based on their understanding of their task and creates a tool for the ERA risk manager a quantifiable and traceable method to accurate assess task risks and communicate at the project level.
ERA Project Phase 2 Portfolio Selection Criteria – Risk Posture
22
RISK
Cost Risk Score (1/3 weighting) Schedule Risk Score (1/3 weighting)Technical Risk Score (1/3
weighting)
WorkforceAvailability
Industry
Component
Procur-ement
Facility Availabil
ity
ITD Comple
xity
Industry Compon
ent
Procure-ment
WorkforceAvailability
Facility Availabi
lity
ITD Comple
xity
Technical
Benefit
ITD Complexity
Industry Compon
ent
Cum Score
(Weightin
g)10% 25% 10% 20% 35% 25% 10% 15% 20% 30% 25% 35% 40% 100%
ITD #1 Low Low Low Low Low High High High High High High High High 4.8
ITD #2 Low Low Low Low Low Low Low Low Low Low Low Low Low 5.0
ITD #3
Medium
High High High High Low Low Low Low Low Low Low Low 2.8
ITD #4 Low Low Low Low Low Low Low Low Low Low Low Low Low 4.6
ITD#5 High High
Medium
Medium
Medium
Low Low Low Low Low Low Low Low 2.5
ITD#6 High
Medium
Low Low Low Low Low Low Low Low Low Low Low 2.7
ITD#7 Low Low Low Low Low
Medium
Medium MediumMediu
mMediu
mMedium
Medium
Medium 5.0
ITD#8 Low Low Low Low Low Low Low Low Low Low Low Low Low 4.4
ITD#9
Medium
Low Low Low Low Low Low Low Low Low Low Low Low 4.2
ITD#10 Low Low
Medium
MediumMediu
mLow Low Low Low Low Low Low Low 3.9
• Example of Risk scoring• Supporting rationale will be developed for each Low, Medium or High score
Low = 5, Medium = 3, High = 1
23
Concluding Remarks
Opening Question: • What is the appropriate risk management construct for an Aeronautics
Technology Development Project responsible for maturing airframe and
propulsion technologies from TRL 3 to 5/6 through Integrated Systems
Research?
Lessons Learned to date:• Tailoring Risk Management Processes to Aeronautics Integrated Systems Research
Technology Development poses different challenges than spaceflight development
• The technology landscape is constantly changing with new technologies coming online promising increased performance. Risk assessment must weigh the promise of new performance against the confidence of what has been done before
• The realization of a risk is not failure, the knowledge gained identifies new foci for integrated systems research to continue the technology’s maturation path to enable technology transition into an aircraft system.
• These considerations do not require us to change the Project’s likelihood and consequence risk criteria but consider the lens through which we view these scales
24
Questions?
• Douglas Brown, ERA Risk [email protected]
757.864.3515
LaRC
• Gaudy Bezos-O’Connor, ERA Deputy Project [email protected]
757-864-5083
LaRC
• Steven Hirshorn, Integrated Systems Research Program Systems Engineering & Integration Manager
202.358.0775
HQ
25