25
Ignalina NPP decommissioning activities are co-financed by European Union Saulius Urbonavičius Senior Advisor to General Director Ignalina Nuclear Power Plant 25 May, 2012 IGNALINA NPP DECOMMISSIONING

Gynybos atase vizitas

Embed Size (px)

Citation preview

Page 1: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union

Saulius UrbonavičiusSenior Advisor to General Director

Ignalina Nuclear Power Plant25 May, 2012

IGNALINA NPP DECOMMISSIONING

Page 2: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union

Introduction

• December 31, 2009: change of INPP core activity

INPP was acting as nuclear power plant operator.

December 31, 2009 Unit 2 reactor was shut down.

Main INPP activity has been changed to decommissioning organization.

December 31, 2009: change of INPP core activity

Page 3: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union

accumulated expertise and know-how of RBMK technology – key prequalification for successful RBMK type plant decommissioning

1974 Preparations started for construction of INPP 1983 Unit 1, 1987 Unit 2 commissioned Originally 4 RBMK-1500 reactors planned ~ 6000 staff employed (1989) In 27 years 308 bln kWh of electricity INPP specialists were the first to start using the enriched fuel with burnable

absorber – erbium Unique project of Unit 1 nuclear fuel reuse in Unit 2 reactor implemented 1st time

in operation history of nuclear reactors Other unique technology improvements & modifications

Successful operation of INPP

Page 4: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union

Defuelling (constrained by delays in ISFSF completion)

• Unit 1: − core fully defuelled− fuel in pools

• Unit 2: − 356 assemblies removed in 2011

(1278 still left in core)− 144 assemblies are to be removed by September 2012 core in non-criticality state

(important safety advance)− fuel in pools

Decommissioning Status & Progress in 2012

Page 5: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union

Decommissioning status & progress in 2012

Dismantling & Decontamination (D&D) Unit 1

− Emergency Core Cooling System tanks (Bldg. 117/1): completed

− Turbine hall (Block G1): ongoing − Reactor gas circuit (Block V1): starts in 2012 − Heat Station (Bldg. 119): ongoing− Main circuit decontamination: discontinued (illustrates pioneering nature of RBMK decommissioning)

ECCS tanks sectioned and removed from Bldg.117/1

Ongoing equipment dismantling in Unit 1 Turbine Hall

All pumps removed from Heat Station (Bldg. 119)

Page 6: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union

Decommissioning status & progress in 2012

D&D Engineering planning (now performed by INPP own staff)

Unit 2: − ECCS Tanks (Building 117/2)

- Environmental Impact Assessment Report is under development - 80% completed.

- Inventory and radiological characterization completed. - Isolation of the systems is in progress.

− Turbine Hall (Block G2)- Inventory of equipment, radiological characterization and system isolation

are in progress.

Development of D&D documentation for other buildings and facilities is in progress.

Page 7: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union

Decommissioning status & progress in 2012

D&D Engineering planning (performed by INPP own staff)

Dismantling in Reactor Shafts

21m

25m

R1R1

R2R2

R3R3

Simplified schematic

Division into 3 D&D areas

•R1 & R2– maintenance experience– available access– limited set of materials – low/no irradiation

(excl. channels / some internals)

•R3– Minor experience– no access – variety of materials– irradiation

INPP internal project UP01

Serpentinite

Concrete

Sand

Water

Graphite

Steel blocks

Metal structure

Support plates

Top cover

Metal structure

Page 8: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union

Decommissioning status & progress in 2012

D&D Engineering planning (performed by INPP own staff)

Dismantling in Reactor Shafts

INPP internal project UP01

Example borehole for sand sampling

Page 9: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union

Decommissioning status & progress in 2012

D&D Engineering planning (performed by INPP own staff)

Dismantling in Reactor Shafts

INPP internal project UP01

Pilot vacuum sampling of serpentinite Jan. 2012

Preparation of trepanning tool for graphite sampling Feb. 2012

Page 10: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union

STORED WASTE END 2009Stored Fuel => 6000 assembliesStored SW => 27000 m3Bituminized waste => 14000 m3 Waste to be cemented => 4000 m3

INPP waste management overview

INPP Site

DECOMMISSIONING

Fuel => 16000 assembliesEquipment => 130000 tons of steelReactors => 10000 tons of steel

=> 3800 tons graphite => 11000 tons fillingBuildings => 1000000 m3 of concrete

=> 200000 tons of steel

Page 11: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union

Dismantling Wastes

Operational Wastes

Opening waste routes

VLLW Landfill

BufferStorage

B19-1

B19-2

Measurement Facility

Free Release

B10

Interim Spent Fuel Storage(s)

B1

B20B2

Waste Retrieval

BituminisedWaste

Near Surface Repository

SW Processing& Storage

B25

B3B4

Testing Operating

Under design

Design complete

Delayed5 yrs

Delayed4 yrs

Delayed4 yrs

Page 12: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union

B1 Interim Spent Fuel Storage Facility

CONTRACT SIGNED12 January 2005 with GNS-NUKEM consortium

COMPLETION DATEOriginal contract 04 / 06 / 2009Current amendment 29 / 03 / 2011Delay 44 months

The new ISFSF will occupy 5, 93 hectare.

The total capacity of the Facility is about 17000 fuel assemblies (about 190 containers).

Page 13: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union

B1 Interim Spent Fuel Storage FacilityStatus

1. Storage building construction 80 % of construction works complete; 30 % equipment installation complete.

2. Manufacture of new-type casks 146 of 190 casks manufactured

Page 14: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union

B1 Interim Spent Fuel Storage FacilityStatus

1. Storage building construction 80 % of construction works complete; 30 % equipment installation complete.

2. Manufacture of new-type casks 146 of 190 casks manufactured

3. Modification to in-unit cask handling works currently suspended by the Contractor

Main outstanding issues Independent report has confirmed INPP’s concerns regarding

safety of using existing spent fuel pool hall cranes, shock absorbers and fuel characterization

INPP has raised issue with Contractor of cask conformity with technical design developed by the Contractor

INPP and Contractor are jointly working on resolution of outstanding issues now

Page 15: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union

B2/3/4 Radwaste Storage and Management Facilities

CONTRACT SIGNED30 November 2005 With NUKEM Technologies GmbH

COMPLETION DATEOriginal contract 28 / 11 / 2009Delay B2: 54 months

B3/4: 47 months

Radioactive waste retrieval from the existing interim storage facilities

Transportation of them to the new build facilites

Waste sorting and its compliance with the new classification system

Waste processing (fragmentation, incineration, compaction)

Packaging of the processed waste to the containers and placing them to the new storage facilities for their interim storage in expectation of construction of the final landfill facilities (storage period up to 50 years)

B3/4B3/4

Page 16: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union

B10 Free Release Measurement Facility

COMMISSIONED August 2010

These facilities will ensure centralized identification of the radionuclide contamination level of materials generated during dismantling of the nuclear power plant.

If the radionuclide contamination of the materials does not exceed the free release levels, these materials will be transported to the conventional dump or reused without application of the radiation safety requirements.

Page 17: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union

B19 Landfill Facility For Short-Lived Very Low Waste

COMPLETION DATE 2014 (disposal modules)

The Landfill Facility will consist of the following facilities:

4000 m3 capacity Buffer Storage Facility (Project B19-1) which operation is due to first half of 2012;

3 Disposal Modules (Project B19-2) with capacity of 20000 m3 each. They are planned to be installed near the currently built new Spent Fuel Storage Facility (Project B1).

Buffer Storage Facility

Landfill

Page 18: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union

The repository will consist of several groups of sections designed for final disposal of 100 000 m3 of treated radioactive waste packed into concrete containers and immobilized in the cement matrix.

The repository, its protection areas and auxiliary buildings will occupy the area equal to approximately 40 hectares.

COMPLETION DATE 2017 (first module)

B25 Near Surface Repository

Radioactive waste will be stored in the repository approximately until 2029, until INPP is completely dismantled and treatment of all radioactive waste is finished.

Upon completion of radioactive waste disposal the repository will be closed.

Surveillance of the repository will be carried out for at least 300 years.

Page 19: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union

Comparison with Greifswald NPP

Operational Solid Waste (to be retrieved and managed)

Operational Spent Resins (for cementation)

30,000 m3

15,000 m3

5,800 m3

2,000 m3

Steel from Equipt. Dismantling contaminated

59%

91%130,000 tons

116,000 tons

Steel

Steel Graphite Shielding ( serpentine / sand ) 9,300 tons2,700 t

Reactor Core Structures(per unit)

3.2 billion Euro

2,660 tons

1,800 t 4,800 t

Greifswald NPP2640 MW (VVER) 1500

Ignalina NPP3000 MW (RBMK)

Decommissioning Funding

440 440440 440 440 1500

1.45 billion Euro 2.93 billion EuroIdentified Required (incl. risks)

Page 20: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union 20

The EU assistance by 2014

In accordance with its commitments, the EU has already allocated a contribution of 1 400 m Euro until 2014 and Lithuania has already allocated 50 m Euro. This financing is intended to be used:

1 100 m Euro for the preparatory decommissioning works – construction of a spent nuclear fuel storage facility, radioactive waste management and storage facilities and repositories.

350 m Euro for funding of strategic energy projects.

Decommissioning funding 2014-2020

Page 21: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union 21

The EU assistance in 2014-2020

In order to ensure proper funding of Ignalina NPP decommissioning process until 2029, 1 120 m Euro should be allocated additionally. In consideration of Lithuanian contribution, additional EU financial support is required (including risk provisions for investment projects) of which:

770 m Euro for the period from 2014 to 2020

exclusively to ensure adequate financing of the decommissioning process until 2029.

Decommissioning funding 2014-2020

Page 22: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union 22

Lithuania’s contribution

Lithuania’s national contribution to the financing of decommissioning process from 1999 to 2029 will compose about 320 m Euro (12%):

188 m Euro are planned for the period until 2014.

132 m Euro are planned for the period from 2014 to 2029.

Decommissioning funding 2014-2020

Page 23: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union

2014-2017 the Ignalina Programme will receive only 210 MEUR (229 629 000 EUR in current prices)

23

Decommissioning funding 2014-2020

Page 24: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union

Possible outcomes of unsufficient funding

Lithuania alone will not be able to provide necessary support for INPP decommissioning.

Long-lasting INPP decommissioning process may require higher amount of resources.

Furthermore, insufficient financing may cause the risk that in the EU large quantities of spent nuclear fuel and radioactive waste will not be properly managed (nuclear safety issue).

24

Page 25: Gynybos atase vizitas

Ignalina NPP decommissioning activities are co-financed by European Union

Thank you!

Thank You for Your Attention !