Software Project Management
-Web server development-
Ioana Jivet, CTI, 4th year
Goal: develop a web server, along with a Graphical User Interface
Maximum duration: 1 month
Human resources: Team leader: Mihai Analysts: Andreea, Vlad Developers: Mihai, Cristina Testers: Mihai, Cristina
Project overview
1. Requirements analysis – client meetings 2. System’s architectural design 3. Implementation 4. Testing 5. Delivery
Project phases
Project phases
Phase 1 – Requirements analysis
The requirements analysis phases includes gathering information from the clients, along with the definition of use case scenarios. A sub-phase represents the design of the architecture of the system.
Total time allocated: 9 days Assigned human resources: Andreea and Vlad
Phase 2 - Implementation
This phases consists of two sub-phases◦ 1. Back-end development and testing◦ 2. Front-end (GUI) development and testing
Before the 2nd milestone is reached, the integration of the two modules is done.
Total time allocated: 6 days Assigned human resources: Cristina and
Mihai
Phase 2 - Implementation
Phase 3 - Testing
Four types of testing and a final bug report
Total time allocated: 3.5 days Assigned human resources: Cristina and
Mihai
Phase 4 - Delivery
Delivery consists of two tasks: developing the install package and finalizing the documentation.
Total time allocated: 2 days Assigned human resources: Andreea and Vlad
Project timeline
Working calendar: 8:00 – 17:00, Mo-Fr; Sa and Su are free.
Total of working hours:
Working hours
Open Proj is an easy to use project management software.
This tools allows you to rapidly define tasks, task flow, allocate resources and estimate completion time and costs.
Conclusions