Electrical UpgradeElectrical Upgrade• The project objective was the reform of
electrical infrastructure of the Diosynth site in Barueri - SP; to meet the actual law requirements; provide electrical power to the site and new production cells with a reliable and safe electricity distribution. The project was implemented in two phases.
Electrical UpgradeElectrical Upgrade• Phase1:
• Construction of SE-01; new power feed to the site.• Construction of SE-02; to power “the upper side” of the
site.• Feed SE-02 from SE-01.• Dismantle of PMV-1, replaced by Switchgear-2• Feed PMV-2 (existing mv switchgear); to power “the
lower side” and utilities of the site.
• Phase2:• SE-01 finalization with installation of a 750kva generator
to power the whole site• Dismantle of PMV-2, replaced by Switchgear-1• Commissioning of site energy consumption system
Electrical UpgradeElectrical UpgradeProject Functional Chart
GESManagercorporate
Procurement
SafetySupervisor
DocumentControl
MechanicalTechnician
Cost ControlCash Flow
PlanningEngineer
JJEngineeringConsulting
SHEDirectorcorporate
SHEManager
E&I Technician
SafetyTechnician
ElectricalEngineer
AssemblyTeam
CivilEngineer
PlanningTechnician
GES ProjectSupport
corporate
SafetyTechnician
Electrical UpgradeElectrical UpgradeNew MV-Switchgear and MCC
wwtp & evaporator mcc’s
MV-Switchgear as per IEC 60529 MCC’s as per IEC 60439-1 and IEC / TR 61641
Site Master Plan
Electrical UpgradeElectrical Upgrade
OriginalSub-station 2
(13.8KV to 380V)
Sub-station 1(13.8KV to 380V)
EletropauloSupply (13.8KV)
PrimarySub-station
Phase 1New EletropauloSupply (13.8KV)
New PrimarySub-station
Phase 2
Emergency Gen.Site Consup. Mng
Site Electrically Balanced
New SecondarySub-station 2